From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #70
Posted: June 6, 2008
Work on the contract to make
permanent repairs to the Lions/LSU Clinic Building;
elevate the Learning Center
to the 6th Floor, elevate critical mechanical,
electrical and plumbing systems to the 2nd Floor,
create lab space on the 7th Floor and construct an
exterior stairwell is progressing on schedule. The interior walls on the 2nd, 6th, and 7th
Floors have been framed up and sheetrock is being
installed. The rough in work on the electrical systems,
mechanical systems, and plumbing systems in the
Learning Center and 7th Floor lab
is well underway. The front of the building has recently been
fenced off, landscaping removed and the exterior
slab is being demolished in preparation for the
construction of the exterior stairwell.
Several contractors continue to
complete work in preparation for reoccupying
portions of
1542 Tulane Ave. The final cleaning and remediation work
continues, new light fixtures are being installed,
and new flooring in being laid. The grinding and polishing of the terrazzo
floors on upper floors is underway and new window
coverings (mini-blinds) are being installed. Repairs to Elevator #7 are also moving
forward.
A number of new projects have
gotten underway since the last update was published. Upgrades to the MEB Lecture Rooms A and B
have started. This project will include the replacement and
enhancement of existing audio/visual equipment that
will provide state of the art presentation quality
in the rooms. Included in the plans are a new audio system,
connection to the Access Grid, new recording
equipment, and an enhanced lectern that allows for
easy reconfiguration of A/V to suit presentation
needs.
The planned renovations of the
MEB 2nd Floor elevator lobby began with a
significant amount of demolition. This project is converting the area into
lounge seating on carpeted islands for students
awaiting class or with furniture removed for
receptions. It will expand the available space by
removing existing Facility Services offices, and
will include new ceilings, wall surfaces, flooring
and furniture.
The Resource Center Library
Commons renovation project is also well underway. A significant amount of the demolition has
already been completed. This project creates an interactive student
study area and lounge, complete with a Coffee Kiosk. There will be two study rooms with large flat
screen displays with IT connections that will enable
student group study or the joint development of
class projects. The entryway feature displays for historic
and artistic pieces. When complete, this space will be available
24 hours a day.
The lobby on the 2nd Floor of
the Residence Hall is undergoing an expansion. Plans include the extension and enclosure of
the Residence Hall end of the walkway leading to the
MEB, the installation of new lobby flooring, and new
store fronts that will enlarge the existing lobby
area. New casework has been ordered for the planned
renovations to Multi-Disciplinary Lab #5.
At the
Dental School, significant portions of the
new roofing material that was installed on the Administration Building has been removed and replaced to
address the penetration of moisture that occurred
during the roof replacement project. Additional moisture testing is planned to
insure that any other areas that require replacement
are identified and addressed. All of the upgrades to Elevator #2 have been
completed and the elevator has been returned to
normal use.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- The dry flood-proofing of
the elevator pit that serves Elevator #2 and #3
is underway and progressing on schedule.
- CMI is working on the
plumbing systems, mechanical systems, electrical
system, sheetrock installation, and fire
sprinklers throughout the 6th Floor.
- Preparing for the
construction of the exterior stairwell, plants
were removed along Gravier side of building and
the granite panels were removed from adjacent
column.
- Temporary fencing has
been installed around the construction area.
- The removal of the
exterior slab that runs in front of the building
in the location of the new exterior stairwell
has begun.
- Sheetrock is being
installed on the new interior walls on the 2nd
Floor.
- CMI is working on the
plumbing in the new laboratory on the 7th Floor.
Repair Work at
1542 Tulane Ave.:
- Elevator Repairs:
- Stratos finished
installing new rollers for Elevator #7.
- They replaced a
defective safety on the same elevator.
- Stratos installed the
electronic infrared door sensors for
Elevator #7.
-
Stratos installed the TLS (terminal limit
switch) on Elevator #7.
-
This is an additional safety which
measures the speed of the cab.
- Stratos installed the
door guides for Elevator #7.
- Stratos is changing
out the travel cables for Elevator #7.
- Final Remediation and
Cleaning:
- Zimmer cleaned the
vestibule in the auditorium on the 1st
Floor.
- Crews re-cleaned Room
109.
- Zimmer is prepping
Room 815 for cleaning.
- Crews are cleaning the
control booth and the storage room in the
auditorium.
- Painting:
- The contractor
finished painting the handrails in Stairwell
C (Center Corridor).
-
Carpet and Tile Installation:
- RCC patched and
prepped Room 115 for the installation of new
VCT.
- RCC installed VCT in
Room 114, 115, and the vestibule of the
auditorium.
-
RCC prepared Suite 122 for the installation
of carpet and VCT.
- RCC installed VCT and
carpet in the corridor behind the
auditorium.
- Construction Walls:
- The contractor has
painted the door frames and stained the new
doors installed in the construction walls.
- The construction walls
are complete.
- Terrazzo Floors:
- Premier Source Inc.
has ground and polished the terrazzo
flooring in the main corridor on the 8th
Floor.
- They have ground and
polished the terrazzo flooring on the 7th
Floor in the center corridor and in the
corridor along
Tulane Ave.
- The contractor ground
and polished the terrazzo floor in the main
corridor of the 6th Floor and in the
corridor along
Tulane Ave.
-
The contractor finished grinding the
terrazzo in the 5th Floor corridor along
Tulane Ave. and they have begun to polish
the newly ground surface.
-
Crews have started grinding the terrazo in
the center corridor of the 5th Floor.
- Mini Blinds:
- The contractor
finished installing mini-blinds in offices
on the 7th and 8th Floors.
- They have begun the
installation work on the 5th and 6th Floors.
- Misc.
-
Trison finished installing the ceiling tiles
on the patched plaster ceilings of Floors 1
through 4.
-
The contractor finished painting the
installed ceiling tiles on Floors 1
through 8.
-
Trison began patching additional holes in
the plaster ceilings on Floors 1 - 4.
- Hogues & Associates
are installing the new corridor lights in
the center corridors on the 5th and 6th
Floors.
Repair Work at the Dental School:
- Permanent Roof Repairs:
- Needham Roofing has
begun replacing the water damaged roof
material on the Administration
Building.
- Crews tore off and
replaced 52 squares of the base
material.
- Needham Roofing
finished installing the granulated cap sheet
on the roof of the Administration Building and is nearing completion
on the 5th Floor balcony roof.
- The flashing has
been installed on the Administration
Building
roof.
- They pressure
washed the
Clinic Building penthouse
and parapet walls.
- They have begun
pressure washing the parapet walls on
the Administration
Building
roof in preparation for the application
of the waterproof sealant.
Elevator Repairs:
- The upgrade of
Elevator #2 is complete and it has been released for
normal use.
- Schindler started the
upgrade work on Elevator #1.
- They have removed the
cab interior.
Downtown Landscaping Project:
- Crews installed sleeving
under the concrete walkways on the Bolivar St. and Gravier St. sides of the Resource Center in preparation for running
the control wiring for the 2" irrigation main
pipe valve.
- The crews completed the
trenching around the
Resource Center for the 2"
irrigation main and the valve control wires.
- Crews completed the
installation of irrigation valve control wiring
around the Resource Center.
- The crews completed the
installation of the 2" irrigation main pipe and
all seven control valves around the
Resource Center.
- The new 2" irrigation
main was activated.
- Crews completed the
installation of pipe and sprinklers for
Irrigation Station # 4 which serves the grassy
area on the Bolivar St. side of the Resource Center.
- The nozzles have been
installed on these sprinklers.
- They flushed Station # 3
to remove debris from the lines.
- Approximately one half of
Station # 5 which serves the planting beds was
installed.
- The automatic controller
has been installed in the generator room.
- Power was connected to the
Resource Center Building
automatic irrigation controller.
- Crews installed conduit to
run the irrigation valve control wires inside
the building to the controller.
- The irrigation valve
control wires have been run through the conduit
from outside the building to the automatic
controller located inside the generator room.
Parking Lot Improvements:
- Boh Bros installed the new
wheel stops and striped the new parking spaces
in the I-10 Lot #3.
MEB 2nd Floor Lobby Renovation:
- The contractor removed the
ceiling tile from the lobby and former Facility
Services offices.
- They completed the removal
of all the storefronts.
- Zimmer is removing the old
floor tiles.
Resource Center Library Renovations:
- The temporary dust barrier
around the interior stairwell is in place.
- All the walls, flooring,
ceilings and grid, the rest of the storefront
including the automatic doors and the storefront
ceiling braces have been removed from the
elevator lobby.
- In the areas outside of
the elevator lobby, all the walls, lighting,
electrical, and ductwork has been removed.
- The temporary string
lights have been hung.
- The emergency egress
route has been marked on the floor.
- The restroom walls and
ceiling requiring demolition have been
completed.
- The interior construction
walls have been modified to allow public access
to the Library via Elevators #1 & #2, and to
prevent access via Elevator #4.
- This will allow the
demolition of additional walls near the
restroom to proceed.
Elevator Upgrades:
- Elevator #5 in the Allied
Health/Nursing Building has been inspected and
certified for normal use.
- All of the contracted
upgrades for elevators in this building are
complete; however Schindler will be rewiring
Elevators #1 and #3 to be consistent with the
others.
- The rewiring of
Elevator #1 is in progress.
Residence Hall 2nd
Floor Expansion:
- Zimmer continues the
demolition of the old flooring in the middle of
the lobby area.
- The replacement of the air
handling unit serving the 2nd Floor
has begun.
- The demolition of the
wall enclosing the AHU has been completed.
- Demolition of the old
AHU has begun.
MEB 4th Floor - MDL
#5 Renovations:
- The new casework is on
order.
MEB Lecture Rooms A & B
Renovations:
- Trison is completing the
installation of new electrical conduits in
Lecture Room A and continues to work in Lecture
Room B.
- New floor duct will be
installed under the slab for the new A/V wires
at the podium.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|