|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #12
Posted: March 11, 2006
Just over 6 months from landfall and less than 6 months since the flood
waters left our campus the return to New Orleans continues! We were
successful in reopening the upper floors of the Medical Education Building
and the Lion’s/LSU Clinic Building on Monday, March 6th as
planned. Researchers are moving back into their labs, research is
restarting, and work is now underway to meet the next major objectives in
the recovery effort.
Accelerated progress on repairs to
the elevators in the downtown campus buildings has continued. Now that
most of the parts required for the repairs have arrived, the additional
out of state crews dedicated to the LSUHSC repair work are expediting the
completion of this work. The repairs to the emergency power generators
that serve the downtown campus buildings are also underway at several of
the downtown campus buildings.
The architect/engineering firm
responsible for the Dental School campus completed their 1st
set of specifications for temporary repairs to key building systems;
specifically the temporary repairs to the building electrical systems.
Bids were received on March 10th and they are being evaluated
at this time. An award is expected to be made shortly.
Work on the initial environmental
remediation contract for the CSRB, MEB and Lion’s Eye Center has been
substantially completed. The punch list is being developed now. The 2nd
environmental remediation contract has now been awarded. Work crews are
expected to begin on Monday, March 13th in all four of the
buildings: the Residence Hall, Stanislaus Hall, the Nursing/Allied Health
Building and the Resource Center. Similar contracts will be issued at
later dates to address the Dental School Clinic and Administration
Buildings and 1542 Tulane Ave. and other smaller structures.
The following is a brief
description of the basic work that will be done by the environmental
remediation contractors:
-
The environmental remediation process provides for the demolition,
removal and disposal of building materials that were flooded or found to
harbor mold spores or other biological hazards. This is in addition to
all of the cleaning and disposal of flood damage materials that has
already been accomplished through earlier contracts.
-
The standard protocol for environmental remediation also provides for
the cleaning and disinfecting of the interior spaces; wiping down hard
surfaces (walls, doors, stairwells, light fixtures, ceilings, etc.),
vacuuming, etc. They will also be replacing filters, cleaning and
disinfecting the air handling unit coils and the interiors of air
handling units.
- On
the 1st floors or in basements where flood water was present,
the demolition will typically include removal of drywall to a height of
7 feet, floor coverings as needed (that were not previously removed by
an earlier contract), ceiling tiles as needed, etc. Removal of asbestos
tiles and the mastic is also included as necessary. Floors and solid
walls (masonry & granite) will be cored to determine if water penetrated
and remediation is required. Metal studs and other structural walls
will initially remain and be cleaned and disinfected. Many metal studs
will require replacement, but that will be done as part of the permanent
repairs. Before the demolition begins, the 1st floor spaces
will be sealed off to prevent migration of any contaminants that may
become airborne during the demolition.
-
When completed, the contract will provide us with unrestricted access to
the cleaned spaces in the upper floors, and spaces on the 1st
floors will be clean and ready for the permanent renovation work.
Here are highlights of work that
has been accomplished since our last update was posted on Friday, February
24th.
- The contract for the second
environmental remediation contract addressing the Nursing/Allied Health
Building, the Residence Hall, Stanislaus Hall and the Resource Center
has been awarded. Crews are scheduled to begin work at all four
locations on March 13th.
- Most of the repair parts for
elevators at the downtown campus have arrived and the permanent repairs
to individual elevators continue at an accelerated pace. Two of the
major elevator contractors have brought in additional manpower from out
of state to dedicate to completing repairs at the Health Sciences
Center. The elevator contractors continue their work at:
- CSRB
- MEB
- Lion’s Eye Center
- Nursing/Allied Health
- Resource Center (two have
been certified for use)
- Stanislaus Hall (work
completed on all 4 elevators, and the inspection will be requested
shortly)
- Residence Hall
- Entergy/Gravier St. Garage
Until
permanent repairs are completed and elevators certified by the State
Elevator Inspector, routine use has been discontinued. Restricting the
use of elevators in buildings where the environmental remediation has not
been completed will help to minimize further spreading of mold to upper
floors.
- Work has been completed under
the contract to make permanent repairs to the switchgear in the CSRB,
MEB, Lion’s Eye Center, Nursing/Allied Health Building and the Residence
Hall.
- School of Dentistry
restoration: Regular weekly meetings with representatives from the
architectural/engineering firms, the Office of Facility Planning &
Control, FEMA and LSUHSC have continued and will remain as a scheduled
item for some time.
- The architect/engineering
firm responsible for the Dental School campus has completed
specifications for temporary repairs to key building systems that,
when completed, will allow the re-occupancy of upper floors of the
Clinic and Administration buildings. The repairs will focus on the
building switch gear, chillers, key building pumps, clinic systems,
and safety systems. The architects are currently using an expedited
procurement process to secure contractors to complete this temporary
repair work.
- The 1st of the bid
packages for temporary repairs to building electrical systems at the
Dental School has been completed and bids were received on March 10th.
They are being evaluated and an award is anticipated shortly..
- Downtown campus restoration:
Regular weekly meetings with representatives from the
architectural/engineering firms, the Office of Facility Planning &
Control, FEMA and LSUHSC have continued and will remain as a scheduled
item for some time.
- The 2nd
environmental remediation contact has been awarded. It addresses the
Residence Hall, Stanislaus Hall, the Nursing/Allied Health Building,
and the Resource Center. Work will begin on all four buildings on
March 13th.
- Contracts have been awarded for
the repairs to various types of pumps to supply water and heat to the
Residence Hall, MEB, CSRB, Lion’s Eye Center, Nursing/Allied Health, and
Resource Center. Parts were ordered have begun to arrive on site.
LSUHSC has provided the contractors with the list of priorities by
building for these repairs; however the availability of some parts may
impact on the ability to strictly adhere to the priorities.
- Contracts to repair the fire
alarm systems and their components in downtown campus buildings have
been awarded to the vendors who currently provide annual maintenance to
the systems. This approach will insure that the systems can be
re-certified and remain under the existing maintenance contract.
Several of the systems have been repaired and inspected and work
continues in the remaining buildings.
- Stanislaus Hall: Completed
and inspected.
- CSRB: Completed and
inspected.
- MEB: Work has been started
and is scheduled to be completed in the near future.
- Lion’s Eye Center: Completed
and inspected.
- Nursing/Allied Health: The
contract has been awarded for the repairs to the fire alarm system.
Work is expected to being shortly as parts become available.
- Resource Center: The repairs
required for the fire alarm system have been identified and the
contract has been issued. Work will begin as parts arrive.
- A contract remains in place to
address the repairs to Animal Care cage washers, bottle washers and
sterilizers at the CSRB. The work on the repairs is almost complete.
The steam generators have been installed and the contract has begun
troubleshooting the systems. Additional damage to a pump in the system
has been discovered and a Change Order to the original contract has been
issued.
- The contract for the repairs to
the emergency generators at the CSRB, MEB, Lion’s Eye Center,
Nursing/Allied Health Bldg., Resource Center and the Residence Hall has
been awarded. Work has begun on several of the generators, and parts
are on order.
- A contract has been issued for
repairs to the medical air compressors, vacuum pumps and water purifiers
at the CSRB, Lion’s Eye Center and the MEB. Parts are on order and
repairs will begin as soon as the parts begin to arrive.
We hope that you continue to find
this information helpful. Don’t forget that Daily Updates are also posted
on the web site so that you can follow the recovery progress more
closely.
|