|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #74
Posted: August 1, 2008
The busy summer construction
schedule continues around campus. The project that is rebuilding the
Cohn Learning Center
on the 6th Floor of the Lions/LSU Clinic
and that raises the critical mechanical, electrical
and plumbing systems to the 2nd floor is
moving forward. The construction of the new exterior
stairwell is well underway. Selected windows have been removed and
temporary construction walls have been built. Many of the new interior walls on the 6th
Floor have been framed and dry walled as the
rough-in electrical work in the walls is being
completed. The installation of the new sprinkler pipe
above the 6th Floor ceiling and the floor
drains, waste pipe and conduit above the 5th
Floor ceiling is progressing. The preparations for elevating the critical
MEP to the 2nd Floor space are proceeding
well.
The two elevators that were taken out of service to
allow the elevator pit to be waterproofed are
expected to be returned to service shortly.
Two new projects are about to
get underway. The first will make major renovations to
research laboratory space located on the 6th
and 8th Floors of the
Dental Clinic Building. This project was in the planning stages prior
to Hurricane Katrina and has been re-started. The second is a project to renovate the two
smaller auditoriums located at the
Dental School. Both projects have the Notices to Proceed
issued with August 4, 2008 effective dates.
There is a flurry of activity
at 1542 Tulane Ave. as the critical
preparations to allow re-occupancy of significant
portions of the building are nearing completion. A great deal of work has been needed to
repair the old fan coil units and prepare them for
normal operation. The painting work around the building is
being concluded. The new lounge areas still require
significant work before they will be completed, but
the installation of new fan coil units and the
related plumbing is progressing. Several other small repair projects have been
completed, while others are in progress.
There are three ongoing
projects in selected areas of the Medical Education
Buildings. The renovations to the 2nd Floor
elevator lobby have progressed and the preparation
of the old concrete sub-floor is the current focus
of the contractor. The demolition within MDL #5 has been
completed, steel supports for the new partitions
have been installed, and the rough-in plumbing for
the medical air, gas, and vacuum has been started. On the 4th Floor, the floor in the
student lounge area has been prepared and new carpet
installed. The fur downs in that area have been framed
up and significant portions of the new ceiling grid
have been installed in the 4th Floor
corridors.
In the Library, the HVAC ducts
have been installed and elevated to the highest
position possible to provide clearance for the
ceiling.
Several of the interior walls have been framed up,
and the LSUHSC Facility Services electricians
continue their work on the electrical rough-in and
network cable is being re-routed. Coring of the slab to provide services to the
Coffee Kiosk has been completed and the fur down
over the Kiosk is being framed.
The perimeter fencing project
for the downtown campus is moving forward. The concrete base for the decorative fencing
has been poured. New conduit and wiring to provide power and
communications with the parking lot access control
devices has been run. The installation of the decorative fencing is
well underway. We have also been receiving and installing
new building trash compactors that replace the old
devices that were damaged by the flood waters.
The duct cleaning work in the
CSRB has been completed and the contractor is
wrapping up their punch list items. The resurfacing of the elevated walkway that
connects the MEB and the Residence Hall continues
and the new overlay material is being applied. The contractor responsible for the expansion
of the Residence Hall lobby area has begun the work
on the exterior of the building. The new air handling unit on the mezzanine
has been installed, the duct work completed and the
mechanical room construction is complete.
The access control devices have
been installed on the new storefront located at the
Derbigny St. entrance to
the Walk to Wellness. Cable is being pulled to connect the access
control devices to the system. The roofing contractor at the
Dental School is completing the
few remaining contract items. Nuclear moisture testing of the new roofs has
been completed and we are awaiting test results. If the testing reveals moisture under the new
roof system, additional roof work will be required.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- The fire-proof sleeve was
installed between the Entergy vault and the
switchgear room for service to new switchgear on
the 2nd Floor.
- The concrete for the
foundation of the new exterior stairwell has
been poured.
- The contractor has begun
removing walls on Floors 2 through 4; preparing
for the installation of steel beams for new
exterior stairwell.
- The installation of
drywall continues on the 6th Floor
and is nearing completion.
- The contractor is piping
in the VAVs on 6th Floor.
- The old storm drain has
been removed from the 6th Floor to
make room for new construction.
- Electricians are
connecting the AHU on the 1st Floor.
- CMU walls are being
installed in the mechanical room located on the Bolivar St. side of the 1st
Floor.
- Sprinkler pipe is being
installed on the 6th Floor.
- Crews are working in the
ceiling of the 5th Floor to install
the floor drains and waste lines for the new 6th
Floor bathrooms on the S. Prieur St. side of the building.
- Electricians are roughing
in electrical service for the new CMU walls on
the 1st Floor.
- They are roughing in the
electrical for the Stryker equipment on 6th
Floor.
- Electricians are
running conduit in the 5th Floor
ceiling for the new Stryker equipment that
will be installed in the new Learning Center.
- Crews are installing
temporary walls on the 5th Floor in
preparation for construction of the new exterior
stairwell.
- Windows have been
removed from the exterior wall on the 2nd,
3rd, and 4th Floors.
- Electricians are running
the wire tray on 1st Floor for the
main wires to the new switchgear on the 2nd
Floor.
- Waterproofing has been
applied to the walls of the elevator pits.
- The contractor is
reconnecting the elevators that have been
out of service to allow for the dry flood
proofing of the elevator pit.
Dental
School
Laboratory Renovations:
- The contract to renovate
laboratories located on the 6th and 8th Floors
of the Clinic Building
has been bid and awarded to Benetech-Franks.
- The Notice To Proceed has
been issued for August 4, 2008.
Dental
School
Auditoriums A & B:
- The contract to renovate
the two smaller auditoriums (A & B) at the Dental School
has been bid and awarded to CS & Associates.
- The pre-construction
meeting has been held.
- The Notice To Proceed has
been issued for August 4, 2008.
Repair Work at
1542 Tulane Ave.:
- Elevator Repairs:
- Stratos Elevator
continues replacing the hoist cables for
Elevator #7
- The repair the work on
Elevator #4 is progressing.
- Ceiling Lights:
- The lighting
contractor completed installing light
fixtures in the center hallways on the 1st
Floor and on Floors 5 through 8.
- Their crew has started
installing light fixtures in the department
head offices on the 6th and 7th
Floors.
- The lighting
contractor is installing exit lights in the
hallways.
- Lounge Areas:
- The mechanical
contractor is installing fan coil units in
the lounges on Floors 5, 6 and 7.
- The mechanical
contractor is installing piping in the new
lounge areas.
- Misc.:
- The general contractor
continued installing suspended ceilings in
several offices, patching and painting
offices and working on punch list items.
- The contractor
completed installing suspended ceilings
in all department head offices on Floors
4 through 8.
- Plumbers are capping
piping and installing segregation/shut off
valves.
- The resurfacing of the
front steps has been completed by the
sandblasting contractor.
- The sprinkler
contractor repaired the dry pipe system on
the 8th Floor and returned it to
service.
- Portable temporary air
conditioning units are being installed in
the rear elevator lobbies.
- Electrical and
mechanical contractors are servicing the
existing fan coil units in offices
throughout the building.
- The contractor removed
the old windows from the front light well in
the old cafeteria and began work to seal up
the opening.
- Crews made repairs to
the sidewalks and cleaned the area around
the rear of building.
- The installation of
the interior signs on Floors 5 through 8 has
been completed.
- LSUHSC Facility
Services personnel continue installing new
fan coil units, removing old FCUs,
installing air conditioning in the rear
lobbies, and installing locksets on the 1st
Floor.
- The new water softener
system has been installed and started up.
Walk To Wellness Storefronts:
- The access control
contractor installed the new access control
equipment on the storefront doors that have been
installed at the Derbigny St. Parking Lot
entrance to the elevated walkway.
- The access control
contractor is pulling wire to the new storefront
doors installed at the Derbigny St.
entrance.
Repair Work at the Dental School:
- Permanent Roof Repairs:
- Infrared Analyzers,
Inc. performed moisture tests on the roof of
the Administration, Clinic, and Power Plant
Buildings.
- The test results
are pending.
- Needham Roofing has
cored the corners of the roofs of the Clinic
and Administration Buildings the holes for the
conduit on the Clinic Building roof.
- The conduit has
been installed and caps applied to seal
the conduit.
-
Needham
repaired and welded the maintenance access
ladder on the Administration Building roof.
- The roofing contractor
is installing additional flashing and
weather-proofing on the parapet walls of the
Clinic Building.
- Crews are repairing
caulk joints and installing weather-sealing
membrane around the perimeter exhaust
stacks.
- The roofing contractor
un-clogged the roof drains.
- The roofing contractor
is caulking windows on the 5th
Floor balcony.
- Elevator #1 in the Clinic Building was carpeted and returned
to service.
- The honing of the terrazzo
floors has been completed on all floors in both
buildings.
- The contractor is
completing the touch-up work.
- The contractor finished
removing the abandoned steam lines from the
Power Plant roof and is installing cover boxes.
Library Commons Project:
- The work on constructing
the bulk head that runs the length of the
Commons area continued.
- LSUHSC Facility Services
electricians continued the electrical rough-in
work.
- The contractor completed
sonar tests to verify the core drill locations.
- The contractor cored the
holes for the plumbing and electrical work to
support the Coffee Kiosk and the Commons area.
- Crews completed installing
sheetrock at the header of the exterior walls
and completed approximately three quarters of
the wall framing.
- The contractor installed
new duct work from the Commons Area to the
existing Library HVAC system and completed
raising the ducts to their maximum heights.
- Auxiliary Enterprises
continues to run network cables to the rear of
the Library from the electrical closet in the
Commons area.
- The portion of the Library
ceiling that was removed for the installation of
duct work has been re-installed.
- The contractor started
framing the fur down ceiling over the Coffee
Kiosk.
MEB 2nd Floor Lobby Renovation:
- The contractor is grinding
the concrete sub-floor to prepare for the
installation of the new flooring.
- The old underlayment
is being removed.
Residence Hall 2nd
Floor Expansion:
- MCC completed the
installation of the ductwork for the AHU on the
mezzanine level.
- The contractor completed
the ductwork insulation for new AHU on the
mezzanine level
- The contractor completed
framing and hung dry wall for the new mechanical
room.
- The drywall has been
floated and painted and the door installed.
- The contractor cut an
opening on the exterior façade of the lobby to
allow for field verification and field
dimensioning related to the installation of the
new steel.
- The contractor removed the
existing exterior metal wall panel to allow for
the tie-in of the steel structure for the roof.
MEB 4th Floor - MDL
#5 Renovations:
- The contractor completed
modifications to the steel support for the new
partition track.
- Plumbing demolition has
been completed in the main room.
- The contractor began
running new plumbing (gas, air, & vacuum) for
the new casework.
- The contractor installed
the steel support in Room 4123A for the
partition storage area.
- The contractor completed
framing the partition for the track.
- The contractor completed
installing gypsum board for sound insulation.
- The crew began installing
the track for the partition wall.
Downtown Perimeter Fence
Project:
- The contractor completed
forming blocks and installing rebar for the
bases of the decorative fencing at Student Lots
#2 and #3.
- New conduit was installed
and electrical lines run to the parking lot gate
controllers for Student Lots #2 and #3.
- The contractor completed
pouring concrete around the perimeter of Student
Lots #2 and #3.
- The new monument fences
are being installed on the Poydras and Perdido
sides of both Student Parking Lots.
Duct Cleaning Project:
- Crews completed cleaning
the ducts on the 1st, 2nd,
3rd and 4th Floors of the
CSRB.
- The work in the CSRB
is substantially complete.
MEB 4th Floor Ceiling
Replacement:
- The contractor completed
framing for the tray ceiling at the student
lounge area on the Roman St. side
of the building.
- The flooring was leveled
in the former locker area and prepared for the
installation of carpeting.
- The crew completed
repairing the concrete sub-floor and installed
the new carpet in the former blue locker area.
- The contractor continues
installing wall angle for the new ceiling grid
in the corridors on the loading dock side of the
building.
Residence Hall Walkway
Resurfacing:
- The contractor filled the
center drains and leveled the area in
preparation to receive the material needed to
slope the surface.
- The contractor has started
applying the overlayment.
Roman St. Garage:
- The contractor is applying
sealant to the newly painted 7th Floor.
- The old groundskeepers’
office on the first floor was demolished.
- The contractor completed
rerouting the new fire alarm wires and removed
the old wires.
Building Trash Compactors: All of the existing building trash compactors
were seriously damaged by the post-Katrina flood
waters.
- New trash compactors were
specified, bid and ordered.
- The old trash compactors
have been removed from behind all the buildings.
- Preparations for the
delivery and installation of the new compactors
are well underway.
- The trash compactor
for the CSRB was delivered and installed.
- The trash compactor
for the Resource Center was delivered
and installed.
- The Sister Stanislaus
Memorial Hall trash compactor was delivered
and installed.
- The trash compactor
for the Lions/LSU Clinic Building was
delivered.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|