From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #81
Posted: November 21, 2008
Another major milestone will be
achieved with first in a sequence of the planned
moves back into the upper floors (7th and 8th) of
the Clinical Education Building are scheduled to
begin next week. The preparations for re-occupying the
building are continuing. New light fixtures for the entry way, in
conference rooms and hallways, and in the parking
lot have been installed. The work in the lounge areas continues;
cabinets have been installed in the 7th Floor lounge
and A/C duct work is in place in the lower floor
lounge areas.
The final cleaning has been finished on the 1st
Floor and on Floors 5 through 8. Restrooms are being cleaned throughout the
building. The new data network cabling has been
completed on Floors 7 and 8, and it is well underway
on the 6th Floor. These are additional network drops being
added to the enhanced network infrastructure
installed prior to the storm. An additional project to enhance wireless
connectivity in selected areas of the building will
begin shortly. The landscaping and irrigation system work
has been completed in the front of the building.
Additional concrete has been
poured as part of the renovations to the Dental
School Auditoriums A and B. The riser seat flooring in Auditorium B has
been poured and the forms have been removed. The entry way stairs into Auditorium A have
also been poured. Electrical work continues in both spaces, and
connections are being made to the newly installed
air handling units. The conduit for the enhanced audio/visual
equipment is being run.
The work on the construction of
the Commons area in the Resource Center Library is
moving ahead. Sprinkler pipes have been run to the
mechanical room. Additional HVAC duct work was installed along
the windows. All but one of the new thermostats have been
installed. The new ceiling grid is in place in several
areas; the study area, the small and large
multimedia rooms, and the café. Wall tiles have been applied to the frieze
wall.
We reached an important
milestone in the project to complete permanent
repairs and hazard mitigation at the LSU/Lions
Clinic Building. We have been granted beneficial occupancy of
the lab space that has been relocated to the 7th
Floor.
While some minor punch list items remain to be
finished we will be able to move into and use this
space in the near future.
The new switch gear has been
moved into place on the 2nd Floor of Lions. Thirty-two electrical feeders and the cable
trays that support them above the 1st Floor ceiling
have been run in preparation for connecting to the
new switch gear. The 2nd Floor location will insure that it
will not be damaged by a future flood event. Lines were also run to the medical air and
vacuum in the 2nd Floor mechanical room. The sprinkler sub also ran lines to the new
fire pump located on the 2nd Floor. The insulating crews have been working around
the building insulating the new duct work, the pipes
for domestic hot and cold water, and the chilled and
heating hot water pipes. The steel workers continue to complete the
many welds on the exterior stairwell tower. They also mounted the supports for the
surgical booms in the 6th Floor simulation rooms.
The contractor working at the
Residence Hall is preparing for the removal of the
existing curtain wall. They framed up and sheathed a temporary wall
that will remain in place until the old wall has
been removed and the new curtain wall installed. Some of the existing exterior light fixtures
have been removed and additional steel clips
installed on the expansion portion of the roof. The new mailboxes have also been installed.
The renovations to
Multidisciplinary Lab have been completed and the
lab will be put back into service next week. A similar project to renovated MDL #6 will
begin immediately. The planned renovations will follow the model
set in MDL #5 and include state of the art
audio/visual, all new case work and countertops, new
ceilings and floors, etc.
A new project is underway to
renovate the MEB 6109 & 6148 lab. Included in the scope of work are new
ceilings, flooring, and lab countertops. The old ceiling, ceiling grid, light fixtures
and HVAC grills have been removed. The old counter tops have also been
demolished. New ceiling grid has been installed and the
light fixtures relocated. Ceiling tiles are being installed. The new countertops are already in place
along with new shelving support panels and shelf
brackets.
New HVAC supply duct has been
installed in the 2nd Floor lobby of the
Medical Education
Building
to serve the restrooms and the newly configured
lobby spaces. A new fire sprinkler valve was installed on
the east side of the lobby. Sheet rock
was hung on the interior walls by Medical Center
Stores.
The walls near the storage areas and restrooms on
the north side of the lobby and the southeast
stairwell were taped and floated.
Here are highlights of work
that has been accomplished during the past two
weeks.
Repair Work at
1542 Tulane Ave.:
- Lighting:
- The electrical contractor
installed new light fixtures on the front
porch and continued installing light
fixtures in conference rooms on the 2nd and
3rd Floors.
- The contractor completed
installing dimmer switches for the light
fixtures in the 5th, 6th and 7th Floor
conference rooms.
- New light fixtures have
been installed in the parking garage.
-
New light fixtures have been installed in
the front hallway on the 6th and 7th Floors.
- Preparations are underway
for the installation of new light fixtures
in the 1st floor lobby.
- Lounge Areas:
- The mechanical contractor
continued installing and insulating air
conditioning ducting in the lounges on the
3rd, 4th, and 5th Floors.
- The furniture vendor is
installing cabinets in the lounge on the 7th
Floor.
- Furniture:
- Crews set up the furniture
and furnishings in Conference Rooms 728 and
756.
- Cleaning:
-
All offices on Floors 1, 5, 6, 7 and 8 are
complete.
- Crews continued cleaning
offices on the 5th Floor.
-
They have started cleaning restrooms on all
floors.
- Cleaning of the stairwells
has begun.
- Misc.:
-
The new FedEx box was relocated to the
vending machine alcove on the rear hallway
of the 1st Floor.
-
The network wiring contractor ran new data
wire in the 7th and 8th
Floor offices.
-
They continue running new wire on the
6th Floor
-
The ceiling grid in the vending machine
alcove on the 1st Floor was painted.
- The ceiling support bases
for the new light fixtures in the 1st Floor
lobby were painted.
-
The window glass contractor replaced broken
windows on the 1st and 2nd Floor, in the 7th
Floor lounge, and in various offices on
Floors 3 and 4.
- The elevator contractor
removed the protective film on Elevator 7
and the plywood sheathing in Elevators 3 and
8.
Dental
School
Auditoriums A & B:
- Auditorium A.
- The concrete for the entry
stairs was poured and the forms were
removed.
-
The contractor floated the sheetrock walls
and installed sheetrock for the ceiling
trough along the south wall.
- They sanded the walls in
Auditorium A.
-
The electrical contractor installed junction
boxes for the sconces on the west wall in
the Auditorium.
-
The electrical contractor connected
additional wiring for the lighting switch
legs.
- Auditorium B.
-
The general contractor installed the support
legs and the first tier of wood forming for
the riser seating.
-
Crews installed foam supports and anchors
for the riser seating.
- The concrete for the riser
seating was poured and the concrete forms
were removed.
- The contractor installed
additional sheetrock in the ceiling troughs
in Auditorium B.
- The electrical contractor
installed wiring for the down lights.
-
Electricians installed the remaining power
and data stub-ups for the riser seating.
-
Crews installed wiring for the step lighting
in Auditorium B.
-
The mechanical contractor assembled the AHUs,
and set them on equipment pads.
- The mechanical contractor
installed chilled water pipes to one of two
AHUs.
- The electrical contractor
started running conduit from the electrical room
to the AV room.
Dental
School
6th and 8th Floor Lab
Renovations:
- The contractor caulked
joints for all the exterior masonry walls in Suite 8405.
-
Crews removed wood blocking from the north and
east exterior walls in Room 8405.
- The general contractor
framed the main doorway and exterior windows for Suite 8405.
Library Commons Project:
- The contractor installed
wall tiles on the frieze wall, sprinkler pipes
in the mechanical room, and ceiling grid in the
study area.
- They installed the ceiling
grid in the café area.
-
Ceiling grid has been installed in both the
large and small multimedia rooms.
-
LSUHSC electricians installed light fixture
supports in the large multi media room.
-
The mechanical contractor installed hard duct
for the window ceiling grid.
-
The mechanical contractor installed branch
ductwork preparing for diffuser installation in
the ceiling grid near the windows.
- Siemens installed all but
one of the new thermostats.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- LSUHSC has been granted
beneficial occupancy of the laboratory that was
relocated from the 6th Floor to make room for
the
Cohn Learning
Center. This means that lab operations can be
moved into the space and research activities
soon can begin.
- The mechanical
subcontractor installed eyewash and emergency
shower signage on the 7th Floor.
- The subcontractor
insulated supply ductwork on the 6th Floor
in the center of the floor, outside of the
simulation rooms.
- They insulated supply air
ductwork on the northeast side of the 6th
Floor.
- Crews insulated domestic
water lines on the east side of the 1st
Floor.
-
A crew insulated chill and heating hot water
lines on the east side of the 1st Floor.
- They installed piping for
the drinking fountain on the west side of
the 1st Floor.
- Chilled water lines were
installed on the west side of the 1st Floor.
-
A crew excavated the existing storm drain
along Gravier Street.
-
The subcontractor installed the pipes for
the storm drain on the street and backfilled
the excavated area.
-
Ductwork from the VAVs to the new supply
ducts on the west side of the 6th Floor was
installed.
- The temporary air intake
line to the medical air equipment on the
south side of the 1st Floor was installed.
- A crew installed control
valves on the west side of the 6th Floor.
- VAV controls for the 6th
Floor simulation rooms were wired.
-
The HVAC system on the 7th Floor was
balanced.
-
They demolished the existing medical gas
pipe on the east side of the 2nd Floor.
-
Pipe was installed for the new medical air
and vacuum on the 2nd Floor.
-
The domestic cold water valve for the 6th
Floor simulation room was relocated.
- The exhaust lines for the
med gas bottle room on the 6th Floor were
installed.
- They finished tying in the
supply and outside air duct on the west side
of the 1st Floor.
- The electrical
subcontractor finished installing the electrical
receptacles for the lab on the 7th Floor.
-
They terminated station cables into the
patch panels on the 7th Floor network
closet.
- The transformer on the 2nd
Floor was moved.
-
The contractor installed all 32 new
switchgear feeders.
-
They installed the cable tray feeders on the
south side of the 1st Floor.
- They ran the feeders into
the new switchgear on the 2nd Floor.
- Crews lifted the new
switchgear into the electrical room on the
2nd Floor.
-
The electrical subcontractor installed
wiring for the lecture room projectors and
projector screens on the north side of the
6th Floor.
- They installed wire for
the fire alarm devices on the south side of
the 6th Floor.
- The iron/steel
subcontractor welded clips on the 2nd Floor and
the roof of the stair tower.
-
The steel subcontractor anchored surgical
booms supports in the 6th Floor simulation
room near the northeast corner.
-
The contractor welded the granite support
corners on the outside stairwell.
-
The iron subcontractor welded the granite
curtain wall brackets on the northwest side
of the 1st Floor.
- The sprinkler subcontractor
moved sprinkler heads on the northwest side of
the 6th Floor.
- They installed fire pump
valves on the 2nd Floor.
- The sprinkler
subcontractor installed piping near the new
fire pump on the south side of the 2nd
Floor.
- The contractor installed
sheetrock on the bulkhead on the northeast side
of the 6th Floor.
- A crew installed studs on
the 2nd Floor between the electrical and
telephone room.
- Crews plastered the CMU
walls on the east and south sides of the 1st
Floor.
-
Crews installed additional door frames on
the northeast side of the 1st Floor.
-
They plastered under the window frames on
the north side of the 1st Floor.
- The contractor installed
restroom wall tiles on the 6th Floor and
primed the locations of the marker boards on
the south side of the 6th Floor.
-
A crew sheet rocked the areas for the
recessed television monitors on the north
side of the 6th Floor.
- A crew installed door
frames and glass on the north side of the
6th Floor.
- Sheetrock is being hung in
the freight elevator vestibule on the 6th
Floor.
- The glass subcontractor
installed the interior framing for the windows
on the north, west and south sides of the 1st
Floor.
-
The glass subcontractor caulked the exterior
window frames on the south side of the 1st
Floor.
-
They installed the interior window trim on
the 1st Floor at the entrance and on the
south side of the building.
MEB 2nd Floor Lobby Renovation:
- The mechanical contractor
installed supply ductwork for the restrooms and
lobby space.
- The contractor leveled the
window framing near Medical Center Stores.
-
A new fire sprinkler valve was installed on the
east side of the lobby.
- The contractor finished
hanging sheetrock on the interior walls by
Medical Center Stores.
- The sheetrock on the north
walls by the storage areas, the restrooms, and
the southeast stairwell was taped and floated.
Residence Hall 2nd Floor
Expansion:
- The contractor installed
the new mailboxes.
-
More steel clips were installed on top of the
new expansion roof and on the steel tube truss.
-
A temporary curtain wall was framed and
sheathed.
-
This wall will remain in place while the old
curtain wall is removed and the new curtain
wall is installed.
-
The contractor removed existing 2x4 light
fixtures and wall mount light fixtures on the
mezzanine level between the A & B towers.
- They removed existing 2x4
wall-mount light fixtures at the corner of
Perdido and S. Roman.
MEB 6109 & 6148 Lab
Renovations: This is a new project that will renovate a
research lab at the MEB. Included in the scope of work are new
ceilings, flooring, and lab countertops.
- The contractor removed
ceiling grids, ceiling tiles, and HVAC grills.
-
The contractor installed new ceiling tiles and
relocated existing light fixtures.
- The contractor removed
existing counter tops in both rooms and
installed the remaining ceiling tiles, light
fixtures and diffusers.
-
The contractor installed new epoxy countertops,
shelving support panels, and shelve brackets in
both rooms.
Downtown Landscaping Project:
-
LSUHSC Facility Services completed planting
shrubs and flowers in front of 1542 Tulane Ave.
-
Crews installed sod in
front of 1542 Tulane Ave.
- Facility Services tested
the sprinkler operation for the landscaping and
completed making the wiring connections for the
bollard lights in front of the building.
Downtown Campus Fence Project:
- The contractor installed
fence and gate on the 6th Floor of the parking
garage.
-
They installed vinyl chain link fence on the
Gravier St. side of
Stanislaus Hall.
Elevator Upgrades:
- The contractor installed new carpet for Elevator 3 & 4 in the
Resource Center.
MEB 4th Floor - MDL
#5 Renovations:
- LSUHSC Facility Services
mopped and waxed the new tile floors in MDL 5.
- All work has been completed
and the lab will be returned to service next
week.
MEB 4th Floor Ceiling Replacement:
-
The contractor installed the cove lights for the
blue sky ceilings.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|