|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #16
Posted: May 6, 2006
We recently received approval to occupy
two additional buildings on the downtown campus!
On May 1st, the State Fire Marshal granted a
conditional permit for temporary (30 day) occupancy of the Nursing/Allied
Health Building and Stanislaus Hall. A number of deficiencies were
identified which will be resolved over the balance of the month. Access to
the Nursing/Allied Health Building was provided the following day, while
access to Stanislaus Hall was delayed for 7-10 days to allow time for
particular conditions to be addressed.
Safety in our buildings will continue
to be a major concern of the State Fire Marshal. We expect special
emphasis on evacuation plans and fire drills to make certain that all are
knowledgeable of evacuation/exit routes.
Repairs to the elevators in the
Nursing/Allied Health Building have not been completed at this time, and
they are not yet certified for passenger use. We hope that these repairs
will be completed within the next two weeks. The elevators in Stanislaus
Hall have been certified for passenger use for some time.
We also wish to remind you that we have
a very limited number of building maintenance and custodian staff. The
understanding, patience and support of all faculty, staff and students of
this reality is appreciated.
We continue to plan for the reopening
of the Residence Hall within the next few weeks. The environmental
remediation contractor has completed all their work, with the exception of
the installation of floor tile. The contractor now has two crews working
around the clock to complete that task quickly. The State Elevator
Inspector is scheduled to inspect the building elevators early next week.
We expect that they will be certified for passenger use shortly
thereafter. The repairs to the fire alarm system are substantially
complete.
The Office of Facility Planning &
Control has instructed the architects to solicit pricing for a project to
complete key permanent repairs within the Medical Education Building.
Repairs to the two large lecture halls, the morgue, the Gross Anatomy
Labs, and the Multidisciplinary Labs are needed to support the return of
the Schools of Medicine, Nursing and Allied Health before the incoming
classes begin. Bids for the project are due on 5/10/06. The solicitation
calls for a start date of 5/20 with the completion of the work specified
for not more than 45 days. Completion of work under this contract is
currently projected for about July 10th.
The work in the Resource Center has
continued to progress well and plans are to be able to reoccupy the upper
floors in early June. The environmental remediation is substantially
complete throughout the building. Work on the fire alarm system is well
underway. The carpet replacement in the Library has also progressed well.
The installation of the new carpet has been completed on the 4th
floor. The installation on the 3rd floor is expected to be
completed very soon, and the 5th floor work is more than 50%
complete.
The planned improvements to selected
parking lots are proceeding. The resurfacing of the Residence Hall lot and
the improvements to Student Lot #2 are largely completed. Work has now
begun on Student Lot #3.
The substantial temporary repairs to
the Clinic and Administration Buildings at the Dental School are underway.
Two contractors have received contracts and begun work. One is addressing
the buildings’ electrical systems and the 2nd is responsible
for the other critical mechanical systems. Both contractors have been
instructed to complete their work by June 30th, although
selected equipment items needed may not be available from manufacturers
within that timeframe. Regardless, the contractors are doing all that they
can to meet this aggressive schedule.
The majority of the equipment for the
new fitness center in Stanislaus Hall has now been delivered and is being
installed. A summer opening of this new facility to faculty, staff and
students is still scheduled.
Here are highlights of work that has
been accomplished since our last update was posted on Friday, April 21st.
- The work on the 2nd contract for environmental
remediation contract addressing the Nursing/Allied Health Building, the
Residence Hall, Stanislaus Hall and the Resource Center has been
underway since mid-March and work is substantially completed in all of
the buildings. Completing the installation of replacement floor tile in
the Residence Hall Progress is the only portion of the contract not yet
finished.
- The 3rd environmental remediation
contract addressing the balance of the buildings and facilities on the
downtown campus has been awarded. The contractor has mobilized and work
will begin immediately.
- The accelerated pace of repairs to building
elevators continue. Inspections by the State Elevator Inspector have
been requested or will be requested shortly for the passenger elevators
at the MEB, the Lion’s/LSU Clinic Building and Stanislaus Hall.
- All of the Stanislaus Hall elevators have been
certified for general use.
- All five of the elevators in the Lion’s/LSU
Clinic Building have passed inspection and are now certified for
general use.
- The installation of new emergency telephones in
the MEB elevators has been completed and they are now certified for
passenger use.
- The contractor has completed repairs to all of
the elevators in the Residence Hall, and the State Elevator Inspector
will complete his inspection early in the coming week.
- Walk To Wellness & Gravier St. Garage: Work has
begun on repairs to the elevators serving both structures.
- The contractor will be replacing the 1st
floor elevator doors on all of the elevators in the Resource Center.
The hoist cable on elevator #3 is undersized and was cited by the
State Elevator Inspector prior to the current contactor receiving the
annual maintenance contract. The former contractor is paying for the
replacement cable and the current contractor will install it. The
replacement cable is in the contractor’s shop.
- School of Dentistry restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC continue.
- The 1st of the bid packages for
temporary repairs to building electrical systems and for temporary air
conditioning at the Dental School has been awarded and work has
recently begun.
- The temporary chiller and generators are on
line at the Dental School Clinic and Administration buildings and
the buildings are being cooled.
- The electrical contractor is continuing to
progress with the work on a temporary electrical power feeds and the
installation of temporary conduit, etc.
- The 2nd of the bid packages for
temporary repairs to the buildings’ critical mechanical systems has
been awarded and the contractor has begun work.
- Demolition of flood damaged building
materials related to the environmental remediation is well underway
in the basements (estimated to be 90% complete) and on the 1st
floors of both the Clinic and Administration buildings (estimated to
be 50% complete).
- Installation of critical pipe insulation in
the basement is complete.
- Downtown campus restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC have
continued and will remain as a scheduled item for some time.
- The 2nd environmental remediation
contact has been awarded and the contract is substantially complete.
- The 3rd environmental remediation
contact has been awarded and will address the remaining buildings and
structures on the downtown campus. The contractor has mobilized and
work will begin immediately.
- The architects are working on a series of
smaller projects that have been "carved out" of the larger permanent
repair work to facilitate the return of the Medical School classes to
campus.
- Permanent repairs to building windows have
been bid and the contract has been awarded.
- A bid package is being finalized for the
permanent repairs to the MEB Lecture Rooms, the Gross Anatomy Lab,
the Morgue, and the Multidisciplinary Labs. The Office of Facility
Planning and Control has approved an expedited process for securing
competitive pricing so that the award can be completed quickly and
prices are being solicited at this time.
- Contracts have been awarded for the repairs to
various types of pumps to supply water and heat to the Residence Hall,
Stanislaus Hall, the MEB, CSRB, Lion’s Eye Center, Nursing/Allied Health
Building, and Resource Center. The following is the status of progress
in each building:
- Stanislaus Hall:
- The sump pumps have been installed and are
operating.
- The chilled water system has been refilled
and air conditioning is available in the building again.
- City water pumps have been delivered and have
been installed. One of the pumps failed and has been removed and
taken to the contractor’s shop for further repair.
- CSRB:
- Domestic hot and cold water pumps have been
installed and are operating.
- The heating hot water pumps have been
installed and have been tested.
- MEB:
- The 3 boiler feed water pumps have been
installed and are now operating.
- The two chemical feed water pumps have been
installed and are operating.
- The brine pumps in the MEB have been
installed and are operating.
- The heating hot water pumps have been
installed and successfully tested.
- We are still waiting on receipt of the
rebuilt condensate return pumps.
- The domestic hot water return pump has been
removed for testing/evaluation.
- Nursing/Allied Health:
- The hot water recirculating pumps have been
installed.
- The city water pumps for this building
shipped this past week and are expected to be received and installed
shortly.
- The domestic hot water pumps have been
installed and are operating in the Nursing/Allied Health Building.
- Lion’s/LSU Clinic:
- The hot water recirculating pumps have been
installed.
- Resource Center:
- Two hot water recirculating pumps have been
installed and are operating.
- Contracts to repair the fire alarm systems and
their components in downtown campus buildings have been awarded to the
vendors who currently provide annual maintenance to the systems. This
approach will insure that the systems can be re-certified and remain
under the existing maintenance contract. Several of the systems have
been repaired and inspected and work continues in the remaining
buildings.
- CSRB, Lion’s/LSU Clinic Building and the MEB:
Completed and inspected.
- Stanislaus Hall: A temporary occupancy permit
has been issued and the list of deficiencies will be addressed within
the next few weeks.
- Nursing/Allied Health: A temporary occupancy
permit has been issued and the identified deficiencies will be
addressed within the next few weeks.
- Residence Hall: The repairs have been
substantially completed. Final repairs are being made to door closers
and when they are complete the State Fire Marshal will be asked to
inspect the building.
- Resource Center: The contractor is replacing
damaged components and testing system operations. When repairs are
completed, the State Fire Marshal inspection will be requested.
- The contract for the repairs to the emergency
generators at the CSRB, MEB, Lion’s Eye Center, Nursing/Allied Health
Bldg., Resource Center and the Residence Hall has been awarded. Work has
begun on several of the generators, and parts are on order.
- The repairs have been completed on the roof
mounted generator at the MEB. This provides emergency power to the
majority of the researcher’s freezers and walk in coolers in that
building.
- All of the damaged stators have been removed
and sent to be rebuilt.
- The contractor has inspected all of the
automatic transfer switches (ATS) in each of the buildings to
determine what repairs are needed.
- The Nursing/Allied Health Building will
require a shutdown of electrical power to the building to work on
ATS. This will be scheduled.
- CSRB: The repair work is complete on the
generator. Diesel fuel is needed and LSUHSC has placed the order.
- Lion’s/LSU Clinic: Most of the repairs have
been completed, however a panel needed for the repairs has not yet
arrived. Diesel fuel is also needed here and will be ordered.
- The MEB, the Residence Hall, the Nursing/Allied
Health Building and the Resource Center are waiting on repairs to be
completed to the stators of their respective generators. As the
repaired stators are delivered, they will be installed.
- After experiencing 2 short term power outages in
the CSRB, the switch gear manufacturer’s representative was requested to
perform further tests of the switchgear to determine the need for
additional temporary repairs.
- The testing of the CSRB switchgear was
completed over the weekend of April 22nd. We are waiting on
the written report from the manufacturer at this time. However, the
following summarizes the findings thus far:
- Some problems were discovered, including some
on the main breaker which has been tripping occasionally, though
nothing was identified that clearly caused our problems.
- There was some indication that there may be
wiring issues on the roof mounted exhaust units. This will be the next
focus for LSUHSC Facilities staff.
- There were also some indications that the trip
settings are too "tight." This will require that we secure some
electrical engineering assistance to analyze further.
- The search for the possible cause(s) of the
power outages recently discovered three damaged electrical feeders
that serve the building. Plans are underway to replace the most
critical feeder during the evening of Tuesday, May 9th and
the other two feeders on Saturday, May 13th.
- The replacement of 20 year old carpeting in the
Resource Center is proceeding smoothly. The installation of carpeting is
complete on the 4th floor, the installation on the 3rd
floor is substantially complete, and work on the 5th floor is
over 50% finished.
- A contract has been issued for repairs to the
medical air compressors, vacuum pumps and water purifiers at the CSRB,
Lion’s Eye Center and the MEB. Parts are on order and repairs will begin
as soon as the parts begin to arrive.
- The contractor has begun removing the damaged
medical air and vacuum pumps and the water purifiers from the CSRB.
Please continue to follow our progress
through our Daily Updates that are also available on the web site.
|