|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #37
Posted: March 5, 2007
Work on the enhancements to the
MEB atrium is substantially complete. All of the painting has been completed. The new floor tile has been installed on the
atrium floor, on the ramps leading to the MEB and in
the elevator lobby of the Nursing/Allied Health
Building. The carpet has been installed on the upper
portion of the atrium. New furniture has been delivered and
installed. Students are already using the atrium as a
location to gather and study.
All of the old ceiling tile in
the Clinic and Administration Buildings at the
Dental School has been removed in
a combined effort by LSUHSC Facility Services
personnel and a contractor hired to assist in the
efforts.
A new contract is being developed to provide for the
removal of the grid that suspended the old ceiling
tiles.
The LSUHSC Industrial Hygienist has completed his
review of the environmental remediation and duct
cleaning bid specifications and the two bids will be
put on the street in the near future. The new motor control center has been
installed.
LSUHSC Facility Services is
finalizing their work with the Dental School
architects to develop plans for replacing the old
ceiling tile in both the Clinic and
Administration Buildings. The use of mold and humidity resistant tiles
that are also smaller in size may present an
opportunity to seek additional reimbursement from
FEMA for some additional components of the
replacement costs.
At 1542 Tulane Ave. the
contractor continues to install additional
electrical components necessary to fully power up
and light the building. New submersible sump pumps have been
installed that will protect the basement spaces from
the intrusion of ground water during heavy rains. Repair work on various building elevators
continues. Several change orders have been priced and
the remaining issues related to FEMA reimbursement
of those change orders are being addressed so that
the work can be authorized.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Project to Make Temporary
Repairs to the Dental School:
- The installation of the
new motor control center at the Dental School
Power Plant has been completed.
- Three sections of the
old motor control center were removed from
the Power Plant and the contractor
disassembling the largest unit so that it
could also be removed.
- The old motor control
center components have been removed from the
campus.
- The flood damaged
transformer removed from the
Dental School some time ago
has also been picked up and moved from the
site.
- The contractor replaced
the first of four electrical sub-panels that are
to be replaced in the Administration Building. This work was coordinated with the
elevator contractor, since it temporarily
interrupted power to the elevators.
- The electrical contractor
has continued working on the installation of
conduit, wiring, etc. needed in the 5th
floor telecom room in the Clinic Building.
- The State Contract
representative of the telephone switch
manufacturer began their inspection of the
Dental School.This will allow them to prepare the
cost estimates for re-cabling the switch in
the new 5th floor location.
- The contractor hired to
assist in removing ceiling tiles from the
Dental School buildings has finished with
the removal of the tiles in both the Clinic and Administration
Buildings.
- They cleaned and
dusted the areas in which ceiling tiles have
been removed.
- A new contract to
remove the ceiling tile grid is being put
into place.
- The architects came on
site to assess how the new 2 x 2 ceiling
grid will be installed in the Clinic and
Administration buildings, and how the new
grid will impact on the existing sprinkler
system and the placement of the HVAC vents.
- A subcontractor
re-insulated two pipes on one of the replacement
chillers in the Dental School Power Plant.
- The Dental School elevator contractor is
continuing to work on the elevators in both the
Administration and Clinic Building.
- The State Elevator
Inspector came out and did a safety check on
the four elevators in the Clinic Building.
- The 110 volt power supply
was connected to the chemical treatment station
in the Dental School Power Plant.
Project to Make Temporary Repairs to 1542 Tulane Ave.:
- The 1542 Tulane Ave. contractor continues
his work on installing electrical panels,
running conduit, and installing new lighting in
basement.
- They now have most of
the lights in the basement installed and in
service. The insulation contractor is
progressing on the insulation of the chilled
water pipes.
- They are also checking
electrical panels on upper floors to
determine which ones have not yet been
energized.
- The elevator contractor
continues to change out the damaged panels in
the elevators.
- The project to insulate
the new pipes in the
1542 Tulane Ave.
basement continues.
- The insulation of the
chilled water pipes is progressing well.
- The insulation of the
steam lines has also begun.
- The contractor received
some electrical cables for the switch gear
located on the fourth floor.
- The mechanical
subcontractor has installed plates over the new
sumps in the basement and has cleaned out the
last sump.
MEB Atrium Renovation:
- The installation of the
new floor tile in the lower portion of the MEB
atrium has been completed.
- The installation of the
floor tile in the elevator lobby of the
Nursing/Allied Health Building has been
completed.
- The installation of the
floor tile on the ramps leading from the atrium
space to the MEB has been completed.
- All of the new light
fixtures have been installed and are operating
in the atrium.
- The hand rails have been
reinstalled on the walls of the two ramps that
lead from the atrium into the MEB.
- The top rails of the new
knee walls that line the upper portion of the
atrium have been installed. Finishing and painting still remain to be
completed.
- Patching and repainting of
walls is in progress.
- The new furniture
(seating, tables, etc.) has been delivered and
installed in the upper portion of the atrium.
Miscellaneous:
- The contract to restore
electrical power to the various parking lots on
the downtown campus is progressing well.
- The electrical
contractor is working on installing the
conduit run from Student Lot 2 to Student
Lot 3.
- They still have to
finish the unistrut on Student Lot 1
(formerly Student Lot 5).
- The contractor who is
repairing or replacing damaged parking lot
controls, gates, arms, etc. is working on
the access controls on the ramp leading to
upper floors of the Roman St. Garage. He expects to be substantially
completed with his entire contract shortly.
We encourage you to follow the details of our progress
through the daily updates which are posted on the web site.
|