|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #46
Posted: July 6, 2007
The bid documents for the
replacement of the Medical Education Building roof
have been prepared and submitted to the Office of
Facility Planning and Control. The bid is to be
advertised on July 12th, the pre-bid
conference is scheduled for July 17th,
and bids are to be opened on July 24th.
Bids will then be reviewed and analyzed to determine
the low responsive and responsible bidder. Once the
determination has been made the contract documents
will be drawn up and the contract awarded.
The architects responsible
for the downtown campus have completed three more
Section 406 Hazard Mitigation design concepts. These
have been forwarded to the State’s 406 Mitigation
team for their review prior to forwarding them to
FEMA. These proposals are somewhat more
straightforward and we hope for a more rapid review
and approval of these concepts, which will allow the
architects to flesh out the proposals for their
final submission. Additional information is provided
below.
The formal FEMA
recommendations for our 406 Hazard Mitigation
proposals for the campus elevators have been
received and they are moving through the internal
FEMA review queues now. We expect the review process
to go smoothly and for the funds needed to support
the proposal to be obligated.
The final environmental
remediation and duct cleaning at the Dental School
is substantially complete. There are only a small
number of air handling units that have not been
cleared to be turned back on. We have also moved
forward with a change order to one of the contracts
in place at the Dental School to replace a number of
the old inline dampers throughout the two buildings.
This should improve the ability to control
temperatures in the two buildings. Replacement of
and/or repairs to the 1st floor exit
doors (required by the State Fire Marshal) are well
underway. The Central Sterilization project is also
proceeding on schedule.
The project to replace the
ceiling grid and tile in the Clinic and
Administration Buildings is proceeding very well and
it appears that they will be able to complete their
work within the schedule provided for in their
contract. The coordination between the remediation
contractor, the network wiring contractor, and all
the sub-contractors working on the ceiling project
has been very smooth and no significant
interruptions of work have occurred.
Good progress continues to
be made at 1542 Tulane Ave. It appears that power
has been restored to the majority of the building.
The contractor has been checking to insure specific
electrical panels throughout the building have been
energized. The air compressor system that is
required by the building system controls is being
replaced. One elevator has been repaired and can be
certified for normal use once the emergency
telephone lines are connected. Repairs are moving
quickly on a 2nd elevator.
Here are highlights of
work that has been accomplished since our last
update was posted two weeks ago.
Section 406 Hazard
Mitigation:
- The design concepts for the permanent
repairs and related Section 406 Hazard
Mitigation work for three of the downtown campus
buildings were submitted to GOHSEP for their
review today.
- The buildings are the Allied
Health/Nursing Building, the Residence Hall,
and the Resource Center.
- If the State Section 406 expert concurs
with the design concepts prepared by the
architects, they will be forwarded to the
FEMA 406 team for their review and initial
concurrence.
- If the FEMA 406 Team has no objections,
the process will move to the 2nd
phase where the architects prepare design &
development documents and a formal cost
estimate. This will form the basis of the
formal submission of the Section 406
Mitigation proposal.
- FEMA has completed the preparation of the
documents that recommend eligibility of the
Section 406 measures that LSUHSC proposed to
protect the many elevators around the campus and
presented them for signature today.
- The documents will now be forwarded to
the Office of Facility Planning and Control
for their concurrence and will then be
processed by FEMA.
- Bids will then be prepared to implement
the proposed 406 measures:
- The purchase and installation of an
automated control system that will allow
LSUHSC Facilities to control the height
of the elevator cabs from a central
location. The controls will be set to
elevate the cabs and cables above flood
water levels.
- TThe purchase and installation of
float switches in the elevator pits that
will sense water in the pits and
automatically raise the elevator cabs
out of harms way.
Project to Make Temporary
Repairs to the Dental School:
- The final environmental remediation and duct
cleaning contract is substantially complete.
- Remediation Status:
- Clinic 1st Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Clearances have been received.
- The containment has been
removed.
- Clinic 2nd Floor:
- Duct work has been cleaned.
- Test results have been received
and passed.
- The interior insulation has been
coated/encapsulated.
- Both AHUs are operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 3rd Floor:
- Duct work has been cleaned.
- Test results have been received.
One unit passed and one unit
required recleaning.
- The interior insulation has been
coated/encapsulated.
- One AHU is operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 4th Floor:
- Duct work has been cleaned.
- Test results have been received
and passed.
- The interior insulation has been
coated/encapsulated.
- Both AHUs are operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 5th Floor:
- Duct work has been cleaned.
- Test results have been received.
One unit passed and one unit
required recleaning. New results are
pending.
- The interior insulation has been
coated/encapsulated.
- One AHU is operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 6th Floor:
- Duct work has been cleaned.
- Test results have been received.
One unit passed and one unit
required recleaning. New results are
pending.
- The interior insulation has been
coated/encapsulated.
- One AHU is operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 7th Floor:
- Duct work has been cleaned.
- Test results have been received.
Two units required recleaning. New
results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 8th Floor:
- Duct work has been cleaned.
- Test results have been received.
Two units required recleaning. New
results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Admin 2nd Floor:
- Duct work has been cleaned.
- Test results have been received.
Two units required recleaning. New
results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Admin 3rd Floor.
- Duct work has been cleaned.
- Test results have been received
and passed.
- The interior insulation has been
coated/encapsulated.
- The AHUs are operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Admin 4th Floor:
- Duct work has been cleaned.
- Test results have been received.
Two units required recleaning. New
results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Stairwell A has had the anti-microbial
coating applied.
- The project to upgrade the network
infrastructure continues to progress.
- All of the coring is complete and
sleeves have been installed on floors 2
through 7 in the Clinic building.
- All of the cable terminations have been
finished on the 2nd floor of the
Clinic Building
- The newly installed cable is being
terminated throughout the Clinic
Building.
- Boe-Tel is installing cable trays in
the ceiling of the Library and they
continue to pull cable throughout the 2nd
floor of the Administration Building.
- The build out of the closets themselves
and the installation of new racks in the
closets is underway throughout the building.
- The demolition of the old IT closets
is complete in the Clinic Building and
work has started in the Administration
building.
- The new closet walls have been
framed on the 2nd thru the 7th floors of
the Clinic Building.
- Drywall has been installed on
all the interior walls of these
closets.
- All of the new racks and plywood
back planes have been installed in the
new closets on the 2nd
through the 7th floors of the
Clinic Building.
- Rack installation began in the 6th
and 7th floors closets in the Clinic
Building.
- The construction of the new
network/telecom closets on the 2nd
and 3rd floors of the
Administration Building is underway.
- The newly installed cable is being
terminated throughout the Clinic Building
and in parts of the Administration Building.
- The contract to replace the ceiling tiles
and grid in the Clinic and Administration
Building is well underway.
- The installation of the new ceiling
grid, the lights, the HVAC flex duct and
diffusers, and the relocation of the
sprinklers to accommodate the new grid has
been completed throughout the two buildings.
- Electrical repairs to damaged lights
and junction boxes on the 6th
and 7th floors are complete.
- The new ceiling tile has been installed
throughout much of the 2nd through the 7th
floors of the Clinic Building.
- Installation is substantially
complete on Floors 2 thru 5.
- Floors 6 and 7 have more than half
of the tile installed.
- The installation of ceiling tile is
well underway on the 3rd and
4th floors of the
Administration Building and on the 8th
floor of the Clinic Building.
- Sheetrock is being installed at the
linear diffusers on the 5th floor
of the Clinic Building. This work will allow
the ceiling tile grid to be connected at
this location.
- The contract to restore the Central
Sterilization function in a 3rd floor
space has been awarded and the initial phase of
work has begun.
- The Central Sterilization demolition has
been completed. The installation of new
ducts and new piping is underway.
- Core drilling is complete and the
contractor is ready to begin framing the
walls.
- The sterilization units were delivered
to the site today. Crews were successful in
moving these large units to the new Central
Sterilization location on the 3rd
floor of the Clinic Building.
- The repairs to the exterior site lighting
and the electrical work necessary to power the
parking lot controls are continuing.
- Old subsurface wires have been pulled
and the damaged light standards have been
dismantled.
- New cables are being run to the light
poles.
- The replacement doors and frames needed for
the 1st floors of the two buildings
have been delivered and the installation work is
proceeding smoothly.
- A change order proposal to replace a number
of HVAC inline dampers in the buildings has been
received and approved.
- The contractor is ordering the needed
parts and materials.
- Installation is anticipated to begin
shortly.
- A change order proposal to make repairs to
the compressed air line running through the
utility tunnel from the Power Plant to the
Clinic Building has been received and approved.
- Work is underway on these repairs.
- The LSUHSC carpenters completed the work to
protect the antique dental equipment in the 3rd
floor Administration Building breezeway.
- LSUHSC Facility Services removed and
disposed of dead trees and damaged picnic tables
throughout the campus.
- The removal of demolition debris from the
4th floor Administration Lecture Halls A & B
continues.
- Chemical waste storage sheds were delivered
and placed behind the Power Plant.
- Representatives of a testing company arrived
on site to survey the roofs of the Clinic and
Administration Buildings for the presence of
moisture in the substrate.
- The presence and extent of moisture
below the waterproof layers of the existing
roofs will help to determine the extent of
the damage to the roofs.
- The survey work has been completed.
Results of the testing should be provided to
the architects shortly.
- The glass over the west vestibule of the
Clinic Building has been replaced. The glass in
the vestibule of the Administration Building has
also been replaced.
- Schindler Elevator has been working on
completing repairs to the three passenger
elevators in the Administration Building.
- MCC is installing the pipes for the new
cooling towers to be installed at the Power
Plant next week.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
- Ordes successfully tied-in a sub-panel that
feeds power to all "LNA panels" which provides
power to lights and receptacles in the NE
quadrant of the building.
- Ordes installed a new breaker to power
the "LW" panels in the NW corner of the
building.
- Ordes is in the process of verifying
that the power is available at these panels.
- Stratos Elevator was on site making a
materials list of the parts needed to complete
the repairs to Elevator #2.
- A portion of the needed parts and
materials have been delivered to the site.
- Stratos Elevator removed the cab from
Elevator #2.
- Emergency telephone lines for the
building elevators were being terminated at
the elevator control panel.
- Stratos installed new wiring for the
governor and other elevator controls on
Elevator #2 in preparations for a manual
run-test of the elevator.
- Stratos is now able to operate Elevator
#2 at slow speeds.
- This level of operation will only
allow the contractor to continue the
repairs to the elevator, but indicates
that the next level of repair work has
been reached.
- Arc Mechanical set auxiliary air compressor
#2 in place and they are making pipe connections
to the unit.
- Ordes installed the disconnect and
wiring for auxiliary air compressor #2 and
they are installing the wiring and
receptacle box for the auxiliary air dryer
#2.
- Ordes installed the 110V receptacles for
the auxiliary air dryers.
- Ordes checked the rotation of
auxiliary compressor #1 and made the needed
adjustments.
- Ordes installed two 110V feeds for the
drain valves of auxiliary compressors #1 &
#2.
- The main air compressor unit has been
delivered to the site, set in place and
preparations for the installation have
begun.
- Arc Mechanical is replacing the valve
actuators on the chilled water pipe runs.
- Siemens delivered and stored parts and
materials for the fire alarm panel and system
devices.
- Arc Mechanical is installing two condensate
return valves and a trap to the main condensate
line in the basement pipe chase.
- Ordes is installing conduit to provide
electrical power to the security station in the
parking lot.
- Ordes ran electrical cable and wires to
provide power to the security booth in the
L&M Lot.
- They have also installed the disconnect
switch on the side of the Medical School
Building across from the security booth.
Downtown Campus
Landscaping Project:
- Most of the work on all of the planting beds
surrounding the CSRB has been completed. Work
includes:
- Removal of all the old plant materials
and grass.
- Installation of the in-ground irrigation
system.
- Preparation of the soil for the new
plants and hand grading of the planting
areas.
- Installation of metal edging to define
the planting beds and grass areas.
- Planting of the large trees.
- Planting of large numbers of small
plants and shrubs.
- Mulching of the planting beds.
- Installation of new sod.
- Work on all of the planting beds surrounding
the Lions/LSU Clinic Building has been
completed. Work includes:
- Removal of all the old plant materials
and grass.
- Installation of the in-ground irrigation
system.
- Preparation of the soil for the new
plants and hand grading of the planting
areas.
- Installation of metal edging to define
the planting beds and grass areas.
- Planting of the large trees.
- Planting of large numbers of small
plants and shrubs.
- Mulching of the planting beds.
- Installation of new sod.
- Work on the planting bed surrounding the
memorial bench area between the CSRB and the
Lions/LSU Clinic Building has been completed.
Work includes:
- Removal of all the old plant materials
and grass.
- Installation of the in-ground irrigation
system.
- Preparation of the soil for the new
plants and hand grading of the planting
areas.
- Installation of metal edging to define
the planting beds and grass areas.
- Planting of the large trees.
- Planting of large numbers of small
plants and shrubs.
- Mulching of the planting beds.
- Installation of new sod.
- Channel drain has been installed along the
sidewalk adjacent to the Lions/LSU Clinic on the
Gravier St. side of the building. This will help
to control rain water runoff.
MEB Cafeteria Project:
- All of the new walls, including the curved
walls have been framed and most of the drywall
has been installed.
- Workers are installing additional
drywall; fitting it into the more
complicated areas of the new wall design.
- Taping the joints and applying joint
compound will follow.
- The interior partition wall has been framed
and is ready for drywall to be installed.
- The majority of the ceiling grid has been
installed.
- The custom, curved ceiling grid has been
delivered and is now being installed.
- This grid is designed and manufactured
to fit the particular curved dimensions of
the new walls in the cafeteria space.
- All of the new terrazzo floor material has
been poured and has dried.
- The contractor has begun the process of
finishing the newly poured terrazzo floors.
This is a multi-step process where the
surface is repeatedly ground down and
polished with increasingly finer abrasives
until the surface is completely smooth and
shines.
- This work is restricted to the evening
hours to minimize the noise, dust and
disruption of daily operations in the
building.
MEB Atrium:
- The new furniture (tables, chairs, etc.) has
been delivered to the MEB Atrium.
- The installers have unpacking and assembled
all of the new furniture pieces. They have been
set in place and are being used by students,
faculty and staff.
Student Parking Lot
Re-Surfacing:
- All of the concrete bumpers were removed
from both lots.
- Both lots have had any old paving material
and debris removed.
- Both lots have been graded; new base
material has been spread and compacted.
- Two layers of asphalt have been installed on
Student Lot #3.
- The contractor is now striping the lot
and installing the concrete wheel stops.
- Student Lot #2 has been graded and the
surface has been sprayed with tar to prepare it
for the application of the 1st layer
of asphalt.
CSRB Temporary Vivarium
Repairs:
- The contractor has begun work on the
project. The initial phase of demolition is
underway.
We encourage you to follow the details of our progress
through the daily updates which are posted on the web site.
|