|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #34
Posted: January 22, 2007
The New Year has come and the
recovery efforts are continuing at full speed.
Repairs to the electrical service to the various
parking lots are well underway on the downtown
campus. The initiative to make some
enhancements to the MEB atrium and 3rd
floor corridors (unrelated to the storm) is
progressing well.
LSUHSC Safety staff and an
environmental contractor completed the
identification, removal and disposal of chemicals
that had remained on the 1st floor of the
Dental School Clinic Building. The
temporary dehumidifiers have been turned off so that
we can determine the effectiveness of the temporary
chillers and boilers in controlling the internal air
quality. We expect to remove the dehumidifiers
shortly. We are close to having the freight
elevator operating in automatic mode and parts for
the repairs of the other elevators have been
arriving and are being installed.
Specifications for the duct
cleaning and environmental remediation projects at
the Dental School are under review
and should be finalized in the near future and the
bids put out on the street. The third party
assessment of the flood damaged boiler has been
completed and FEMA is reviewing the report.
Various punch list items are being addressed by the
general contractor. The 2nd phase
of the incinerator repair project has been
completed. Only the repair of flood damaged
fire brick remains before the unit will be fully
functional.
At 1542 Tulane Ave. the
contractor continues to install additional
electrical components necessary to fully power up
and light the building. The elevator
contractor has been busy making a series of repairs
to components of the building elevators as parts
arrive. A few new change order proposals have
been priced out by the contractor and are now being
considered for eligibility by FEMA. We also
continue to discover minor but important items that
were damaged by the storm as building systems are
tested and those are being addressed as quickly as
possible.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Project to Make Temporary
Repairs to the Dental School:
- The mechanical
sub-contractor is working on the exhaust fans on
the roof. They are checking the operation of
the fans, and replacing belts and bad fans as
necessary.
-
LSUHSC Safety personnel and Veolia Environmental Services worked
for approximately a week to remove old chemicals
from spaces on the 1st floor of the
Dental School Clinic Building; identifying
the chemicals and preparing them for proper
handling and disposal.
-
The new basement doors for the Clinic elevators have arrived and
all have been installed.
-
The freight elevator will be ready to operate in automatic mode in
the near future.
-
The elevator contractor is working on the
repairs to the 1st floor call
buttons and to the rollers on the doors in
the basement of the Clinic Building.
- The installation of
the elevator doors on the 1st
floor of the Dental Clinic Building
has begun.
- The temporary
dehumidification units that have been operating
at the Dental School were shut down late last week
at the request of LSUHSC. This allowed the
LSUHSC Facility Services staff to assess the
capability of the new temporary chillers and the
repaired building systems to maintain an
acceptable humidity level in the buildings prior
to instructing the contractor to remove the
dehumidification equipment.
- Periodic readings have
been taken throughout the buildings on a
daily basis. The initial readings suggest
that the interior air is being well
controlled.
- If the readings
continue to show adequate control, the
contractor will be instructed to remove the
dehumidification equipment.
-
The mechanical subcontractor wired the motors to
the control panel for the wet vac system in the
basement of the Clinic Building.
-
The system was started and flushed out
several times.
-
A significant amount of post-storm debris
was removed from the system.
-
The contractor has been identifying the switches
and wires in the flood damaged motor control
center that will be used in the installation of
the replacement unit.
-
Preliminary work necessary to re-establish
telephone and network connectivity to the Dental School has begun.
-
The contractor has delivered some of the
materials needed to install a new back board
and supply electrical power to the location
where BellSouth will terminate their trunk
lines and fiber optic (network) cable.
-
Boe-Tel Communications has surveyed the site
to provide a quote on the cabling necessary
to install and connect a new telephone
switch.
- The mechanical
subcontractor worked on the steam condensate
line in the Dental School Power Plant at the
platform level.
- They also found a
crack in a 4" vacuum line in the Faculty
Practice area on the 1st floor of
the Clinic building when they started up the
unit.
- The water hoses that
connected the chilled water supply and the
return lines to the emergency chiller at the
Dental School have been removed.
-
The transformer that had been serving the
temporary chiller outside the Power House is
being disconnected.
- The manufacturer of the
incinerator at the Dental School
completed the Phase II repairs.
- Only the repairs to
the fire brick that was damaged by flood
waters remain to be priced and completed.
- The formal inspection and
assessment of the flood damaged boilers has been
completed and the report has been forwarded to
FEMA for review. FEMA’s initial comments have
been returned and a joint visit to the site by
the assessment company representative and the
FEMA team is being coordinated.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
-
The installation of new, temporary lighting in
the basement of 1542 Tulane Ave. is an ongoing
effort.
- The contractor is
installing electrical panels for the 13 – 8
switchgear and pulling wires for lighting
and switches in the basement.
-
New conduit and wiring is being run to
supply power to the new fixtures.
-
Conduit and wiring is also being installed
to connect the various equipment starters
that are located on the 1st
floor.
-
The old, flood damaged conduit and wiring
that has been abandoned in the basement is
being removed.
- The old transformers
were removed from the parking lot at 1542 Tulane Ave.
- The contractor
received 2 pieces of electrical switchgear
for the outside generator.
- They also installed
new electrical panels in the basement to
service the elevators.
- The contractor
received two new transfer switches for the
emergency generators located at
1542 Tulane Ave.
and they are installing them at this time.
- The elevator contractor
continues to make repairs to elevator equipment
located in the penthouse located in the rear of
the building.
- He is also removing
the damaged elevator controls so that they
can be replaced.
- The mechanical
sub-contractor is removing old pipes in the
basement that have been replaced and abandoned.
- They also received the
four sumps pumps that will be installed in
the basement.
-
The subcontractor found two drain lines
capped off. These were apparently damaged
by the clean-up contractor and then capped.
When the lines were traced out, they were
found to be serving two sinks on the 3rd
floor. These drains will need to be
replaced.
- Steam was not restored to
the building recently as originally planned due
to the discovery of a flood damaged steam valve,
and flood damaged pop-off and steam traps.
Repairs will be made shortly.
MEB Atrium Renovation:
- Work on the enhancement
project in the MEB atrium and the 3rd
floor hallways is continuing.
- The completion of the
work in the 3rd floor corridors
was waiting for the delivery of the
remaining new light fixtures.
-
The remaining lighting fixtures have
recently been delivered and are being
installed.
-
The exit signs have been installed in the 3rd
floor corridors of the MEB.
- The sprinklers located
in the ceilings of the 3rd floor
corridors were temporarily moved so the last
of the new light fixtures can be installed.
- The installation of
drywall on the atrium fur downs and walls is
well underway.
- The contractor was
asked by the architects to install angle
iron bracing on the ceiling beams to provide
additional support for the fur downs.
-
80% or more of the sheet rock is now
installed and is being taped, floated and
prepped for painting.
- The remaining sheet
rock installation is waiting for the frames
for the new light fixtures to be installed.
- The fire sprinklers
that were covered by the new fur-downs have
been lowered so the contractors can finish
those areas.
- Approximately 80% of
the new grid for the ceiling tile has been
installed.
-
The contractor installed new fire alarm speakers
in the MEB 3rd Floor corridors, and LSUHSC
personnel tested them to insure that they were
all operating properly.
Miscellaneous Items:
-
Leaking water valves were discovered on two
floors of the Medical Education
Building. There was
a domestic water outage scheduled during the
evening of January 10th so that the
valves could be replaced.
-
An additional problem was found with the
de-ionized water in the Clinical Sciences
Research Building. The system
has had some additional work done on it and it
is not suitable for use. Users in the building
will be advised when the system is cleared for
use.
-
A number of valves and faucets in the Residence
Hall are leaking. A domestic water shut down
has been scheduled for the evening of January 25th
to allow repairs to be completed.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|