|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #13
Posted: March 28, 2006
LSU's stunning upset of #1 ranked Duke and overtime victory over #2 seed
Texas, reminds us that desire, determination, dedication and teamwork can
overcome significant challenges. Researchers are continuing to move
back into the Medical Education Building and the Lion’s/LSU Clinic
Building; both of which reopened on March 6th. Research is
underway, samples are coming back from their temporary sites, and people
are adjusting to some of the challenges of returning “home”. Much remains
to be done, but a great deal has been accomplished and we have much to be
proud of! Work is well underway to meet the next major objectives in the
recovery effort.
We remain optimistic that
Stanislaus Hall will be reopening soon as work on the environmental
remediation, elevator repairs and various building water pumps is
completed. Work continues on schedule in support of the projected
reopening of the Nursing/Allied Health in mid-April and food services will
soon be available in the MEB as the cafeteria is preparing to reopen and
begin operations. Though the environmental remediation work is more
involved and time consuming in the Residence Hall (due in large part to
the removal and replacement of a large number of damage floor tiles), it
is also projected to be reopened in the next month or so.
Progress on repairs to the
elevators in the downtown campus buildings has continued. Inspections of
repaired elevators are beginning to occur in the MEB, the Lion’s/LSU
Clinic Building, and Stanislaus Hall. The repairs to the emergency power
generators that serve the downtown campus buildings continue. The
generator on the roof of the MEB, which supplies emergency power to the
majority of the research freezers and walk in coolers, was restored to
normal operations recently. Repairs to the other building generators are
also underway.
The 2nd environmental
remediation contract for the downtown campus has now been awarded. Work
crews began on Monday, March 13th in all four of the buildings:
the Residence Hall, Stanislaus Hall, the Nursing/Allied Health Building
and the Resource Center. Work is progressing on schedule. The bid
specifications for a similar contract to address 1542 Tulane Ave. and
other smaller structures on the downtown campus have been completed and
prices are being solicited now.
The architect/engineering firm
responsible for the Dental School campus completed their 2nd
set of specifications for temporary repairs to key building systems and
prices are being solicited now. The contract for the temporary repairs to
the buildings’ electrical systems is expected to be awarded shortly.
Planning continues on the best approach to make permanent repairs and
prevent damage to critical building systems should a similar event ever
occur.
Here are highlights of work that
has been accomplished since our last update was posted on Friday, March 10th.
- The contract for the second
environmental remediation contract addressing the Nursing/Allied Health
Building, the Residence Hall, Stanislaus Hall and the Resource Center
has been awarded. Crews began work at all four locations on March 13th.
Progress by building follows:
- Residence Hall: All of the
damaged floor tiles will have been removed from all floors by
Saturday, March 25th.
- Stanislaus Hall: All of the
basic clean has been completed on every floor. Cleaning of the
stairwells and mechanical rooms is underway.
- Nursing/Allied Health: The
cleaning has been completed from the top floor down to the 8th
floor.
- Resource Center: All of the
floors have been cleaned.
- The accelerated pace of repairs
to building elevators continue. Inspections by the State Elevator
Inspector have been requested or will be requested shortly for the
passenger elevators at the MEB, the Lion’s/LSU Clinic Building and
Stanislaus Hall.
- Until permanent repairs
are completed and elevators certified by the State Elevator Inspector,
routine use has been discontinued. Restricting the use of elevators
in buildings where the environmental remediation has not been
completed will help to minimize further spreading of mold to upper
floors.
- School of Dentistry
restoration: Regular weekly meetings with representatives from the
architectural/engineering firms, the Office of Facility Planning &
Control, FEMA and LSUHSC have continued and will remain as a scheduled
item for some time.
- The architect/engineering
firm responsible for the Dental School campus has completed
specifications for temporary repairs to key building systems that,
when completed, will allow the re-occupancy of upper floors of the
Clinic and Administration buildings. The repairs will focus on the
building switch gear, chillers, key building pumps, clinic systems,
and safety systems. The architects continue to use an expedited
procurement process to secure contractors to complete this temporary
repair work.
- The 1st of the bid
packages for temporary repairs to building electrical systems and for
temporary air conditioning at the Dental School has been completed. An
award is anticipated shortly.
- The 2nd of the bid
packages for temporary repairs has been developed and the solicitation
of bids is underway. Bids are due to be returned late next week.
- Downtown campus restoration:
Regular weekly meetings with representatives from the
architectural/engineering firms, the Office of Facility Planning &
Control, FEMA and LSUHSC have continued and will remain as a scheduled
item for some time.
- The 2nd
environmental remediation contact has been awarded. It addresses the
Residence Hall, Stanislaus Hall, the Nursing/Allied Health Building,
and the Resource Center. Work began on all four buildings on March 13th
and is on schedule.
- The 3rd
environmental remediation contact specifications have been approved
and prices are being solicited now.
- The architects are working on
a series of smaller projects that have been “carved out” of the larger
permanent repair work to facilitate the return of the Medical School
classes to campus.
- Contracts have been awarded for
the repairs to various types of pumps to supply water and heat to the
Residence Hall, MEB, CSRB, Lion’s Eye Center, Nursing/Allied Health, and
Resource Center. Parts were ordered continue to arrive on site. LSUHSC
has provided the contractors with the list of priorities by building for
these repairs; however the availability of some parts may impact on the
ability to strictly adhere to the priorities.
- Contracts to repair the fire
alarm systems and their components in downtown campus buildings have
been awarded to the vendors who currently provide annual maintenance to
the systems. This approach will insure that the systems can be
re-certified and remain under the existing maintenance contract.
Several of the systems have been repaired and inspected and work
continues in the remaining buildings.
- Stanislaus Hall: Completed
and inspected.
- CSRB: Completed and
inspected.
- MEB: Completed and the
inspection has been scheduled.
- Lion’s Eye Center: Completed
and inspected.
- Nursing/Allied Health: The
contract has been awarded for the repairs to the fire alarm system.
Work is expected to being shortly as parts become available.
- Resource Center: The repairs
required for the fire alarm system have been identified and the
contract has been issued. Work will begin as parts arrive.
- The contract to make the needed
repairs to Animal Care cage washers, bottle washers and sterilizers at
the CSRB is substantially complete. Cages are being washed on the 1st
floor now.
- The contract for the repairs to
the emergency generators at the CSRB, MEB, Lion’s Eye Center,
Nursing/Allied Health Bldg., Resource Center and the Residence Hall has
been awarded. Work has begun on several of the generators, and parts
are on order.
- The repairs have been
completed on the roof mounted generator at the MEB. This provides
emergency power to the majority of the researchers freezers and walk
in coolers in that building.
- A contract has been issued for
repairs to the medical air compressors, vacuum pumps and water purifiers
at the CSRB, Lion’s Eye Center and the MEB. Parts are on order and
repairs will begin as soon as the parts begin to arrive.
- Work under a contract to clean,
decontaminate and re-certify the biosafety cabinets in research labs
began on March 15th. There are 100 cabinets covered under
the contract.
- The library collection has been
removed from the Resource Center in preparation for the environmental
remediation contractor. The collection is being cleaned and will be
returned and re-shelved when the remediation has been completed.
- Repairs to the boilers at the
MEB are substantially completed. Both are on line and operating, but
some additional work remains to be done to the electronic controllers.
- The core switch at the CSRB has
been replaced and full Internet access is available due to the efforts
of the School of Medicine’s PC Supporters in patching and updating all
of the machines.
- Similarly, full Internet access
is now available on Floors 5-7 in the MEB as the School of Medicine PC
Supporters completing the patching and updating of machines on those
floors as well.
- Claims for the building content
losses are being prepared and submitted to FEMA, ORM and the Office of
Facility Planning & Control. Initial submissions include:
- All movable property
(capitalized assets) that was lost due to flooding in basement spaces
and on 1st floors. (Over $5 million in losses in this
submission alone.)
- Biochemistry losses for their
labs located in the Dental Clinic Building, the MEB and the CSRB.
- Genetics losses for labs
located in the CSRB.
- Alcohol Research Center
losses for labs in the CSRB.
As
additional data on losses is gathered and verified, more claims will be
submitted. Claim information is coming in from Physiology, Nephrology,
Ophthalmology, Pharmacology, the Neuroscience Center, Microbiology, etc.
and will be packaged for submission shortly.
We hope that you continue to find this information helpful. Don’t forget
that Daily Updates are also posted on the web site so that you can follow
the recovery progress more closely.
|