|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #60
Posted: January 18, 2008
With the winter holidays
behind us, work has resumed at full speed on the
various projects around the campus. There has been
an intense focus on completing temporary repairs to
1542 Tulane Ave. over the past months. This
continues as the final remediation and cleaning
contract is well underway and spaces are being
readied to be reoccupied. The fire alarm replacement
is nearing completion and the elevator repairs
continue. The contractor who held the main contract
for all the temporary repairs is completing their
work on the punch list.
The re-roofing of the MEB
has been underway for approximately a month now. The
contractor has made good progress. The recent
discovery of some concealed damage on the roof
resulted in the execution and approval of 4 modest
change proposals.
We are also just beginning
the work to replace the roofs of the Dental School’s
Clinic Building, Administration Building, and the
Power Plant. The contractor has been receiving
materials for the job on site, and they have begun
the initial demolition of the old roof of the Clinic
Building. The current plan is to complete the Clinic
Building, followed by the Administration Building
and then the Power Plant.
Over the holiday period,
the contractor who was awarded the Lion’s/LSU Clinic
Building project received the contract documents,
gathered up their information, and were able to
return the documents to the Office of Facility
Planning & Control recently. We expect that the
Notice to Proceed will be issued shortly.
The emphasis on safety
around the campus continues. All of the bollard
lights that line the sidewalks of the downtown
campus have been replaced and are operating. A
number of exterior lights on the buildings have been
replaced with brighter lights that improve the
lighting in the area. New and enhanced lighting is
planned for three more of the parking lots on campus
and this project has just begun.
We believe that FEMA is
close to making formal recommendations to accept our
Design/Development proposals for Section 406 Hazard
Mitigation and permanent repairs at the Resource
Center and the Residence Hall. They are also
reviewing the D/D submission for the Allied
Health/Nursing Building and we remain optimistic
that this will also be recommended. Finally, our
Design Concept for the Section 406 Hazard Mitigation
and permanent repairs to the CSRB and MEB is drawing
significant attention. We’ve been asked to provide a
variety of additional information that we hope will
allow FEMA to support this concept as well.
Contracts for the
demolition of nine buildings on the back campus of
the Dental School were recently sent out by the
Office of Facility Planning and Control to the three
contractors who won the jobs. As soon as the
contract documents are executed, the Notices To
Proceed will be issued and the demolitions will
begin. We will communicate the starting date(s) of
these contracts as soon as we receive notice.
Here are highlights of
work that has been accomplished since our last
update was posted two weeks ago.
Repair Work at 1542 Tulane
Ave.:
- Fire Alarm System:
- Siemens completed the installation of
new fire alarm wires on the 8th Floor for
the new fire alarm speakers and strobe
boxes.
- The contractor has established a
stable connection between the new fire
alarm panel and the 8th Floor devices.
- They have also established a stable
connection between the fire panel and
the devices in the basement, and the
mechanical and animal care spaces on the
roof.
- The contractor replaced damaged wiring
on the 7th Floor and is pulling new fire
alarm wiring on the 6th Floor.
- Siemens connected the flow switches to
the sprinkler piping in Stairwell D.
- The contractor is pulling the main fire
alarm communication trunk/riser through the
pipe chase from the 1st Floor to the 8th
Floor.
- Siemens is trouble-shooting the fire
alarm wiring on the 1st Floor.
- Elevator Repairs:
- Elevator #1:
- The cab has been delivered to the
site.
- The new doors for the elevator have
been installed.
- New door hangers and track have been
installed.
- New governor cables are being
installed.
- Elevator #7:
- The cab station is being wired.
- Elevator #8:
- The contractor is working on the
wiring for the elevator.
- They are also wiring the cab
station.
- Stratos has installed the buffers.
- Final Remediation and Duct Cleaning:
- Duct Cleaning Status:
- The contractor moved their night
crew to the 6th Floor to begin coating
the HVAC ducts.
- Crews have finished
encapsulating the ducts on the 6th
Floor.
- Crews have also finished
encapsulating the ducts on the 5th
Floor.
- They are working on encapsulating
the 8th Floor ducts.
- Carpet Removal:
- All of the carpet has been removed
from the 3rd Floor.
- The contractor finished removing
carpet on the 2nd Floor.
- Debris Removal:
- Zimmer finished removing building
debris, ACM countertops, lab benches,
and building debris from the 3rd Floor.
- They have also finished removing the
countertops, lab benches, and building
debris from the 2nd Floor.
- The contractor began removing
building debris in the rear of the
building (the old section) on Floors 5 -
8.
- Final Remediation/Cleaning/Painting:
- Zimmer finished removing the peeling
paint on the 3rd Floor and has begun
cleaning in the corridors and rooms
along the Tulane Ave. side of the
building.
- Zimmer-Eschette completed the
initial cleaning down the center
corridor of the 4th Floor.
- The 4th Floor failed
the visual inspection and is being
re-cleaned.
- The contractor continues to
remove the peeling paint in the
corridor and rooms along the Tulane
Ave. side of the building.
- The 5th Floor was re-cleaned and
visually inspected.
- The floor passed the visual
inspection and was re-sampled for
mold.
- The 7th Floor failed the visual
inspection due to the overspray of
encapsulant.
- The contractor is removing the
overspray.
- The contractor has begun
floating the walls.
- The painting contractor finished
floating the walls on the 1st and 8th
Floors.
- They are painting the 8th Floor
walls and priming the 1st Floor.
- Ceiling Tile Removal:
- The remaining ceiling tile has been
removed from the 2nd Floor.
- The contractor finished removing
ceiling tile on the 3rd Floor.
- Floor Tile Removal:
- The contractor has removed all the
damage floor tile from the 8th Floor.
- The floor passed the visual
inspection.
- All the damaged tile has been
removed from the 7th Floor.
- The floor passed the visual
inspection.
- The night crews have removed all of
the damage tile from the 6th Floor.
- The tile has been removed from the
4th Floor corridor.
- The contractor began removing
the floor tile from the 4th Floor in
the "A section".
- Sample Results:
- Ducts on the 3rd Floor were cleared
with the exception of a fan coil.
- Fan coil 331C is scheduled for
re-cleaning.
- All ducts on the 4th Floor have been
cleared.
- Ducts on the 6th Floor were cleared
with the exception of a fan coil.
- Fan coil 609M is scheduled for
re-cleaning.
- Air samples taken on the 4th Floor
passed.
- Air samples for the 5th Floor failed
to be cleared and re-cleaning will be
required.
- The 5th Floor has now passed
clearance for mold testing, except
for Rooms 550, 531, 556 and 557.
- Air samples for the 6th Floor were
cleared except for a couple of rooms
that are scheduled to be re-cleaned.
- The 5th Floor passed clearance for
lead testing.
- Suite 122C passed TEM clearance
following the removal of the floor tile.
- The 7th Floor passed TEM clearance
related to the removal of the asbestos
floor tile.
- TEM (Transmission Electron
Microscope) samples were taken in Rooms
867 and 865 on the 8th floor.
- Room 866 passed TEM clearance
related to the removal of the asbestos
floor tile.
- The 6th floor passed TEM clearance
for asbestos floor tile removal.
- Network Closets:
- Trison Construction is framing the walls
of the new network closets in Rooms 126 and
455.
- This is a part of the project to
enhance the network infrastructure in
the building that began prior to the
hurricane.
- The contractor installed sheet rock for
the new network closet walls in Rooms 126
and 455.
- The contractor removed demolition debris
in Room 356.
- The framing for the network closet in
Room 356 is finished and sheetrock has been
installed.
- Trison finished installing sheetrock for
the new network closet in Room 357 and 357A.
- Trison Constructors relocated the
sprinkler heads in the new network closets
(Rms. 126/126A, 357, and 455).
- The contractor has installed the plywood
backboard in Room 455.
- Boe-tel is removing the old network
wiring and is pulling new network wires on
the 7th Floor.
- Trison Constructors installed the
required electrical utilities for the 4th
Floor network closet (Rm. 455).
- The contractor also installed the
plywood backboard for the 3rd Floor network
closet (Rm. 357A).
- AT&T is working on relocating the demark to
the 2nd Floor.
- Misc. Electrical and Mechanical Repairs:
- Ordes continues to work on the
outstanding punch-list items.
- Ordes is making a panel schedule for the
electrical panels in the basement.
- Insulators from Arc Mechanical are
insulating some domestic water and chilled
water lines.
Repair Work at the Dental
School:
- Roof Replacement:
- The contract to replace the roofs on the
main Dental School buildings has been
executed.
- The Notice To Proceed was issued for
January 7, 2008.
- A pre-construction meeting was held on
January 8, 2008.
- Needham Roofing delivered materials and
equipment to the site as they prepared to
begin the roof replacement project. They
began work on the Clinic Building roof.
- They lifted the roofing materials by
crane onto the roof of the building.
- Needham Roofing completed the demolition
of the penthouse roof on the Clinic Building
and removed the debris from the roof.
- They have removed 10 squares of the
old material down to the concrete deck.
- They sealed all penetrations in the
area; installed blocking where needed
and covered roof drains to prepare for
the installation of the new material.
- Once completed, they installed the
first ply of the roofing membrane.
- Temporary Bookstore:
- The contractor disconnected the
electrical wiring in the demolished walls.
- They removed the metal stud wall from
the interior of the new bookstore space.
- The layout of the vestibule walls for
the temporary bookstore is finished.
- The metal stud framing for the temporary
bookstore walls is complete.
- The rough in electrical work has been
finished.
- Dry wall is being installed on the
walls.
- They have installed the duct board and
flex duct for the supply air and return air
to the temporary bookstore area as well as
the existing adjacent rooms.
- Elevator Repairs:
- Schindler adjusted the cab, door
operator and call buttons for Elevator # 3.
- They remounted the door operator for
Elevator # 3 and adjusted the doors.
- Schindler dismounted and readjusted the
cab and door operator for Elevator # 4 to
allow for a smoother operation.
- They developed a punch list on the
freight elevator in preparation for the
certification inspection.
- Schindler Elevator adjusted the doors on
the freight elevator and adjusted the fire
service circuitry.
- Misc.
- Trison Constructors completed the
demolition of the existing duct work in the
basement and 1st Floor that had
served as the oven exhaust.
- They began the installation of the
new ducts in the basement and on the 1st
Floor.
- Securitas ran coax cables for the
intercom system to the front desk located in
the Clinic Building, 1st Floor lobby.
Exterior Lighting Project:
- All of the new bollard lights lining the
sidewalks on the downtown campus have been
installed and are working.
- New can lights have been installed at the
Resource Center.
- The twelve new lights on the exterior of the
MEB have been installed.
- Mesh has been installed at locations of
the MEB that require re-plastering where
holes had to be cut for the new can lights.
- New exterior lights are being installed
around the perimeter of the Allied
Health/Nursing Building.
- The installation of new entry lights is
complete.
- The contractor cut the last of the
access panels on the Allied Health/Nursing
Building.
- They are now installing the new lights
at those locations.
- Frischhertz started mobilizing crews and
materials for the installation of new lights in
the 440 parking lot, Student Lot #1, and the
Residence Hall lot.
MEB Roof Replacement:
- The contractor completed installing the
temporary roof on the Bolivar St. and the
Perdido St. corner of the building.
- The contractor has completed a signification
portion of the temporary roof on the Perdido
Street side of the roof and is moving to the
Allied Health/Nursing side of the building.
- They have completed demolition of the
lightweight ballast on the Allied Health/Nursing
side (on top of the boilers) and have started
priming that section of roof.
- The temporary roof is complete in the area
of the boiler exhaust and the emergency
generator.
Landscaping Project:
- Trenching for additional irrigation pipe is
underway.
- Crews starting on the Bolivar St. side
of the MEB and they are working around the
corner to the Perdido St. side of the
building.
- Crews installed irrigation piping and
sprinklers along the Bolivar St. side of the MEB
and around the corner on Perdido St.
- Crews continued installing irrigation piping
and sprinklers and covering the trenches on the
Perdido St. side of the MEB.
- They completed one station and are close
to completing the other.
- Crews also trenched for two additional
irrigation stations mid-block on the Perdido St.
side of the MEB.
- The crews completed the installation of
another irrigation station on the Perdido St.
side of the MEB.
- New sod has been laid on the S. Roman St.
side of the Allied Health/Nursing Building. This
completes the landscaping of this building.
- Sod was also laid at the corner of the MEB
at the intersection of S. Roman St. and the
entrance/exit to the MEB loading dock area.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|