|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #84
Posted: January 16, 2009
The holidays are behind us and work
on the various projects around campus has returned
to a more normal schedule. Some of the contractors
worked during the holidays and this update reflects
their accomplishments during that period.
Faculty and staff are settling into
their offices on the upper floors of the Clinical
Education Building as work continues on preparing
the lower floors for use. New ceiling light fixtures
have been installed in the 2nd Floor hallway. The
4th Floor lounge received a refrigerator, sink and
ice machine in the kitchenette space and new
cabinetry has been installed. Offices and hallways
are being painted and/or touched up on the 4th
Floor. On the 5th Floor, new conference room
furniture was installed and cabinets installed in
the lounge.
Work on the renovations to the
auditoriums in the Dental School Clinic Building
continues. The newly poured concrete risers have had
a layer of thin set applied and have been ground
down in preparation for the installation of
carpeting. The room that will house the new
audio/visual equipment has been framed up and the
speaker housings in both rooms have been dry walled,
taped and floated. Electrical work includes the
installation of additional down lights, the
installation of trim rings on the fixtures, and new
dimmer controls.
The lab renovations on the 6th and
8th Floors of the Clinic Building are progressing.
Door frames have been installed in new walls.
Exterior walls are being insulated and sheet rocked.
The new walls in most of the rooms have been taped
and floated and are being prepared for primer and
paint. The fume hood exhaust duct was installed in
Room 8405B.
The branch duct work has been
installed throughout the Library Commons area. HVAC
diffusers have been installed and adjusted along the
window walls and in the café and study areas. Floor
tiles have been installed and grouted on the floors
in front of the elevators and on the frieze wall.
The bar top framing has been completed in the café
area. New dry wall has been taped and floated. The
installation of the custom wood column covers
continues.
The electricians working at the
Lions/LSU Clinic continue to switch major electrical
feeds over from the old switch gear on the 1st Floor
to the new gear located on the 2nd Floor. They have
also been busy running conduit and installing
fixtures, switches and outlets on the 6th Floor in
the old laboratory area. New fixtures have been
installed in the large Lecture Room.
The mechanical contractor continues
to run and insulate supply lines that connect to the
new VAVs located on the 6th Floor. Chilled water
lines have been run to the AHU on the 1st Floor. Old
storm drain has been removed from above the ceiling
in locations on the 6th Floor where they interfered
with the routing of new infrastructure components.
New storm drains were installed in the stairwell on
the 5th and 6th Floors. The general contractor has
crews working through out the 1st, 2nd, and 6th
Floors completing a variety of work.
Renovations to Multidisciplinary Lab
6 are well underway. Rough in plumbing for the new
casework has been completed. The structural support
for the folding partitions has been installed and
the steel support for the partition track has been
raised. Ceiling grid has been installed in the main
MDL and the corner rooms. Sprinkler heads have been
put in place. Light fixtures are being installed and
connected. Supply and return air grills are being
installed.
The sprinkler pipe has been
installed throughout the MEB 2nd Floor lobby. The
floor has been prepared and the floor tile and
carpet has been installed. Tile base was also
installed. Demolition in the Pharmacology labs has
been completed. New walls have been framed up in the
laboratory area and walls are being erected in the
administrative area. The electricians have begun to
run conduit in the lab area. Across the street, new
class is being installed on the new storefront at
the Residence Hall lobby. The contractor has framed
up the various fur downs in the lobby area around
the new HVAC diffusers.
Here are highlights of work that has
been accomplished across the holiday period and
during the past two weeks.
Repair Work at 1542 Tulane Ave.:
- Lighting:
- The electrical contractor installed new
light fixtures in the 2nd Floor hallway.
- Lounge Areas:
- Facility Services installed the sink,
refrigerator and the ice machine in the 4th
Floor lounge kitchenette.
- Furniture:
- The furniture vendor installed new
cabinets in the 5th Floor lounge and set-up
conference room furniture in Rooms 524 and
544.
- They set up furniture in Conference Room
639 and installed the new cabinetry in the
4th Floor lounge.
- Misc.:
- The granite contractor repaired walls in
the center hallway on the 1st Floor.
- The general contractor sanded and primed
in Room 545.
- The general contractor framed new walls
and installed drywall in Room 443.
- The painting contractor painted the
front stairwell on the Claiborne Avenue end
of the front hallway.
- The terrazzo contractor made repairs to
the cove base in the front hallways on the
4th through the 7th Floors.
- LSUHSC Facility Services replaced two
fan coil units in Rooms 516 and 517.
- Facility Services removed the old
striping in the Lakeside Lot
- A leaking fan coil unit supply line was
repaired in Room 417.
- Facility Services painted offices and
hallways on the 4th Floor and
moved building supplies from Rooms 111, 111A
and 111B to Room 313.
Dental School Auditoriums A & B:
- The contractor spread and leveled thin set
on the floors in preparation for the carpet
installation.
- The general contractor installed the door
frame for the new A/V Room 4202.
- The flooring contractor ground the floors
for the riser seating in Auditoriums A and B.
- The contractor installed metal framing for
the audiovisual room.
- The general contractor installed sheetrock
for the speaker housings in Auditoriums A and B.
- They taped and floated sheetrock speaker
housings in Auditoriums A and B.
- The mechanical contractor installed
additional insulation on the ductwork of the
AHUs in the mechanical rooms.
- The electrical contractor mounted the dimmer
control box in the electrical room.
- The electrical contractor installed the down
lights in Auditorium A and B.
- The electrical contractor installed trim
rings for the recessed can light fixtures in
Auditoriums A and B.
Dental School 6th and 8th
Floor Lab Renovations:
- The general contractor completed
installation of door frames and installed
insulation along the exterior wall in Room 6335
(Moss Street wall).
- The contractor installed wood blocking along
the Castine Street Side, in Room 6335.
- The mechanical contractor installed a fume
hood exhaust duct in Room 8405B.
- The mechanical contractor installed the
supply duct outlet taps for the ductwork in
8405B.
- The contractor installed sheetrock on the
southwest walls.
- The contractor removed drain pipe thimbles
from the floor in Room 6335.
- The electrical contractor installed new
outlet box rings for data duplex receptacles,
and light switches in Rooms 6333 and 6335.
- The contractor finished installing sheetrock
around doorways and service utilities in Room
8405A, 8405D, 8405E, 8405F, 8405G and 8405J.
- The contractor taped and floated the walls
in Rooms 6333, 6335, and 8405.
- The contractor sanded and placed the second
skim coat on the walls in 6333, 6335, and Suite
8405.
Library Commons Project:
- The contractor began installing wood panels
on the feature wall near the entrance.
- They installed wood ceiling panels and
installed the bar tabletop framing in the cafe
area.
- Crews continued installing the custom column
covers.
- The contractor grouted wall tiles on the
frieze wall and installed floor tiles near the
Library entrance.
- The contractor installed HVAC diffusers near
the window walls and adjusted HVAC diffusers in
the cafe and study area.
- The contractor installed sprinkler heads in
the café area.
- The mechanical contractor completed all
branch duct work.
- The contractor installed metal base around
the columns.
- LSUHSC electricians installed light fixtures
in the coffee kiosk.
- The contractor taped and floated the walls
in the Library Commons and installed a doorframe
in the small multi media room.
Lions/LSU Clinic Permanent Repairs
and Mitigation:
- The mechanical subcontractor installed chill
water lines connecting to the AHU on the Bolivar
St. side of the 6th Floor.
- Chilled water lines were run to the AHU
on the 1st Floor, Bolivar St. side.
- The mechanical subcontractor set
plumbing fixtures on the CSRB side of the
6th Floor.
- They demolished old storm drain that was
run above the ceiling on the 6th Floor,
Gravier/Bolivar St. side and new storm drain
pipe was installed in the new stairwell from
Floors 5 and 6.
- The mechanical subcontractor installed
heating hot water lines and supply ducts to
the new VAVs on the 6th Floor, Bolivar
Street side.
- They caulked the 6th Floor, S. Prieur
Street restroom fixtures.
- Additional supply duct was installed and
insulated on the Bolivar St. side of the 6th
Floor.
- The mechanical subcontractor began
installing control wire to the VAV boxes on
the CSRB side of the 6th Floor.
- They installed medical gas outlet boxes
in the simulation rooms and insulated
heating hot and chilled water lines on the
Bolivar St. side of the 1st Floor.
- The electrical contractor completed the
transfer of the 2 existing A/C risers from the
old to the new switchgear.
- Electricians installed wire for outlets
and lights on the 6th Floor, Gravier/Bolivar
side.
- They lifted the new emergency generator
onto the roof of the building.
- The electrical subcontractor installed
Panel LA6A on the 6th Floor.
- They ran conduit for lights on the 6th
Floor, Gravier/Bolivar St. side.
- The electricians wired Panel 2AC to the
switchgear on the 2nd Floor, wired the
switchgear to Panel 2AC2A, and installed the
emergency junction box on top of the
switchgear.
- The electrical subcontractor installed
lights in the 6th Floor large lecture room
- They continued installing outlets and
switches on the Gravier St./Bolivar St. side
of the 6th Floor and roughing in electrical
conduit in the old laboratory space.
- The electrical subcontractor installed
the buss duct tap box for the B riser.
- The general contractor installed additional
sheetrock in the new mechanical/electrical room
on the 2nd Floor.
- Crews installed granite panels near the
1st Floor elevators.
- They began framing the walls in the old
lab space on the 6th Floor.
- New ceiling grid was installed in the
6th Floor hallway on the CSRB side of the
building.
- The walls on the 2nd Floor were
fire-caulked.
- The contractor taped and floated
sheetrock and installed corner bead on the
6th Floor.
- Projection mount poles were installed on
the 6th Floor.
- Crews installed studs and sheetrock on
the 2nd Floor by the new stairwell on the
Gravier St. side.
- Crews plastered the 1st Floor CMU wall
on the S. Prieur Street side and installed
wall tile in the restrooms on the 1st Floor,
S. Prieur Street side.
- The contractor installed studs on the
6th Floor on the Bolivar Street side/
- They framed the vanities in the
restrooms, installed fire extinguisher
cabinets on the 6th Floor.
- The contractor cut sink holes in the
bathroom vanities on the 6th Floor, painted
in 6th Floor simulation rooms, and installed
ceiling grid and ceiling wire on 6th Floor.
- Crews plastered above the doorframe on
the 1st Floor, Gravier/Bolivar St. side.
- Crews caulked between the granite seams
on the 1st Floor, Bolivar St. side, fire
caulked CMU walls on the 1st Floor and
continued fireproofing the beams on the 1st
– 6th Floors of the new stairwell.
- The contractor continued framing the
soffit on the 6th Floor Bolivar
St. side.
- Crews installed ceiling tiles in 6th
Floor simulation rooms, in the middle
hallways on the 6th Floor and on the 2nd
Floor, CSRB side.
- The sprinkler subcontractor installed
sprinkler heads on the Gravier St. side of the
6th Floor.
- The sprinkler subcontractor installed
sprinkler heads in the 6th Floor simulation
rooms.
- They installed sprinkler heads in the
middle of the 6th Floor and tied in pipe
from the pump to stairwell riser on the 2nd
Floor.
MEB MDL 6 RENOVATIONS:
- Floor tiles were removed from Rooms 4114A
and 4121A.
- The contractor completed installation of the
structural support for the folding partitions.
- The plumbing for the new casework was
roughed in.
- They raised the steel support for the new
partition track in the MDL room.
- The contractor completed installing ceiling
grid in the main MDL room and in three of the
corner rooms.
- The ceiling light fixtures were installed.
- The contractor wired light fixtures in the
main MDL room.
- They began relocating sprinkler heads in the
main MDL room.
- The contractor is installing supply and
return grills in the main MDL room.
MEB 2nd Floor Lobby Renovation:
- The sprinkler contractor completed
installation of the new sprinkler piping.
- The flooring contractor prepped the floor
for tile installation.
- The new floor tile and tile base was
installed.
- The new carpet was installed.
Residence Hall 2nd Floor Expansion:
- The contractor began installing the new
glass on the Perdido and Bolivar sides of the
lobby.
- They installed the remaining tinted
glass on the Perdido Street side.
- The spandrel glass on Perdido Street
side has been installed.
- The break metal for the diffuser and flex
duct was installed between Towers A and B.
- The vertical mullions were installed in
front of the temporary wall.
- The contractor painted the plywood for the
temporary wall.
- Stud frames were constructed for the
fur-down along the diffusers in the lobby
between Tower A & B.
- The contractor installed exterior mullion
trim and flashing on the roof.
- A crew installed sheetrock for the soffit
along the Perdido Street side of the A & B
Towers.
- The contractor installed the stud frame for
the soffit on the corner of S. Roman St. and
Perdido St.
MEB PHARMACOLOGY LAB RENOVATIONS:
- The contractor removed the interior walls in
the administrative area and in the laboratory
area.
- The electrical subcontractor removed the
lights from the administrative area and the
laboratory area.
- The old ceilings have been removed.
- The electrical subcontractor completed
demolition.
- The general contractor framed walls inside
the laboratory area.
- They continue to frame walls in the
administrative area.
- The electrical contractor continues to run
conduit in the laboratory area.
EXTERIOR/LANDSCAPING:
- Facility Services graded the landscaping in
front of the Resource Center and planted new
shrubs.
- Facility Services installed landscape edging
and mulched the planting beds in front of the
Resource Center.
- Brick pavers have been installed for the new
sidewalk along Gravier St. adjacent to the
Gravier Garage.
- Sprinkler piping and edging have been
installed in the lot at the corner of S.
Claiborne Ave. and Gravier St.
- Facility Services mulched and cleaned the
planting beds in front of the Allied
Health/Nursing Building.
- Facility Services installed irrigation
piping and sprinklers beside the Resource
Center.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|