|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #64
Posted: March 14, 2008
We continue to focus on
completing the work necessary to allow us to
reoccupy the front and center portions of 1542 Tulane Ave. The duct cleaning project is nearing
completion. The removal of peeling paint (a result of the
extended exposure to heat and humidity) and the
final cleaning/remediation is complete throughout
the Tulane Ave. side of the building and the
center corridor. This work is nearing completion in
the old section of the building.
The repainting that was needed
has been more extensive that initially contemplated. This was further aggravated by the discovery
of mold in the drywall behind the base molding in
many parts of the building. The molded drywall has been removed and new
drywall installed, taped and floated. A significant portion of the damaged floor
tile that contained asbestos has been removed from
the building. Ceiling tiles are being replaced and ceiling
grids are being cleaned and repainted as necessary.
The contractor responsible for
the majority of the repairs to the multiple building
systems at
1542 Tulane Ave. recently
completed a walk though of the building with the
architects and a punch list has been developed. One electrical panel that provides power to
selected air handlers was found to have been missed
by the engineers and it does not yet have power
provided to it. This should be corrected quickly.
We were pleased to be able to
sign off on the Project Worksheet (PW) versions and
the related Section 406 Hazard Mitigation proposals
for the Allied Health/Nursing Building and the Resource Center
recently. These documents have been submitted to the
various review queues within the FEMA offices in Louisiana. They will also be reviewed in Washington, DC
due to the amount of the Federal funding involved. We are confident that both projects will be
approved and funds obligated. The design team is already at work on the
Construction Documents for both of these buildings. We would anticipate seeing similar documents
for the Residence Hall within the next few weeks.
The Design Concept for the
permanent repairs and Section 406 Hazard Mitigation
to the MEB and the CSRB (a combined building
proposal) is being routed internally within FEMA. Its complexity and sophistication have drawn
additional attention from FEMA, but we remain
optimistic that the concept will be found to be
acceptable. We recently received the Design/Development
documents from the design team on this project and
they are under review at this time. This package of documents will become the
basis of the final and formal review, approval and
obligation of funds by FEMA.
During the past week, FEMA
received the Design Concept for the permanent
repairs and Hazard Mitigation of the
Dental School Clinic Building, Administration Building
and the Power Plant. This is another proposal that combines
multiple but related buildings into a single
proposal. The plan is highlighted by the construction
of an annex to the Clinic Building that will house critical
functions that were previously located on the 1st
Floor of the Clinic
Building, as well as
critical mechanical, electrical and plumbing
equipment that was originally located in the shared
basement spaces. Early indications are that the benefit/cost
analysis of this project should be very favorable,
so we are optimistic that the concept will be found
to be acceptable by FEMA.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- Construction Masters, Inc.
continued the demolition of the interior spaces
on the 7th Floor.
-
CMI has removed all of the items that were to be
thrown away from 6th Floor.
- The ceiling demolition is
underway on the 6th Floor.
- The removal of cabinets
and built in service desk areas that were
attached to building on the 6th Floor is
underway.
Other Permanent Repair and
Mitigation Projects:
- The FEMA Health & Research
team has completed preparing the PW versions and
Section 406 Hazard Mitigation recommendations
for the Resource Center and the Allied Health/Nursing
Building.
- LSUHSC and the Office
of Facility Planning and Control have signed
off on the recommendations and they are
being submitted for review within FEMA which
should lead to their formal approval and
funds being obligated.
- The Dental School
design team has completed their work on the
Design Concept for the permanent repairs and
Section 406 Hazard Mitigation for the Clinic Building,
the
Administration
Building and the
Power Plant. This combined proposal was recently
submitted to FEMA for their initial review and
comments.
Repair Work at
1542 Tulane Ave.:
- Fire Alarm System:
- Siemens finished
pulling new wires and connecting them to the
fire alarm devices on the 3rd Floor along
the
Tulane Ave.
side of the building and down the center
corridor.
- The 3rd Floor fire
alarm wiring in the old section has been on
hold until the remediation is complete.
- With the recent
completion of the final cleaning and
mitigation in the area, Siemens resumed
the installation of the new fire alarm
wiring and devices on the 3rd Floor in
the old section of the building on the Charity Hospital
side.
-
Siemens finished the installation of new
fire alarm wiring and devices on the 3rd
Floor in the old section of the building
on the I-10.
-
Siemens finished pulling new fire alarm
wiring and terminating the wiring at the
alarm devices on the 4th Floor in the old
section on both sides of the building.
- Siemens has started
pulling new wiring and connecting the fire
alarm devices on the 2nd Floor along the
Tulane Ave.
side of the building.
- Elevator Repairs:
- Elevator #1:
- Stratos Elevator
wired the controls for the elevator.
- The contractor has
load tested the elevator.
- They are
run-testing and calibrating the elevator
in preparation for requesting an
inspection.
- Elevator #2:
- Stratos Elevator returned Elevator #2 to active service.
- Elevator #7:
- The Position
Indicator devices for the elevator have
been installed on the 1st Floor.
- Elevator #8:
- The Position
Indicator devices for the elevator have
been installed on the 1st Floor.
-
Stratos Elevator has installed a new
electrical disconnect for Elevator #8.
- Miscellaneous Elevator
Repairs:
- Stratos installed
the elevator monitoring station in the
University Police office on the 1st
floor.
- Stratos cleaned
the granite walls in the elevator
lobbies of Elevators #1, #2, & #3.
- Stratos changed
all of the damaged light bulbs for the
Position Indicators on all floors for
Elevators #1, #2, & #3.
-
They are sealing the penetrations in the
elevator control room for Elevators #1,
#2, and #3.
- Final Remediation and Duct
Cleaning:
- Duct Cleaning Status:
-
Zimmer-Eschette
began coating the duct interiors and
sealing the access holes cut into ducts
on the 1st Floor in the old section of
the building.
- Remediation:
- Zimmer finished
cleaning on the 3rd Floor in the old
section of the building on the Charity Hospital and on the Interstate 10
side.
- The 3rd Floor passed the visual inspection and air samples were taken.
- They are in the
process of cleaning on the 2nd Floor in
the old section on the I-10 side of the
building.
- All the
peeling paint was removed from this
part of the building.
- The contractor has
begun removing the peeling paint on the
2nd floor (old section) on the Charity Hospital side of the building.
- Drywall Replacement:
- The contractor
finished floating and preparing the new
sheetrock on the 4th Floor for paint.
- Crews continue to
install new sheetrock on the 3rd Floor.
- They are
floating, sanding and preparing the
walls for paint as they complete the
installation of the new sheetrock.
- The contractor is
sanding and prepping the walls and new
sheetrock on the 2nd Floor.
- Painting:
- The painting
contractor completed applying the finish
paint in the offices on Floors 5 through 8.
- The painting
contractor completed applying touch-up
paint in the offices on Floors 5 through
8.
-
The contractor continues to trim around the
windows and walls on the 3rd Floor.
-
They are applying the finish paint on the
4th Floor in the corridor along Tulane Ave.
- Floor Tile Removal:
- Zimmer finished
removing floor tile on the 7th Floor in the
old section of the building.
-
The contractor finished removing floor tile
from the 6th Floor in the old section.
- The contractor
finished removing floor tile on the 5th
Floor in the old section of the building on
the Charity side.
- The 5th Floor
passed visual inspection and samples
were taken.
- The contractor
finished removing floor tiles in the
stairwells along the Tulane Ave. side of the building.
- Ceiling Tile Replacement:
- The contractor
finished painting and trimming the ceiling
grid on the 5th through the 8th Floors.
-
The crews finished painting the ceiling grid
on the 1st, 2nd, 3rd and 4th Floors.
- The contractor is
installing new ceiling tiles on the 6th
Floor.
-
Network Upgrades:
- Trison Constructors
installed the new 30A NEMA - L6 power outlet
for the network closet on the 6th floor
(Room 655).
Repair Work at the Dental School:
- Permanent Roof
Replacements:
- The contractor has
completed the installation of the 1st ply of
the new two ply system on the roofs of the
Clinic and Administration
Buildings.
- They are testing for
water intrusion into the underlying layers
of the roofing system that might have
resulted from the leaks during the heavy
rains in February.
- The contractor has
been asked to prepare and price three
additional cost proposals.
- Sealing gaps
discovered at the parapet walls.
- Removal of two
exhaust vents no longer in use on the Administration
Building
roof.
- Addressing new
penetrations in the roofs that will
accommodate new security cameras and
related wiring.
- Work is expected to
begin on the Power Plant roof next week.
- Temporary Bookstore:
- Sherlocks Construction
completed the installation of the storefront
at the main entrance to the temporary
bookstore.
- They completed the
painting in the vestibule, installed the
door hardware on the entrance doors to the
side offices, and painted the door frames.
-
Sherlocks waxed the tile floors in the
vestibule near the temporary bookstore and
moved the Kell's Exhibit into position at
the right of the entrance.
- They received and
installed the new circuit panel recently
which provides power to the temporary
bookstore and several outlets on the north
side of the Library.
- Sherlocks cored the
holes in the floor to run power to the cash
registers from below.
- Elevator Repairs:
- Elevator #8:
- Schindler
installed the top and bottom limiters on
the elevator.
- Schindler
continued adjusting the equipment and
the ride of the elevator.
- The metal panels
have been installed inside the elevator
cab.
- Freight Elevator:
- Repair parts
needed to address the water damage from
the roof leaks have been ordered.
- Demolition:
- HDC Building
119 (Barracks)
- Work not yet
started. Contract Completion – On or
before 3/21/08.
- HDC Administration
Building 138
(Barracks)
- Work not yet
started. Contract Completion – On or
before 3/21/08
- HDC Building
124 (Day Care)
- Building and slab
removed.
- A water leak from
an old pipe is being repaired by the
N.O. Sewerage and Water Board.
- Final grading and
seeding has been completed.
- Contract
Completion – On or before 4/11/08.
- HDC Building
180 (Library)
- Building and slab
removed.
- Final grading and
seeding has been completed.
- Completion – On or
before 3/14/08.
- Time extension may
be requested.
-
HDC
Building 100 (Storage Building)
- Work not yet
started.
- Contract
completion – On or before 4/25/08.
- Storage Barn
- Building removed.
- Grading work
remains to be done.
- Contract
completion – On or before 3/14/08
- Time extension may
be requested.
- Disposal Facility
- Work not yet
started.
- Hazardous
materials are still locked in the
building and LSUHSC is handling the
disposal.
- Contract
completion – On or before 4/25/08.
- Auto Shop
- Work not yet
started.
- Contract
completion – On or before 4/25/08.
- Green House
- Structures and
foundation removed.
- Grading and
seeding remains to be completed.
- Contract
completion – On or before 3/14/08.
- Time extension may
be requested.
-
Security:
- Securitas continued
working on the installation of new security
equipment at the Clinic Building.
- The intercom
system has been installed with speakers
at each entrance to the Clinic Building.
- Crews are working
on installing the cameras that will be
located at the building entrances.
- They installed
the cameras and the intercoms at the
loading dock and at the Clinic Building entrance facing Navy Pkwy.
- Securitas wired the
security cameras mounted on the four corners
of the Clinic Building roof and the cameras are
operational.
-
Misc.:
-
The temporary ATM has been installed outside
of the Administration Building elevator
lobby on the 3rd Floor breezeway.
-
It is not yet in service.
MEB Roof Replacement:
- Crawford has completed
installing the new wood on the perimeter of the
parapet wall on the main roof.
- They have completed
installing the flashing that overlaps the wood
around the parapet wall.
- The crew has replaced all
of the roof drains on the main roof and started
working on the drains located on the roofs of
the penthouses.
Downtown Landscaping Project:
- Crews completed the
installation of the irrigation pipe and
sprinklers on the Perdido St. Side of the
Residence Hall.
- They installed the
wiring for the electric irrigation valves.
- The installation of
irrigation pipe and sprinklers on the Bolivar St. side of the Residence
Hall has started.
- Crews installed one
half of the 2nd irrigation station on the
Bolivar St. side of the Residence Hall.
- Crews completed the
installation of the electric irrigation
valve control wire to the location where it
will enter building for connection to the
controller.
- They installed the
irrigation controller for the Pocket Park
located in Student Parking Lot # 2 and connected
the control wires to the valves and the
controller.
- Two holes were bored in
the Residence Hall concrete wall on the Bolivar St.
side.
- One was for the
irrigation control wires and the other for
the electrical conduit serving the new
bollard lights.
- Conduit was run
through both holes and connections were
completed.
- The irrigation wires
were pulled inside of the building.
- The control wires for
the Residence Hall irrigation valves were
connected to the controller located in the
'C' Tower laundry room.
- Power was connected to the
irrigation controller for the Pocket Park in
Student Lot # 2 and the controller was
activated.
- Water was run through
the Pocket Park irrigation stations to flush
the pipes and sprinklers preparing for the
installation of the sprinkler heads.
-
Crews installed a 20 ft. 'Drake' Chinese
Elm in the Student Parking Lot # 2 Pocket Park.
- They installed nozzles
on the sprinklers and activated the system
to water the tree automatically three times
daily.
- Crews completed preparing
holes in the MEB and Allied Health/Nursing
sidewalk planters for the installation of new
trees next week.
Downtown Campus – 1st Floors:
- The State Fire Marshal has
required that we take measures on the unoccupied
1st Floors and basements of the buildings on the
downtown campus. This work will insure that the existing
sprinkler systems will function properly while
we wait for the permanent repairs to be
designed, bid, contracted and completed.
- In the majority of the
buildings, the most cost effective method of
accomplishing this goal is to re-install
ceiling tiles into the existing ceiling grid
on the 1st Floor.
- Trison completed
installing the temporary ceiling tiles in
the MEB, the Residence Hall, the CSRB, the
Resource
Center and the
Allied Health/Nursing Building.
- Trison completed the
installing ceiling tile in the front portion
of the Lions/LSU Clinic Building on the
Bolivar and
Gravier Street
side of the building.
- Installation of
ceiling tile continues on the back side near
the loading dock area.
- Trison continues to
install ceiling tiles in the last 5 rooms
(by the loading dock area) and in the lobby
on the 1st floor of the Lions/LSU Clinic
Building.
Exterior Lighting Project:
-
Frischhertz has installed the new electrical
service at the exit of the 440 Perdido St.
parking lot and three of the new light poles are
connected and lit.
- Frischhertz has aiming
the new lights that were installed in the
parking lot.
- The old lights in the 440 Perdido St.
lot that were mounted under Interstate 10 have
been removed.
- The new lights are
being installed in the same locations.
- Frischhertz pulled the
electrical cable in Student Parking Lot #1 and
dressed out the poles in preparation for their
installation.
- All of the new light
poles in Student Lot #1 have been wired.
- The new electrical
service is being built at the entrance to
the lot.
- The switch over to the
new service should take place early next
week.
- The electrical conduit for
the new bollard lights on the Perdido St. side of the Residence
Hall has been installed.
- The contractor removed all
of the mud and debris from the light pole sites
at Student Lot #1, the
440 Perdido St.
Lot, and the Residence Hall Lot.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|