From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #83
Posted: December 19, 2008
In spite of the fast approaching
holidays, the last two weeks have been very
productive. Four more clinical departments were
moved into the Clinical Education Building;
Dermatology, Anesthesiology, Urology, and OB/GYN.
The majority of the work that remained to be
completed on the 5th Floor has been addressed and
only minor issues remain. As a result, the focus of
the ongoing work in the building is shifting to the
lower floors.
The renovations to the Dental School
auditoriums have progressed nicely. The door frames
for the entrance doors have been installed and
insulated. The dry wall in both rooms has been
primed. The ceiling grid and the HVAC diffusers have
been installed in Auditorium B. Work continued in
the mechanical and electrical rooms. Conduit, wiring
and electrical fixtures have been installed, and
chilled water lines insulated. The new audio/visual
equipment room has been framed up, the A/C unit has
been set in place, and the necessary piping has been
run.
The contractor responsible for the
6th and 8th Floor lab renovations in the Dental
Clinic Building has completed significant portions
of the wall construction. The exposed exterior walls
were waterproofed and insulated. Interior and
exterior walls have been framed up and insulated.
They have started to hang the new dry wall. The
terrazzo floors have been honed and polished in some
of the rooms.
Floor and perimeter tiles have been
laid and grouted in the elevator lobby of the
Resource Center Library as part of the Commons
project. The contractor began and made significant
progress in the installation of the coffee kiosk.
The have also begun installing the supports for the
custom wood covers that will surround the concrete
columns in the Commons area. The frieze that had
been removed from 1542 Tulane Ave. and restored has
been mounted on the frieze wall. Door frames for the
restrooms have been installed and the ceiling grid
was hung in the women's restroom. Power has been
connected to the air handling unit and the fire
alarm subcontractor has begun working. The old fire
alarm devices have been removed and they are
roughing in for the new devices.
A great deal of progress has been
made by the electrical subcontractor working at the
Lions/LSU Clinic Building as they move the building
electrical service from the old switch gear to the
new gear located on the 2nd Floor. They have pulled
feeders, installed and connected new electrical
panels, connected critical building components to
the panels, etc. The mechanical sub has been working
in the old laboratory area on the 6th Floor;
installing new VAVs and connecting them, and
installing new supply air duct in that space. They
have also installed plumbing fixtures and water
fountains on both the 6th Floor. They continue to
remove old storm drains from above the 6th Floor
ceiling as necessary and they have installed new
storm drain lines in the stairwell. They also
installed piping that will connect to the sump pumps
to be located in the elevator pit that serves
Elevators 1 and 4.
The general contractor working at
the Lions/LSU Clinic Building has been completed a
significant amount of work on the interior walls. As
the electrical and mechanical work behind the walls
is completed they are able to begin the finish work.
They are installing, floating, priming and painting
drywall in a number of locations. Wall tile is being
installed on the 1st Floor. They have also laid
floor tile in restrooms on both the 1st and 6th
Floors. Plaster is also being applied where
appropriate. Crews continue to install doors and
ceiling grid on the 6th Floor, and the concrete wall
for the elevator pit has been poured.
Work in the Medical Education
Building, MDL #6 continues. New drain lines are
being installed in the ceiling of the 3rd Floor that
will serve the lab in its new configuration. New
studs and dry wall have been installed above the
movable partitions to assist with sound attenuation.
Old floor tiles were removed from Room 4117A. Two
floors down in the MEB 2nd Floor lobby, the fire
sprinkler subcontractor has been fully engaged in
running new sprinkler lines in the ceiling. Finally,
a new project to make major renovations to
Pharmacology lab spaces on the 5th Floor has gotten
underway. Following the pre-construction meeting
held by the Office of Facility Planning and Control,
the demolition phase began. The old lab furniture
has been removed. The ceilings in the lab and
administrative spaces have been demolished and
interior walls in several rooms are being torn down.
The project to expand the lobby of
the Residence Hall has continued at a steady pace.
Preparations for the installation of the new
exterior glass continue as new vertical and
horizontal mullions have been installed in front of
the temporary wall. Rubber glazing material has also
been installed in the new store front. Roof
insulation and roof membrane was installed in the
roof expansion area. Inside, the mail boxes were
removed so that the brick pavers in the mail box
room could be removed. Nailers for the roof flashing
were installed.
Here are highlights of work that has
been accomplished during the past two weeks.
Repair Work at 1542 Tulane Ave.:
- The initial re-occupation of the building
continues.
- The moving contractor delivered
furniture and contents for the Dermatology
and Anesthesiology departments to their
offices on the 6th Floor.
- Four truckloads of material for OB-GYN
and Urology were delivered to offices on the
5th Floor.
- Furniture:
- The furniture vendor set up new
furniture in Conference Room 544 and in the
5th Floor lounge.
- The painting contractor completed painting
the front stairwell on the Claiborne Avenue end
of the front hallway.
- They completed painting Conference Room
637.
- They completed painting the Shipping and
Receiving area.
- They completed painting the freight
elevator lobby.
- The painting contractor completed work
in the rear stairwell.
- Misc.:
- The terrazzo contractor completed cove
base repairs in the front hallways on the
4th through the 7th Floors.
- The general contractor installed ceiling
tiles in the front hallway on the 5th Floor.
- The general contractor completed
painting in Room 545 and installed switch
and outlet plates.
- The general contractor completed ceiling
tile work and carpet work in Rooms 544 and
547.
- The general contractor completed
installing carpet in Room 545.
- The general contractor continues to
install ceiling tiles and grid in the 4th
Floor lounge, hallways, and offices.
- Crews began scraping and patching the
walls in the auditorium.
- Facility Services installed four new
flood lights in the rear of the building.
- Facility Services power washed the
Lakeside Lot.
Dental School Auditoriums A & B:
- Auditorium A.
- The general contractor installed the
entrance door frame to Auditorium A.
- They finished the installation of the
ceiling grid in Auditorium A.
- Auditorium B.
- The mechanical contractor installed
diffusers and flex duct.
- The general contractor installed the
entrance door frame.
- The walls in the Auditorium B were
primed.
- The electrical contractor installed conduit,
wiring, and light fixtures in the electrical
closet and mechanical room.
- They installed conduit for the new air
handling unit.
- Additional conduit was installed for the
electrical panel power feeds.
- The mechanical contractor set the new A/C
unit and installed the drip pan in the A/V room
(Room 4202).
- Crews installed piping for the A/C unit
in A/V Room 4202.
- They insulated the chilled water supply
lines for the auditorium A/C units.
- The general contractor installed metal
framing for the audio/visual room.
- They sanded and prepped the sheetrock at
the entrances to Auditoriums A and B.
- The contractor installed foam insulation
inside the new door frames.
Dental School 6th and 8th
Floor Lab Renovations:
- The contractor applied water-proofing mastic
to the exterior walls.
- Sheetrock was installed on the southwest
walls.
- Crews installed sheetrock on the
interior walls in Rooms 8405D, E, and F.
- Sheetrock was hung on the exterior walls
in Suite 8405.
- They installed insulation on the exterior
walls in Rooms 8405B and 8405K.
- Insulation was installed for all
interior walls.
- The corridor wall framing was extended to
the slab of the deck above.
- Framing support rods were installed for
all walls in Suite 8405.
- Blocking was installed for the walls in
Rooms 8405C, 8405D, and 8405G.
- The general contractor honed and polished
the terrazzo floors in Rooms 6333 and 6335.
- The terrazzo in Room 8405A and Room
8405J was honed and polished.
- The electrical contractor connected the
electrical circuits to the electrical panels.
Library Commons Project:
- The contractor laid additional floor tiles
at the Library entrance and grouted the tiles.
- They installed and grouted perimeter
floor tiles in elevator lobby and the
restrooms.
- The contractor is installing wood supports
around the concrete columns in the Commons area
that will allow custom wood column covers to be
affixed.
- Crews began the installation of custom
wood panels around the columns.
- They installed wood panels around the
column nearest the coffee kiosk.
- The contractor began installation of the
coffee kiosk.
- They installed the coffee kiosk cooler
and wall panels.
- The contractor installed cabinetry for
the coffee kiosk.
- The countertops and shelving for the
coffee kiosk were installed.
- The contractor installed the frieze on the
frieze wall.
- Doorframes for the restrooms have been
installed.
- Ceiling grid was hung in the Women's
restroom.
- The contractor installed sheetrock on the
center bulkhead.
- LSUHSC electricians completed the electrical
rough-in in the center head wall.
- Power has been provided to the air
handling unit.
- The fire alarm subcontractor removed old
fire alarm devices.
- They began rough-in for fire alarm
devices.
Lions/LSU Clinic Permanent Repairs
and Mitigation:
- The mechanical subcontractor set plumbing
fixtures on the CSRB side of the 6th Floor.
- They demolished old storm drain that was
run above the ceiling on the 6th Floor,
Gravier/Bolivar St. side.
- Storm drain pipe is being installed
in the new stairwell from Floors 5 and
6.
- The mechanical subcontractor set water
fountains on the 6th Floor, S. Prieur St.
side.
- Crews tested water fountains and
fixtures in the Women's restroom on the
6th Floor, S. Prieur St. side.
- They installed heating hot water pipes
on the 6th Floor, Bolivar St. side.
- The mechanical subcontractor installed
VAVs on the 6th Floor Gravier/Bolivar St.
side.
- They ran pipe to the VAVs on the 6th
Floor, Gravier St. side and installed
return air lines on the 6th Floor, S.
Prieur St. side.
- The mechanical subcontractor installed
medical gas outlet boxes on the 6th Floor in
the simulation rooms.
- They installed piping for the sump pump
in the pit of Elevators 1 and 4.
- The mechanical subcontractor installed
supply duct on the 6th Floor on the Gravier
St./Bolivar St. side.
- The electricians wired Panel 2AC to the
switchgear on the 2nd Floor, wired the
switchgear to Panel 2AC2A, and installed the
emergency junction box on top of the switchgear.
- The electrical subcontractor installed
Panel LA6A on the 6th Floor.
- They ran conduit for lights on the 6th
Floor, Gravier/Bolivar St. side.
- Entergy installed electrical service to
the building.
- The electrical subcontractor pulled
wires for the switch gear from 1st Floor to
the 2nd Floor.
- The electrical subcontractor wired Panel
2AB and the B riser to the new switchgear.
- They ran conduit for Panel LA6A, wired
domestic water pumps to Panel AC2A, wired
Riser B to the switchgear breakers on the
2nd Floor, installed and wired Panel 2AB on
the 2nd Floor and installed cable tray on
the 2nd Floor, Gravier hallway side.
- The electrical subcontractor ran conduit
from Panel LA6A to the 6th Floor junction
box, pulled two feeders for bus duct Riser A
(Bolivar side of building) on the 1st Floor
to the new switchgear and installed
additional cable tray on the 2nd Floor,
Gravier hallway side.
- Electricians pulled the last 2 feeders
for bus duct Riser A (Bolivar side of
building) on the 1st Floor to the new
switchgear on the 2nd Floor.
- They wired the switchgear to the clean
power conditioner on the 3rd
Floor, installed cable tray on the 2nd Floor
and ran wire from the new switchgear to the
ATS on the 2nd Floor.
- The fireproofing subcontractor painted the
main structure beams on the 5th Floor of the new
exterior stairwell.
- The fireproofing subcontractor painted
the exterior beams in the new stairwell;
Floors 1 through 6.
- The sprinkler contractor rerouted sprinkler
piping on the 6th Floor, S. Prieur/Gravier
Street side.
- The sprinkler subcontractor installed
sprinkler heads on the 6th Floor, Bolivar
St. side.
- The contractor completed a wide variety of
work throughout the building.
- Crews installed studs and sheetrock on
the 2nd Floor by the new stairwell on the
Gravier St. side.
- They installed metal studs and
sheetrock on the 2nd Floor between the
new fire pump and the medical air/vacuum
pumps.
- The contractor taped and floated
sheetrock on the 6th Floor, S.
Prieur/Gravier Street side.
- They primed the 6th Floor walls on
the Gravier/Bolivar Street side and
painted marker boards on the Perdido
Street side.
- Crews installed studs and sheetrock
in the 2nd Floor electrical room and
plastered the 1st Floor CMU wall on the
S. Prieur Street side.
- They installed studs and sheetrock
in the 2nd Floor mechanical room.
- The contractor painted the 6th Floor
walls on the Gravier/Bolivar Street
side.
- The contractor taped and floated
walls in the mechanical room on the 2nd
Floor.
- The contractor painted the 6th Floor
walls on Gravier and S. Prieur Street
side of the building.
- Crews installed studs and sheetrock
on the 2nd Floor on the CSRB side.
- The contractor painted on the 6th
Floor, Gravier St. side.
- Sheetrock on the 2nd Floor CSRB side
was floated.
- The contractor painted walls on the
2nd Floor, CSRB side.
- They applied fire retarded paint to
the plywood for the network and phone
rooms.
- Crews continued to plaster the 1st Floor
CMU wall on the S. Prieur Street side and
install wall tile in the restrooms on the
1st Floor, S. Prieur Street side.
- They finished laying floor tiles in
the Men/Women bathroom on the 1st Floor,
S. Prieur Street side.
- Wall tile was installed in the lobby
area on the corner of Gravier and
Bolivar Street.
- They grouted wall tile in the 6th
Floor restrooms.
- The contractor applied plaster for
the 1st Floor lobby walls on the corner
of Gravier and Bolivar Street.
- They applied first coat of plaster
on the 1st Floor restroom wall by the
elevators.
- A crew plastered the restroom on the
1st Floor, Bolivar/CSRB side.
- They installed restroom accessories
on the 6th Floor.
- They installed CMU on the front of
the 1st Floor lobby by Elevators 1 and
4.
- Crews demolished concrete blocks of
Elevators 1 and 4 on the 1st Floor.
- A crew framed the wood block for the
Elevators 1 and 4.
- The contractor poured concrete for
the new wall by Elevators 1 & 4.
- A crew ground down the cement in the
pits of Elevator 1 and 4.
- The contractor installed door frames in
the back rooms of the 6th Floor, Gravier and
S. Prieur Street side.
- Doors were installed on the 6th
Floor, Gravier/S. Prieur St. side.
- They installed doors on the 2nd
Floor.
- The contractor installed ceiling grid on
the 6th Floor on the Gravier/S. Prieur side.
- They installed ceiling grid in the
simulation rooms.
- The contractor installed ceiling
grid in the middle of the 6th Floor.
- Crews primed the marker boards in the
6th Floor simulation rooms.
- The contractor installed trim and
trays for the marker boards on the 6th
Floor, CSRB side.
- Projection mount poles were installed on
the 6th Floor.
MEB MDL 6 Renovations:
- The contractor completed installing studs
frame around the steel support for sound
attenuation in the main MDL room.
- The old floor tiles were removed from Room
4117A.
- The contractor installed piping for hot/cold
water and drainage in the 3rd Floor ceiling for
MDL 6.
- They installed sheetrock above the movable
partitions.
MEB 2nd Floor Lobby Renovation:
- The sprinkler subcontractor installed
sprinkler pipe along the walls by the lecture
halls and in the middle of the ceiling on the
Roman Street side.
- The contractor installed sprinkler main
piping on the Bolivar St. side of the lobby.
- They began installing sprinkler branch
piping on the Bolivar St. side of the lobby.
- The contractor touched up the paint after
the sprinkler pipe installation.
- They removed ceiling remnants on the
Bolivar Street side.
- Crews installed the knife edge ceiling
grid trim on the S. Roman Street side.
- The center ceiling framing was installed
on the S. Roman Street side.
- Obsolete computer wiring has been
removed from the center of the lobby.
MEB Pharmacology Laboratory
Renovations:
- The Office of Facility Planning conducted
the pre-construction meeting.
- The contractor removed the ceiling and lab
furniture in the large laboratory area.
- They removed the ceiling grid in the
administrative area.
- The contractor began removing walls in Rooms
5221, 5220, 5124, 5218, 5218A, 5219, 5220, 5220A
and 5124A.
MEB 6109 & 6148 Lab Renovations:
- The contractor installed new cove base in
both rooms.
Residence Hall 2nd Floor Expansion:
- The contractor installed five vertical
mullions above the entrance of the Residence
Hall.
- They installed additional vertical and
horizontal mullions in front of the
temporary wall.
- Horizontal mullions for the new curtain
wall below the roof have been installed.
- The contractor taped and floated the
interior temporary wall.
- Crews patched the plaster ceiling on the
Bolivar St. side of the enclosure.
- The contractor removed the mailboxes.
- They removed the brick pavers under the
existing mailbox room.
- Wood nailers for roof flashing above the
walkway were installed.
- The contractor installed roofing insulation
and roofing membrane on the roof of the lobby
expansion.
- Two doors between Tower A and Tower B on the
Perdido St. side were removed.
- The contractor installed rubber glazing for
the expanded storefront system on Perdido St. to
prepare for glass installation.
Exterior/Landscaping:
- Facility Services installed landscape edging
and mulched the planting beds in front of the
Resource Center.
- Crews removed old vegetation in front of
the Resource Center.
- They installed irrigation lines in front
of the Resource Center.
- Facility Services activated the new
irrigation station on the front corner of
the Resource Center closest to Tulane Ave.
- The contractor started the sidewalk
construction and landscape grading at the corner
of Gravier St. and S. Claiborne Ave.
- They placed the base course for the new
concrete sidewalk along the Gravier St. side
of the District Energy/Gravier St. Garage.
- Crews continued site work and grading at
the corner of Gravier/S. Claiborne.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|