|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #14
Posted: April 11, 2006
With a substantial
portion of the research enterprise restored to operations on the downtown
campus, the focus of the recovery effort has shifted to the return of
student housing and the Schools of Medicine, Allied Health and Nursing.
If all goes as planned, we would expect to see the reopening of the
two student residence facilities, the Nursing/Allied Health Building and
the Resource Center occur within the next 2 months.
The Office of Facility Planning & Control is working
closely with us to “carve out” and expedite some key permanent repairs to
portions of the MEB needed to support the return of the School of Medicine
before the incoming class begins. Projects to restore the two large
lecture halls, the morgue, the Gross Anatomy Labs, and the
Multidisciplinary Labs are being moved forward as rapidly as possible.
Completion of work under these contracts is currently projected for about
July 1.
The environmental remediation in the Nursing/Allied
Health Building is progressing on schedule and the work is substantially
complete on the upper floors. The majority of the parts needed for
elevator repairs in that building arrived last week, and we anticipate
that the repairs should be completed within the next two to three weeks.
Repairs to the build’s fire alarm system are well underway and should be
completed in the near future as well. We are cautiously optimistic that
the building will reopen in mid to late April as planned.
Stanislaus Hall is targeted to reopen in late April.
The environmental remediation is substantially completed throughout the
building. The repairs to the building elevators are complete and the
inspection of the State elevator inspector has just certified them for
general use. The majority of the build’s pumps are operational; the city
water pumps will be installed within the week.
We have recently begun to receive shipments of new
fitness equipment for the Wellness Center. The majority of the equipment
should be delivered and installed within the next few weeks. We hope to
have this new facility available to faculty, staff and students this
summer.
Due to the need to replace a large portion of the
floor tiles in the building, the environmental remediation in the
Residence Hall is a more time consuming process. The old tile has been
removed and the new tile will be installed as soon as it is delivered.
The other remediation work in the building is progressing well. Elevator
parts have been arriving for some time and work is underway to complete
repairs so that they can be certified for general use. New refrigerators
for the rooms are being ordered and will be delivered shortly. The target
for reopening the building is mid-May.
The work in the Resource Center has progressed well
and plans are to be able to reoccupy the upper floors in early June. Two
elevators are already certified for use and the remaining repairs are
underway. The environmental remediation is largely completed throughout
the building. Work on the fire alarm system is under contract and should
begin shortly. The domestic water pumps have been delivered and
installation will be completed shortly. We’ve also taken this opportunity
(while the Ische Library collection has been removed for cleaning) to
replace the 20 year old carpet on all three floors.
Many of the parking lot controls; gates, card
readers, etc. were damaged during the storm. In anticipation of the
return of larger numbers of faculty, staff and students, contracts have
been issued to complete the needed repairs. This will allow us to secure
and control the lots as we had in the past.
The emphasis will be on making repairs to the larger
and more heavily used parking lots first to maximize the availability of
convenient, safe parking. While the various lots have been closed, we
have also taken this opportunity to make improvements to the Residence
Hall parking lot and to the Student Lots 2 & 3 before we open them up for
use again.
The architect/engineering firm responsible for the
Dental School campus completed their 2nd set of specifications
for additional, temporary repairs to key building systems and bids have
been received. The contract for this second set of temporary repairs to
the buildings’ mechanical systems is expected to be awarded shortly.
Here are highlights of work that has been
accomplished since our last update was posted on Tuesday, March 28th.
- The work on the 2nd contract for environmental
remediation contract addressing the Nursing/Allied Health Building, the
Residence Hall, Stanislaus Hall and the Resource Center has been
underway since mid-March. Progress reports on each building follows:
- Residence Hall: All of the damaged floor tiles
have been removed from all floors. New tiles are on order and will be
installed as they are delivered.
- Stanislaus Hall: All of the cleaning has been
completed on every floor. Cleaning of the stairwells and mechanical
rooms is substantially complete.
- Nursing/Allied Health: The cleaning has been
completed from the top floor down to the 2nd floor. Work
on removal of sheet rock, etc. on the 1st floor is well
underway. Approximately one half of the mechanical rooms have been
cleaned and inspected.
- Resource Center: All of the upper floors (2nd
through 8th) have been cleaned. Work on removal of sheet
rock, etc. on the 1st floor is well underway.
Approximately one half of the mechanical rooms have been cleaned and
inspected.
- The accelerated pace of repairs to building
elevators continue. Inspections by the State Elevator Inspector have
been requested or will be requested shortly for the passenger elevators
at the MEB, the Lion’s/LSU Clinic Building and Stanislaus Hall.
- The Stanislaus Hall elevators have just been
certified for general use.
- Results of the inspections at the Lion’s/LSU
Clinic Building are expected to be published shortly.
- The initial inspection of elevators at the MEB
revealed some minor issues that have been reported to the contractor.
Another inspection will be scheduled soon as the minor repairs are
completed.
- The contractor is replacing the hoist cables in
the “C” Tower elevators at the Residence Hall.
- Work has begun on repairs to the elevators
serving the Walk To Wellness.
- School of Dentistry restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC continue.
- The 1st of the bid packages for
temporary repairs to building electrical systems and for temporary air
conditioning at the Dental School has been awarded and work has
recently begun.
- The 2nd of the bid packages for
temporary repairs to the buildings’ critical mechanical systems has
been developed and the solicitation of bids has been completed. The
bids have been evaluated by both the architect and LSUHSC and the
award recommendations have been made to the Office of Facility
Planning & Control. An award is anticipated shortly.
- Downtown campus restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC have
continued and will remain as a scheduled item for some time.
- The 2nd environmental remediation
contact has been awarded. See the report above for details.
- The 3rd environmental remediation
contact specifications have been approved, bids have been solicited
and the contract is being awarded at this time.
- The architects are working on a series of
smaller projects that have been “carved out” of the larger permanent
repair work to facilitate the return of the Medical School classes to
campus.
- Permanent repairs to building windows are out
on bid.
- The replacements for the flood damaged MEB
Lecture Rooms seating have been ordered. A bid package is being
developed for the remainder of the repairs to the Lecture Rooms.
- The contracts for repairs to the parking lot
control systems have been awarded.
- Bid packages are being developed for permanent
repairs (in the MEB) to the Gross Anatomy Lab, the Morgue, and the
Multidisciplinary Labs.
- Contracts have been awarded for the repairs to
various types of pumps to supply water and heat to the Residence Hall,
Stanislaus Hall, the MEB, CSRB, Lion’s Eye Center, Nursing/Allied Health
Building, and Resource Center. The following is the status of progress
in each building:
- Stanislaus Hall:
- All the sump pumps have been installed.
- City water pumps have been delivered and will
be installed soon.
- CSRB:
- Domestic hot and cold water pumps have been
installed and are operating.
- The heating hot water pumps have been
installed and will be tested shortly.
- MEB:
- The 3 boiler feed water pumps have been
installed and are now operating.
- The two chemical feed water pumps have been
installed and are operating.
- The brine pumps in the MEB have been installed
and are operating.
- The heating hot water pumps have been
installed and will be tested shortly.
- Nursing/Allied Health:
- The hot water recirculating pumps have been
installed.
- Lion’s/LSU Clinic:
- The hot water recirculating pumps have been
installed.
- Resource Center:
- Two hot water recirculating pumps have been
installed, but the electrical connections must still be made
- Contracts to repair the fire alarm systems and
their components in downtown campus buildings have been awarded to the
vendors who currently provide annual maintenance to the systems. This
approach will insure that the systems can be re-certified and remain
under the existing maintenance contract. Several of the systems have
been repaired and inspected and work continues in the remaining
buildings.
- Stanislaus Hall: Completed and inspected.
- CSRB: Completed and inspected.
- MEB: Completed and the inspection has been
scheduled.
- Lion’s Eye Center: Completed and inspected.
- Nursing/Allied Health: All smoke detectors and
pull stations are installed with the exception of 8 pull stations and
duct-mounted smoke detectors on the 5th and 10th floors. The
contractor is working on the terminations for all of the control wires
for the fire system and the work is approximately 25 % completed.
- Resource Center: The repairs required for the
fire alarm system have been identified and the contract has been
issued. Parts are arriving and repairs should begin shortly.
- The contract for the repairs to the emergency
generators at the CSRB, MEB, Lion’s Eye Center, Nursing/Allied Health
Bldg., Resource Center and the Residence Hall has been awarded. Work
has begun on several of the generators, and parts are on order.
- The repairs have been completed on the roof
mounted generator at the MEB. This provides emergency power to the
majority of the researcher’s freezers and walk in coolers in that
building.
- All of the damaged stators have been removed and
sent to be rebuilt.
- The rebuilt stator for the Resource Center
generator has been delivered and installation will begin soon.
- A contract has been issued for repairs to the
medical air compressors, vacuum pumps and water purifiers at the CSRB,
Lion’s Eye Center and the MEB. Parts are on order and repairs will
begin as soon as the parts begin to arrive.
- Work under a contract to clean, decontaminate and
re-certify the biosafety cabinets in research labs began on March 15th.
There are 100 cabinets covered under the contract and work is underway.
The Purchasing Department is contacting the departments and coordinating
this work as specific cabinets are identified.
- Full Internet access has been restored to the 6th,
7th, 8th and 9th floors of the
Lion’s/LSU Clinic Building. This was accomplished in large part through
the efforts of the School of Medicine’s PC Support team, as they worked
to get all of the computers updated to insure that the LSUHSC-New
Orleans network is protected.
- After experiencing 2 short term power outages in
the CSRB, the switch gear manufacturer’s representative is coming out to
perform further tests of the switchgear to determine the need for
additional temporary repairs. Additional work needed will be defined
and submitted to FEMA, the Office of Facility Planning & Control and ORM.
- Additional claims for the building content losses
have been prepared and submitted to FEMA, ORM and the Office of Facility
Planning & Control. Recent submissions include:
- Physiology
- Ophthalmology
- Pharmacology
- Supply Chain Management
- PeopleSoft Support
As additional data on losses
is gathered and verified, more claims will be submitted. FEMA has already
begun working some of the initial claims and has requested validating
documentation; using a 20% sample size from each claim. They will also be
making site visits to view damaged equipment.
We hope
that you continue to find this information helpful. Don’t forget that
Daily Updates are also posted on the web site so that you can follow the
recovery progress more closely.
|