|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #5
Posted: November 23, 2005
We continue to make progress on a
number of tasks related to both temporary and permanent repairs to the
campus facilities. In our work with the State’s Office of Facility
Planning & Control and Office of Risk Management, FEMA and the LSU Systems
Office we have agreed upon strategies designed to re-open the upper floors
of the three primary research buildings as early as possible (MEB, CSRB, &
Lions Eye Center).
This approach will involve "sealing
off" the 1st floors (where mold and other environmental issues
remain to be addressed through the major repair/renovation projects) and
cleaning of the upper floors. It will also require getting key building
systems repaired or replaced (fire pump systems, switchgear, domestic
water pumps, etc.) so that the buildings can be occupied. Much of this
work is already underway. (Details are contained in the list of highlights
at the end of this document.)
Key animal care space to support
research on the downtown campus was located on the 1st floors
of two of the three research buildings (MEB and CSRB) and these spaces
cannot be rapidly renovated. Alternatives for providing temporary animal
care facilities including the use of the CSRB 2nd floor
facilities and temporary modular facilities are being explored. Temporary
modular animal care facilities have recently been used at Texas A&M, are
currently in use at Univ. of Virginia and are planned for use at Univ. of
Cal-Davis during major building renovation projects. The availability of 2nd
floor access via the pedestrian walkways will be a significant advantage
to us as we press towards this goal, as it will allow employees to enter
and exit the buildings without going through the un-remediated 1st
floor spaces.
In the 10/28/05 update, we also shared
the general pattern that we anticipate following for completing the major
building repairs. Here is a summary of that pattern and recent notes on
progress:
- Architect Selection.
OFPC is using an expedited process to select architect(s).
- NOTE: The State’s Architect Selection Board met
on 11/21/05 to consider proposals for the two LSUHSC-NO major
repair/renovation projects; one for the downtown campus and one for
the Dental School. The downtown campus project was awarded to the firm
of Duplantier & Meric, while the Board deferred a decision on the
award of the Dental School project until their meeting of 12/13/05.
- Develop Bid Package(s) For
Building Repair
.
The architect(s) selected will begin developing the bid packages for the
repairs needed in each building.
- Develop Environmental Remediation
Plans and Specifications.
Concurrent
with the above, the selected architect(s) will also develop plans and
specifications for the work needed to perform any environmental
remediation in the flood damaged buildings.
- Bid and Award Contract(s).
The bid packages for building repairs and the plans/specifications for
the environmental remediation will be advertised, bids received, and the
contracts awarded.
- Construction, Repair &
Remediation.
The contractor(s)
selected will complete the repairs required. The environmental
remediation work will also be completed during this phase.
- Final Inspections.
As a contractor completes the work for a building, the final inspections
will be scheduled and completed.
During the first town hall meeting held
at Pennington Biomedical Research Center, some questions regarding the
status of the campus residence halls were raised. The Residence Hall and
Stanislaus Hall are the two buildings in which students have been housed
in the past. Both were impacted by the flood waters, as were all the
buildings on campus. The following is a brief summary of their current
status:
- The Residence hall currently has 22 vacant
apartments (1, 2 & 3 bedroom) and 7 vacant dorm rooms. Three units
require some minor renovations (not storm related). The Residence Hall
does not have a true 1st floor, so major building renovations
due to the flood are not expected to be necessary as they will be in
other buildings. However all the major building systems (fire pumps,
switchgear, etc.) were located on the 1st level, so repairs
or replacements are already underway on those systems.
- One of the two domestic water pumps has been
replaced and the 2nd is to be removed and sent to be
rebuilt shortly.
- The contract to repair/replace the switchgear
has been issued to Fisk Electric.
- The fire pump controller panel was repaired on
11/7.
- All of the refrigerators have been removed from
the rooms and the major cleaning of the kitchens & baths in the
facility has been completed.
- Some temporary elevator repairs have been made
and parts for permanent repairs are being ordered by the elevator
maintenance contractor.
- Stanislaus Hall currently has 70 dorm suites
vacant. The building also has a more traditional 1st floor
configuration and is one of the three LSUHSC-NO buildings with a
basement. The lower floors in the building were being renovated to
accommodate the Wellness Center and the Daycare Center. The dormitory
living was limited to the upper floors and that space was basically
undamaged. Like most other buildings, the major building systems were
located in the basement and were fully immersed in floor waters for many
days.
- All of the refrigerators have been removed from
the rooms and the major cleaning of the kitchens & baths in the
facility has been completed.
- A contract that includes the repair/replacement
of city water pumps and sump pumps is out for bid now.
- A contract to remove flood-damaged furniture
and equipment from basements and 1st floor campus spaces
has been awarded and work is well underway.
- A contract to remove flood-damaged carpeting
and other semi-porous building materials from basements and 1st
floor campus spaces is out for bid. Some temporary elevator repairs
have been made and parts for permanent repairs are being ordered by
the elevator maintenance contractor.
Here are highlights of work that has
been accomplished since our update posted on Friday, November 11th.
- The contract with the architectural/engineering
firms to assess the damage to the campus buildings is coming to a close,
as they work to complete the extensive written documentation and
photographic evidence of the damage to campus buildings. Negotiations
are underway to amend the contract to provide for the design of plans to
environmentally seal off the 1st floors of the MEB, CSRB, and
Lions Eye Center buildings, in hopes of expediting re-occupancy of the
upper floors.
- The assessment of the damage to elevators across
the campus continues. Repair parts are beginning to arrive. As they do,
the permanent repairs to individual elevators will begin. The
contractors have continued to assist in making temporary repairs to get
selected elevators in buildings operating.
- Implementation of the plans for providing
temporary housing in Baton Rouge for students, faculty and staff
continue to progress. Room assignments on the FinnJet ship continue
being made for faculty and staff as requests for rooms are received. We
have received all of the 110 house trailers that were ordered and all
but approximately 10 have been connected to utilities and passed
inspection. The assignment of trailers has continued as they have been
turned over to the institution.
- A new contract is being bid to clean various
portions of the Dental School Administration and Clinic Buildings.
- Movable equipment and furnishings in basements
and 1st floors has been assessed by LSUHSC staff and work
under the contract for the removal and disposal of the items that are
not salvageable continues. Work has been completed at the Resource
Center, the Lions Eye Center, the CSRB, the Nursing/Allied Health Bldg.,
the Auxiliary Enterprises warehouse, HDC Library and HDC 124, and the
Medical Education Bldg. Rapid progress continues.
- Work on the permanent repair/rebuilding of
domestic water pumps in the Resource Center, Residence Hall, and MEB
continues. The 1st pump removed from the Residence Hall has
been rebuilt and installed. The remaining (backup) pumps from the
Resource Center, Residence Hall and MEB have now been removed and have
been sent to be rebuilt.
- The re-circulating pump at the MEB has been
rebuilt and reinstalled.
- The bid solicitation for the emergency removal
and disposal of carpet, wall board, and other porous & semi-porous
materials from basements & 1st floors to prevent further spread of mold
was released on 11/3/05. Addenda to the solicitation were issued to
answer a number of questions that arose out of the pre-bid conference
and responses are now due on 11/28/05.
- A bid solicitation to make permanent repairs to
the switchgear in the Residence Hall, CSRB, Lions Eye Center and
Nursing/Allied Health Buildings was awarded on 11/16/05 to Fisk
Electric.
- Permanent repairs to the MEB switchgear are in
progress and power has been restored to most of the building, except for
one quadrant. LSUHSC Facilities staff are now testing various circuits
throughout the building.
- Permanent repairs to the switchgear at the
Resource Center were completed on 11/16/05.
- The State of Louisiana Architect Selection Board
awarded the design contract for the major repairs/renovations to the
downtown campus buildings to the firm of Duplantier & Meric at the
meeting of 11/21/05. The award of the contract for the Dental School
campus was deferred to the Board’s meeting of 12/13/05.
- A bid solicitation has been issued on 11/10/05 to
make permanent repairs to various types of pumps to supply water and
heat to the Residence Hall, MEB, CSRB, Lions Eye Center, Nursing/Allied
Health, and Resource Center. One addendum has been issued and responses
are due on 11/28/05.
- A bid solicitation for the permanent
refurbishment or replacement of fire pump systems in the Nursing/Allied
Health Bldg, the Residence Hall, the Resource Center, the CSRB, the
Lions Eye Center and the MEB has been issued. Responses are due to be
received on 12/2/2005.
- A small contract was awarded on 11/15 for the
repairs to the MEB boilers.
We trust that you continue to find this
information helpful. You may also want to read the Daily Updates posted on
the web site to received more frequent information on progress.
|