From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #79
Posted: October 24, 2008
The contractor and subcontractors
working at 1542 Tulane Ave. are pressing to complete
their projects so that reoccupation of portions of
that building can begin. Developed in coordination
with the Dean of the School of Medicine, the plan
begins by moving individuals into the building
starting on the upper floors and moving down to
lower floors as work is completed on a floor by
floor basis. Floors 5 through 8 will be occupied
first and the initial move is scheduled for the week
of November 17th. Selected spaces on the 1st Floor
will also be put back into use early on. In this
way, we hope to be able to bring faculty and staff
into areas where there is little or no construction
that remains to be completed and the related
disruption will be minimized.
On the 8th Floor, the planned work
is substantially complete and the post-construction
cleaning is underway. New furniture has been placed
in the offices and rooms that will be reoccupied.
The lounge area walls have been dry walled and
painted on the 5th, 6th and 7th Floors and the
ceiling grid has been installed on the 6th and 7th
Floors. The fire alarm components are being roughed
for the lounges on Floors 5 through 7. Furniture has
been installed and arranged in the 7th Floor rooms
and in selected spaces on the 1st Floor.
Post-construction cleaning has begun on the 7th
Floor. The repairs to Elevator #4 are substantially
complete; the elevator has been inspected and a
punch list has been developed.
The contractor continues to make
good progress on the renovations to Dental School
Auditoriums A & B. The new walls in both auditoriums
have been framed up. Conduit and electrical wiring
for the ceiling light fixtures have been run in both
rooms and recessed light fixtures were installed.
The rough in electrical work for the receptacles has
been finished in Auditorium A. Wood supports for the
handrails and baseboards in Auditorium A & B have
been installed and the soffit for the ceiling in
both rooms has been framed.
The project to renovate 6th and 8th
Floor laboratory spaces in the Dental Clinic
Building is moving forward. The domestic water lines
were capped in Rooms 6333 and 6335 and the vacuum
piping for Room 8405 is in place. The mechanical
subcontractor removed waste lines in Rooms 6333 and
6335, and installed a new vent and drain in Room
6333. The new walls in Room 8405 were framed and the
mechanical contractor finished the de-ionized water
piping installation and pressure testing for the 6th
and 8th Floor labs. The horizontal gas and vacuum
piping inside the interior walls of the tissue
culture room in Room 8405J have been installed and
the drain line for the fume hood in Room 6335 is in
place. The general contractor removed the door and
frame at the south entrance of Room 8405 and they
framed the exterior wall for Room 8405K and the
south entrance of Room 8405.
In the Resource Center Library, the
project to create the new Commons area continues.
The sprinkler contractor removed existing sprinkler
piping that conflicted with the new ceiling layout
and new sprinkler piping and sprinklers have been
installed above the coffee kiosk, near the entrance
and in the Commons area. Duct work that was
interfering with the new ceiling has been relocated
and new duct work was installed in the multimedia
room, near the center stairwell and near the Library
entrance. Additional sheet rock has been installed
in the same areas.
The effort to make the permanent
repairs and complete the hazard mitigation work at
the Lions/LSU Clinic Building continues. The iron
contractor has the steel frame for the exterior
stairwell fully erected and welded. The stairs and
handrails for all floors have been installed and
welded. The steel roof panel is in place and
attached. The new casework and countertops for the
7th Floor lab have been installed. The mechanical
subcontractor piped in water, waste, air, and vacuum
lines for the new fume hood on the 7th Floor. The
duct work for the hood has been connected and valves
installed. A significant amount of effort is being
expended on the HVAC, the plumbing, and the
electrical systems on the 1st, 2nd, 6th, and 7th
Floors.
The renovations to
Multi-Disciplinary Lab #5 are nearing completion.
The majority of the network cabling has been
finished and tested. Several of the large LCD
monitors have been installed. The panels and
countertops for the middle island in all 4 quadrants
of the lab have been installed. The four pedestal
frames have been installed in the center of the lab
and the countertops for the pedestals are in place.
Electrical receptacles have been mounted and wired
in the pedestal frames. The MEB 4th Floor ceiling
replacement is substantially complete. The fire
alarm caps and the four large supply air ducts have
been installed. The tray ceilings located in the two
student study areas have been painted.
Some additional work needed to
complete the MEB 2nd Floor lobby renovations has
been identified. The concrete ceiling that is to be
painted was rougher in many areas that was
anticipated, so the pans of all the ceiling sections
are being skim coated to provide a smooth surface to
which paint can be applied. While that work is in
progress, the new glass store fronts have been
delivered to the site and the wood blocking that is
necessary for installation of the store fronts is
being installed. The old HVAC duct work has been
removed. Supports for the new ceilings have been
installed and the installation of ceiling grid has
started on the Roman St. side of the lobby.
Over at the Residence Hall, the
contractor built the concrete forms and poured the
concrete for the curbs that will support the new
glass store fronts at the Bolivar St. entrance and
the Roman St. side of the lobby. The flooring
contractor placed a coat of concrete primer on the
floor between Tower A and Tower B and poured a final
layer of self-leveling concrete over the entire
area. Multiple rows of new porcelain tiles have been
laid across the floor between the towers and the
tile joints have been grouted.
The upgrade to the audio/visual
equipment in Auditorium A in the Medical Education
Building is substantially complete and is being
used. As minor issues arise in the use of the new
state of the art systems, Computer Services is
addressing them. The update effort in Auditorium B
is expected to be finished in December. The A/V
upgrades in Auditorium B will be exactly the same as
those in Auditorium B.
Here are highlights of work that has
been accomplished during the past two weeks.
NOTICE: On Monday, October 27th,
Schindler Elevator will begin the upgrade process of
the final elevator in the Medical Education
Building; Elevator #8, commonly referred to as the
Animal Care Elevator. Elevator #8 has two doors; a
front and rear door and opens directly onto the
loading dock. We expect this elevator to be out of
service for 12 weeks.
Repair Work at 1542 Tulane Ave.:
- Lighting:
- The electrical contractor installed new
light fixtures in Conference Room 728.
- The electrical contractor installed new
light fixtures in Conference Room 756.
- The electrical contractor installed new
light fixtures in Conference Room 524.
- The electrical contractor continues
installing new light fixtures in conference
rooms on the 6th Floor.
- Lounge Areas:
- Crews taped and floated the sheetrock
wall in the lounge on the 5th Floor.
- The contractor sanded the lounge walls
in preparation for primer and paint.
- The general contractor completed
painting lounge walls on the 5th, 6th and
7th Floors.
- The fire alarm contractor continued
roughing in strobes and speakers in the
lounges on the 5th, 6th and 7th Floors.
- The contractor installed suspended
ceiling grid in the lounges on the 6th and
7th Floors and started installation of
ceiling grid in the lounges on the 4th and
5th Floors.
- Furniture:
- The furniture vendor finished the
installation and arrangement of furniture in
offices on the 7th Floor.
- The furniture vendor completed the
furniture placement on the 1st Floor.
- Crews moved furniture assigned to the
4th Floor from the staging areas in the
parking garage to the 4th Floor annex.
- The furniture vendor continues arranging
new furniture in offices on the 5th Floor.
- Elevator Repairs:
- The elevator contractor is making final
preparations for the formal inspection of
Elevator #4.
- Elevator #4 (freight elevator) was
inspected and a punch list generated.
- Cleaning:
- The construction cleaning contractor has
been completing the final (post
construction) cleaning on the 8th Floor.
- They shampooed the 8th Floor office
carpets.
- Crews returned to cleaned areas that
failed inspection on the 8th Floor.
- They continued cleaning on the 7th Floor
and began cleaning on the 6th Floor.
- The construction cleaning contractor
shampooed the 7th Floor office carpets.
- Misc.:
- The general contractor continues
repairing the ceiling grid in the front
hallway on the 5th and 6th Floors.
- A cool room on the 5th Floor has been
demolished.
- LSUHSC Facility Services repaired locks
on the exterior loading dock doors.
- LSUHSC Facility Services personnel are
installing new paper towel and soap
dispensers in restrooms on all floors.
Dental School Auditoriums A & B:
- The general contractor framed up walls in
Auditoriums A and B.
- The electrical subcontractor installed
junction boxes and to mount hardware for the
ceiling light fixtures in Auditorium A.
- The insulation subcontractor is labeling the
HVAC piping.
- The electrical contractor installed recessed
light fixtures in Auditoriums A and B.
- The contractor completed sheetrock work in
both auditoriums.
- The general contractor installed wood
supports for the handrails and baseboards in
Auditorium A & B and framed the soffit for the
ceiling in Auditorium A & B.
- The electrical subcontractor installed
wiring and conduit for the power receptacles in
Auditorium A.
- The electrical contractor installed wiring
and conduit for the sconces and receptacles in
Auditorium B.
- The general contractor installed wood
supports for the baseboards in Auditorium A
along the east wall.
- The contractor installed metal framing for
the soffit and ceiling in Auditorium B.
Dental School 6th and 8th
Floor Laboratory Renovations:
- The domestic water lines were capped in
Rooms 6333 and 6335.
- The mechanical contractor installed vacuum
piping for Room 8405.
- The general contractor removed thimbles from
the demolished lab casework in Room 8405.
- The mechanical subcontractor removed waste
lines in Rooms 6333 and 6335, and installed a
new vent and drain in Room 6333.
- They framed up the new walls in Room 8405.
- The mechanical contractor finished the
de-ionized water piping installation and
pressure testing for the 6th and 8th Floor labs.
- The mechanical contractor installed
horizontal gas and vacuum piping inside the
interior walls of the tissue culture room in
Room 8405J.
- They installed the drain line for the fume
hood in Room 6335.
- The general contractor removed the door and
frame at the south entrance of Room 8405.
- They framed the exterior wall for Room 8405K
and the south entrance of Room 8405.
Dental School Permanent Roof
Replacement:
- The contractor finished installing cap
sheets over roofing sheets marred by foot
traffic.
- The contractor installed the final sheet
metal vent caps on the Administration Building
roof and finished installing roofing cap sheets
over the marred roof sheets.
- The contractor removed the dumpster and
excess materials from the job site.
- The project is complete, pending the final
inspection(s).
Library Commons Project:
- The sprinkler contractor removed existing
sprinkler piping that conflicted with the new
ceiling layout.
- The contractor painted the concrete ceiling
of the Library.
- The contractor continues to sheetrock in the
elevator lobby and the cafe area.
- The contractor installed sheetrock in
areas near the Library entrance and in the
back area of the cafe.
- The contractor installed sheetrock
around the stairs.
- LSUHSC electricians ran feeds to the new
electrical panel.
- The mechanical contractor relocated ductwork
that conflicted with the ceiling.
- The contractor installed sprinkler piping
above the coffee kiosk.
- The contractor installed fire sprinklers
near the Library entrance.
- The contractor installed fire sprinklers in
the hall of the Commons.
- The contractor removed all of the existing
fire sprinkler piping and installed fire
sprinklers in the café area.
- Ductwork has been installed in the
multimedia room.
- The contractor installed ductwork near the
center stairwell.
- The contractor installed ductwork near the
Library entrance.
Lions/LSU Clinic Permanent Repairs
and Mitigation:
- The mechanical subcontractor insulated
supply duct on the 6th Floor Gravier St. side of
the building.
- Crews are installing branch lines to the
VAV boxes on the Gravier St./S. Prieur St.
side of the 6th Floor.
- A VAV that was in way of duct on the 6th
Floor was raised.
- They re-piped the raised VAV.
- ID tagged the domestic hot and cold
water lines and the heating hot water lines
on the 6th and 7th Floors.
- Crews continue installed piping outside
of the elevator lobby to connect to the sump
pump that will be installed in the pit of
Elevator 1 and 4 and in the pit for the
freight elevator on the 1st Floor.
- Support carriers for the water closets
and urinals in the S. Prieur St. side
bathroom on the 1st Floor were installed.
- Supply duct has been run in the
mechanical room on the Bolivar St. side of
the 1st Floor.
- They moved a vent line in the bathroom
on the 6th Floor that conflicted with a
duct.
- The subcontractor trimmed out cabinets
and a fume hood on the 7th Floor and welded
the exhaust for the fume hood.
- The mechanical subcontractor piped in
water, waste, air, and vacuum lines for the
new fume hood on the 7th Floor.
- They installed valves for the fume hood
on the 7th Floor and installed the duct for
the fume hood on the 7th Floor.
- They moved a gas line that was in way of
a new fume hood on the 7th Floor.
- Water closet and urinal carriers were
installed in the S. Prieur St. side bathroom
on the 1st Floor.
- The mechanical subcontractor tested the
heating hot water line on the 6th Floor.
- They roughed in the waste and vent lines
for the urinals and the toilets in the
bathroom on the 1st Floor.
- The mechanical subcontractor installed
sinks and faucets in the 7th Floor lab.
- They insulated the heating hot water
lines going to the VAV on the 6th Floor.
- The mechanical subcontractor installed
three sinks and faucets in the 7th Floor
lab.
- The electrical subcontractor installed new
conduit for the new breaker box on the 2nd Floor
in the electrical room located on the S. Prieur
St side of the building.
- Conduit was run to the new panel in the
1st Floor electrical room.
- They wired the sump pump for Elevators 2
and 3 on the 1st Floor.
- The electrical subcontractor installed
lights and receptacles in the pit for
Elevators 2 and 3 on the 1st Floor.
- The electrical subcontractor moved the
transformer on the S. Prieur St. side of the
2nd Floor.
- They powered the medical gas alarms in
the simulation rooms on the 6th Floor.
- The electrical subcontractor trimmed out
the electrical devices on the 7th Floor.
- They ran electrical feeders to provide
power to the rollup door on the 6th Floor.
- The electrical subcontractor installed
lights on the 6th Floor on the CSRB side of
the building.
- They ran wire for the new lights in the
elevator lobby on the 6th Floor.
- The iron subcontractor welded the exterior
stairwell frame on the 3rd, 4th, 5th and 6th
Floors.
- They welded the saddles on the 2nd, 3rd,
4th, 5th, and 6th Floors.
- The iron subcontractor welded the
landings on the 3rd and 4th Floors.
- They installed the deck and stair
closures on the 4th through the 6th Floors.
- The iron subcontractor welded the frame
for the stairwell roof and the joints where
each stair level meets.
- The roof decking was welded in place.
- The sprinkler subcontractor is installing
sprinkler heads on the 6th Floor.
- The fire sprinkler subcontractor
installed fire sprinklers on the 6th Floor
Gravier St./S. Prieur St. side of the
building.
- They relocated sprinkler heads on the
1st Floor on the S. Prieur St. side.
- The casework subcontractor installed new
laboratory casework on the 7th Floor.
- The casework subcontractor installed
countertops on laboratory casework in the
7th Floor lab.
- The contractor is sealing wall penetrations
throughout the 6th Floor.
- Crews continue installing door frames
throughout the 6th Floor.
- They formed up the slab on the 1st Floor
by the bathrooms on the Bolivar St. side.
- The new housekeeping pads were framed up
in the 2nd Floor mechanical room for the
medical air and gas equipment.
- They poured the concrete for the
housekeeping pads for the medical air and
vacuum equipment on the 2nd Floor.
- CMU walls have been installed on the S.
Prieur St. side of the 1st Floor.
- They re-waterproofed the elevator pit on
the 1st Floor.
- They installed projector screens on the
CSRB side of the 6th Floor.
- The walls of the Womens bathroom on the
Bolivar St. side of the 6th Floor were
insulated.
- They installed sheetrock in the Bolivar
St. side bathroom on the 6th Floor.
- Rails for the removable wall panels on
the 6th Floor were installed.
- The sheetrock ceiling on the 1st Floor
across from the security desk was removed to
allow for the installation of the new door.
- They installed fur downs on the 6th
Floor on the S. Prieur side.
- The fur downs on the 6th Floor CSRB side
were taped and floated.
- A crew began cleaning the granite on the
outside of the building on the Bolivar St.
side of the 1st Floor.
MEB 4th Floor - MDL #5
Renovations:
- The network wiring contractor tested the new
data cables and connections.
- The audio/visual subcontractor installed
four 65" LCD monitors in MDL 5.
- The casework contractor installed panels and
countertops for the middle island in all 4
quadrants of the lab.
- The contractor removed pipe thimbles from
floor.
- The contractor installed cove base wrapping
the new casework.
- The contractor adjusted light fixtures,
sprinkler caps, and patched the flooring.
- The contractor replaced the four center
pedestal frames in the main MDL room.
- The contractor installed coax cables and the
control boxes for the 65" and 42" LCD monitors.
- The audio/visual subcontractor installed
three of the four 42" LCD monitors in the center
of the MDL.
- The contractor installed countertops for the
pedestal frames in the MDL lab.
- The contractor installed electrical
receptacles for the pedestal frames in the MDL
room.
MEB 2nd Floor Lobby Renovation:
- The contractor delivered the frames for the
glass storefronts and the store doors.
- They installed wood blocking for the
installation of the frames for the storefront
glass and doors.
- The contractor installed ceiling supports
for the drop ceiling on the Bolivar St. side and
started installing new ceiling grid outside Room
2104.
- The contractor installed ceiling grid on the
Roman St. side of the lobby.
- The mechanical subcontractor removed the
existing supply and return air ductwork.
- The contractor is skim coating the pans of
the honeycomb ceiling to create a smooth finish
once it is painted.
MEB 4th Floor Ceiling Replacement:
- The contractor installed the fire sprinklers
caps.
- The contractor installed four large return
air grilles.
- The contractor painted the tray ceiling in
the student study area on the S. Roman St. side
of the building.
- The contractor painted the tray ceiling on
the Bolivar St side of the building.
Residence Hall 2nd Floor
Expansion:
- The contractor built the concrete forms for
the storefront curbs at the Bolivar St. entrance
and the Roman St. side of the Residence Hall.
- The contractor poured concrete for the new
storefront curbs.
- The flooring contractor placed a coat of
concrete primer on the floor between Tower A and
Tower B.
- The contractor removed sprinkler piping from
the new mailbox location.
- The contractor placed three eighths of an
inch of self-leveling concrete from Tower A to
Tower B on the 2nd Floor of Residence Hall.
- The flooring contractor installed fourteen
rows of porcelain tiles between Towers A and B.
- The contractor grouted the new tiles that
have been laid between the A and B Towers.
Downtown Landscaping Project:
- Facility Services continued grading the
landscape and setting planter bed edging in
front of 1542 Tulane Avenue.
Residence Hall Walkway Resurfacing:
- The contractor placed three more sections of
the stamped concrete surface.
Trash Compactors:
- All of the new trash compactors around
campus have been tested and are ready for normal
use.
- The new trash compactors installed around
campus were put into operation.
- The trash compactor vendor hauled away the
old trash compactors and components.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|