|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #54
Posted: October 26, 2007
The proposal for the
permanent repairs and Section 406 Hazard Mitigation
of the Lions/LSU Clinic have been prepared, reviewed
and approved at the local level by FEMA. The
proposal has been forwarded to Washington, DC for
the final approval. Once approved at that level the
funds will be obligated. Concurrently, LSUHSC, the
LSU System and the Office of Facility Planning &
Control have been completing their reviews of the
construction documents. The final comments are due
to Facility Planning on 10/31/07 where they will be
consolidated and returned to the architects to be
incorporated into the final bid documents. We are
cautiously optimistic that this major project will
be out on bid prior to the Thanksgiving holiday.
The downtown campus design
team completed their conceptual packages for
permanent repairs and Section 406 mitigation to five
additional buildings or structures. The packages
have been forwarded to FEMA and GOHSEP for their
preliminary review. The next phase will be the
preparation of the Design/Development packages which
FEMA will use for their eligibility determinations.
The concepts proposed address 1542 Tulane Ave., the
Central Utility Plant, the District Energy Parking
Garage, the Roman St. Parking Garage, and the Walk
to Wellness.
Prices are currently being
solicited for the demolition of a number of
buildings on the back campus of the Dental School.
These buildings were determined by FEMA to have been
damaged by the storm and post-storm flooding to the
extent that repairs were not cost effective. The
buildings include the five Human Development Center
buildings, and some of the smaller buildings
previously used by LSUHSC Facility Services. The
solicitation of prices should be completed within
the next 10 days to 2 weeks, and contracts for the
demolition of these buildings will be issued shortly
thereafter.
The contract for the
replacement of the roof of the Medical Education
Building has been signed by all the parties. The
Notice To Proceed has been issued to the contractor
for November 19th and the preconstruction
meeting has been set for November 9th.
The project contemplates that the work will be
completed within a six month period, but we are
hopeful that the work may be completed in advance of
that deadline. Occupants of the building can
anticipate some inconveniences during the completion
of the work, but we will work with the contractor to
minimize the impacts.
Our emphasis on preparing
1542 Tulane Ave. to be partially re-occupied has
continued. The repairs to the building fire alarm
system are progressing on schedule. The repairs to
selected building elevators are also well underway,
although the contractor has been delayed by the
challenges of removing flood damaged elements that
were severely corroded. Still, two elevators are
certified for normal use and repairs are progressing
well on three others. The contract to complete the
final remediation and duct cleaning of the building
is on the street, the pre-bid conference was held
and bids are due on October 31st. We
would expect to award that contract in the near
future. Due to the extended period of time that the
building experienced high levels of humidity and
heat, a significant amount of paint has peeled off
various wall and ceiling surfaces. A painting
contract is already on site removing the damaged
paint, patching the surfaces, and priming and
repainting.
Work at the Dental School
has focused on the 1st floor lobby of the
Clinic Building, the 2nd floor conference
room in the Administration Building, and the repairs
to the building elevators. Much of the work in the
Clinic Building lobby has been completed. The
specialty ceiling is the main element that has not
yet been completed. The 2nd floor
conference room is progressing on schedule and four
additional elevators should be ready to be inspected
and certified in the near future.
The bids for the
replacement of the roofs of the main buildings on
the Dental School campus were opened on 10/23/07.
Eight bids were submitted ranging from $1,040,226 to
$1,487,000. The bids are being examined and
evaluated at this time and we hope to make an award
recommendation in the near future
The downtown landscaping
project has continued to show progress. Most every
day reveals new elements being completed around the
Medical Education Building and the Allied
Health/Nursing Building. The project to enhance
exterior security lighting has begun a new phase.
Lights mounted on the roof of the MEB are being
replaced with new brighter lights that will improve
the lighting of the pedestrian areas and streets
near the building.
The MEB Morgue work has
continued and is nearing completion. The contractor
is now focusing on completing the various start-up
procedures and insuring that all of the new
equipment is functioning properly. Work on the MEB
cafeteria continues to progress as well.
Here are highlights of
work that has been accomplished since our last
update was posted two weeks ago.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
- Fire Alarm System:
- Siemens pulled wires to all of the fire
alarm device boxes in the basement and on
the 1st floor.
- The contractor tied-in and programmed
the water flow and tamper switches on the
valves for the sprinkler system.
- Siemens is currently installing and
programming the fire alarm system smoke
detectors.
- The contractor installed the fire alarm
device back-up power supply boxes on Floors
1 - 8.
- Siemens has installed all of the fire
alarm speakers and strobes in the basement,
the mezzanine and 1st floor.
- Elevator Repairs:
- Current Status:
- #1 – Repairs are underway. Stratos
is demolishing the platform and pit
components.
- (Emergency phone line available)
- #2 – Certified for normal use, but
temporarily shut off until protection
for the interior of the cab can be
provided.
- (Emergency phone line available)
- #3 - Certified for normal use and in
operation.
- (Emergency phone line available)
- #4 – The scope of repair has
recently been determined.
- Additional documentation of the
storm-relatedness is being prepared
and the State Elevator Inspector
will review the scope of repair and
approved.
- It will then be forwarded to
FEMA for their review and comment.
- #5 (Old Library) – No activity. This
elevator was not in operation prior to
the storm and will not be put back into
service.
- #6 (Loading Dock) – No activity.
- #7 - Repairs are underway. Stratos
is changing the door track.
- (The availability of an
emergency phone line is not
determined.)
- #8 - Repairs are underway. Stratos
is changing the cab and replacing the
platform.
- (The availability of an
emergency phone line is not
determined.)
- Final Remediation and Duct Cleaning:
- Bid specifications have been developed
for the final remediation and duct cleaning
that is required within the building.
- The pre-bid conference was held on
October 16th. A large number
of potential bidders were in attendance.
- Bids are due to open on October 31st.
- The packing of office contents in
preparation for the remediation will begin
early next week.
- Painting: The extended exposure to heat and
humidity caused significant amounts of paint to
peel off the walls and ceilings in a variety of
locations throughout the building. A painting
contract has begun work to remove the peeling
paint and to patch and prepare the surfaces for
repainting.
- The painters have been working in
Stairwell C and all of the peeling paint has
been removed in the stairwell on floors 1
through 9.
- The painting contractor has primed the
handrails from floors 1 - 8 in the
stairwell.
- The contractor is priming and patching
the surfaces to prepare them for new paint
and they have already patched and primed the
stairwell on Floors 9, 8, and 7.
- Misc.
- The steam pipes are being tested for
leaks.
- The broken CHW lines that used to feed
the cafeteria units were capped and the
system has been refilled.
- Arc Mechanical worked on rewiring the
water softener.
- Ordes terminated and connected
electrical power to the wiring for the
Parking Garage lighting and the exhaust
fans.
- The contractor also continues to
pull wiring for the new HVAC controls.
- Ordes is installing the wiring for the
Parking Garage exhaust fan starters.
- The contractor is checking the exhaust
fans and Parking Garage lights to insure
that they are operating properly.
- Ordes continues to work on pulling wires for
the electronic controller (PLC) serving the
Energy Transfer Stations (ETS).
- Arc Mechanical is on site working on the
water softener.
- Entergy Thermal turned off the steam to the
building so that the leaks can that were
identified during the testing can be repaired.
- Ordes continues to install the wiring
required by the electronic controller (PLC)
serving the Energy Transfer Station (ETS).
- Ordes installed the control wiring for the
exhaust fans in the parking garage.
- They also installed the 110v wiring for
the heating hot water pumps.
- Ordes Electric Co has removed the pressure
switches for the Entergy Transfer Station and
has run the wiring for new pressure switches.
Project to Make Temporary
Repairs to the Dental School:
- 1st Floor Clinic Building Projects:
- The contractor has completed the
installation of the wood veneer throughout
the Clinic Building 1st floor
space.
- The curved ceiling features are being
installed in the 1st floor lobby.
- The contractor has started the
installation of the Curviture ceiling in
the elevator lobby.
- The ceiling tiles have been
installed in the vestibules.
- The recessed can lights have been
installed in the Composo ceiling near the
curved wall.
- The metal doors have been installed for
the mechanical room, the Facilities Office
and the Central Supply area on the Clinic
Building 1st floor.
- These replace the temporary plywood
doors that had been put in place to
secure the areas while waiting for the
delivery of the doors that had been
specified in the contract.
- The hardware for the doors has been
installed.
- The plastic laminate doors for the first
floor of the Clinic Building have been
delivered to the site.
- All of these doors have been
installed.
- The door hardware/locksets have been
installed.
- The air handling unit serving the
temporary Central Supply area has been
turned off because the drain used for
condensate is clogged and cannot be cleared.
- The assessment of repair options
continues.
- 2nd Floor Conference Room Administration
Building:
- Landis prepared the walls to begin the
sheet rock installation.
- The large viewing windows and the
concrete steps to the studio have been
removed which completes the demolition.
- All of the drywall has been hung and the
windows have been installed.
- The new drywall is being taped, floated
and prepared to receive paint.
- The viewing windows have been framed and
enclosed with sheet rock on one side.
- New duct work is being installed in the
conference room.
- The electrical rough in for the lights
and power outlets has been completed.
- Painting of the new walls has begun.
- Permanent Roof Replacement:
- The bids for the replacement of the
roofs of the main buildings on the Dental
School campus were opened on 10/23/07.
- Eight bids were submitted ranging from
$1,040,226 to $1,487,000.
- The bids are being examined and
evaluated at this time and we hope to make
an award recommendation in the near future.
- Elevator Status:
- Clinic Building:
- #1 – Certified for normal use and
fully operational.
- #2 – Certified for normal use and
fully operational.
- #3 – The new motor is being
installed.
- #4 – The new motor is being
installed.
- #5 – The repairs are close to being
complete.
- The elevator recalls and shunt
trip modules need to be installed.
- The telephone line for the
emergency phone must be installed.
- Administration Building:
- #6 – The repairs are completed.
- The telephone line for the
emergency phone must be installed
and the inspection can then be
scheduled.
- #7 - The repairs are completed.
- The telephone line for the
emergency phone must be installed
and the inspection can then be
scheduled.
- #8 – The repairs are approximately
90% complete.
- Miscellaneous:
- Some of the damaged laminate wall panels
on the 2nd floor of the Clinic Building were
replaced with sheet rock and will be painted
to match the color of the panels in the
area.
- Work on the temporary repairs to the
flood wall surrounding the loading dock ramp
into the basement has been completed.
- The library books that were removed from
the Dental School library shortly after the
storm, cleaned and stored until the building
was ready to be reoccupied are now scheduled
to be returned to the Dental School early
next week.
Lions/LSU Clinic Permanent
Repairs & Mitigation:
- LSUHSC has been completing their review of
the construction documents for the proposal to
make permanent repairs to the building and to
elevate the Cohn Learning Center to the 6th
floor and the critical mechanical, electrical
and plumbing equipment to the 2nd
floor.
- FEMA is evaluating the cost data that
has been submitted to insure that the
estimates represent "fair and reasonable"
figures.
- The versions to the related Project
Worksheets have been written and submitted
for internal reviews by FEMA.
- The internal FEMA reviews have been
completed and the project has been forwarded
to Washington, DC for the final approval and
the obligation of funds.
MEB Roof Replacement:
- The contract for the replacement of the roof
of the MEB has been signed and the contractor
has been issued the Notice to Proceed effective
November 19th.
Downtown Campus
Landscaping Project:
- The crews completed making the drain pipe
connections in the catch basins.
- All of the garden edging has been installed
on the Gravier St. side of the Allied
Health/Nursing Building and the grading has been
finished.
- All of the plants have been installed in
the graded beds.
- All of the sprinkler nozzles on the Gravier
St. and Bolivar St. sides of Allied
Health/Nursing Building have been installed.
- Crews started trenching for the irrigation
piping and wiring on the Bolivar St. side of the
MEB.
Cafeteria Project:
- The counter top for the feature wall has
been installed.
- Advanced Millwork continues to work on the
installation of the booths on the elevated deck
at the rear of the cafeteria.
- The contractor is installing cove base and
building the steps for the raised platform.
- The general contractor continues to work on
a variety of punch list items.
MEB Morgue:
- The project is nearing completion.
- The contractor continues to work on
start up of the new condensing units.
- The contractor continues to work on
addressing the remaining punch list items.
Permanent Building Repairs
and 406 Hazard Mitigation:
- The design team prepared and submitted their
initial design concepts for the permanent repair
and 406 Hazard Mitigation of five additional
buildings/structures. Those buildings are:
- 1542 Tulane Ave.
- Central Utility Plant
- Roman St. Garage
- District Entergy Garage
- Walk To Wellness
- The design concepts are currently under
review by the 406 Hazard Mitigation team with
GOHSEP and by LSUHSC.
Allied Health Flooring
Enhancement:
- A project to enhance the appearance of the
floors within the School of Allied Health is
underway. The old tile is being removed and new
tile installed. The new tile will enhance the
appearance of the hallways and rooms, and will
be easier to maintain.
- The installation of the new floor tile
and wall base molding on the 6th Floor has
been completed.
- The contractor is addressing the
punch list items.
- The old floor tile has been removed from
the 7th floor and the sub-floor
has been patched and prepared to receive the
new floor tile.
- The new floor tile has been installed in
the 7th floor Elevator lobby and in all of
the corridors.
- The base molding is currently being
installed.
Exterior Lighting Project:
- As part of the project to enhance the
exterior lighting around the campus, new
exterior can lights are being installed
on top of the MEB in the area on the corner of
Perdido St. and Bolivar St.
- The demolition of the old lights has
started on top of the area on the corner of
Perdido and South Roman Streets.
We encourage you to follow
the details of our progress through the daily
updates which are posted on the web site.
|