From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #86
Posted: February 13, 2009
A new major hurricane recovery
project is about to get underway. The roof of the Allied Health/Nursing
Building was damaged by the high winds and uplift
pressure generated by Katrina. As a result the entire roof must be replaced. The contract has been awarded and the initial
preparations are underway. The contractor is required to install and use
an exterior elevator/lift to move men, equipment and
materials to the rooftop. The concrete base for the lift has been
poured.
Bids have recently been opened
for the project to replace the roof of the
Resource Center. This project is also related to damage done
by Katrina. We anticipate that a decision on the award of
this contract should be made shortly. The contract documents are likely to take a
month to be prepared and executed, so the beginning
of actual work is still some time away.
Over at the
Clinic Education Building, the work on
the 4th Floor is substantially complete. New network drops have been installed and
tested.
The network wiring crew has moved to the 1st Floor. Furniture is being installed and arranged in
4th Floor offices and conference rooms. New fan coil units are being connected in
various locations on the 2nd and 3rd Floors. The sprinkler pipe has been installed in the
2nd Floor lounge, and the crew has moved to the 1st
Floor lounge.
The lab renovations on the 6th
and 8th Floors of the Dental School Clinic Building
are moving towards completion. The interior walls of all the 8th Floor
spaces have been primed and painted. Door frames and doors have been installed and
doors are being painted. The electricians are completing finish work;
installing light fixtures, bulbs and cover plates
for wall switches and receptacles. Damaged areas of the terrazzo flooring on the
8th Floor have been patched, honed and polished.
The most noticeable work being
done at the Lions/LSU Clinic is the installation of
the steel vertical and horizontal mullions on the
exterior stairwell. The exterior skin of the stairwell will be
attached to the mullions. Sprinkler pipe is also being installed in the
stairwell. Inside the building, a lot of finish work is
underway. Floor tiles have been installed and grouted. Partitions and mirrors are now in place in
the Women’s restroom on the 6th Floor. Window frames have been installed in the 6th
Floor simulation rooms. Drywall is being hung and floated in the 1st
Floor elevator lobby. The mechanical subcontractor has started
installing the diesel fuel lines that will supply
the roof mounted emergency generator.
The Library Commons project is
progressing. The walls in the multimedia rooms have been
primed and painted. The composite walls in those spaces are being
installed and floated. New carpet has been installed in the large
multimedia room and in the large study area. The automatic doors that will serve as the
main entrance to the Library have been installed. Security cameras have been mounted in key
locations. Light fixtures have been installed above the
coffee kiosk and the kiosk sink has been installed.
Old electrical conduit has been
removed from the exposed ceiling portions of the MEB
2nd Floor lobby. The storefront wall under the window frames
has been finished and the interior walkway door
installed. Ceiling grid is going up on the Bolivar St.
side of the lobby.
The concrete subfloor in MDL 6
has been prepped and VCT has been installed in the
main lab space and the corner rooms. The installation of the new casework frames
is well underway in the main lab. The gas lines for the new casework have been
roughed in. Marker boards have been replaced and new
electrical receptacles have been installed. The renovations to the Pharmacology labs are
progressing well. New waste water drains have been installed. New drywall and insulation have been
installed in the laboratory area. Drywall has also been hung in the
administrative area. Conduit has been installed throughout the
administrative area and light circuits are being
pulled.
The lobby expansion project at
the Residence Hall continues. The temporary wall has been removed. The door frame, the door and the sidelight
glass on the walkway leading to the Residence Hall
Lobby have been installed. The fur downs on the 2nd Floor and mezzanine
have been dry walled and ceiling grid is being hung. Additional hard HVAC duct that serves the
extended lobby areas has been installed. New roof drains have been put in place and
connected.
The LSUHSC Facility Services
landscape crew has been busy at the Resource Center. They planted shrubs in the planting beds on
the
Gravier St.
side of the building. Landscape edging has been installed around
the planting bed at the corner of Bolivar St. and Gravier St. They installed irrigation piping and
sprinklers behind the
Resource Center at the corner of S. Prieur St. and Gravier St.
The landscape work at the
District Energy Garage has progressed nicely. The contractor placed concrete footers for
the new fence at the corner of
Gravier St. and
S. Claiborne Ave. and
placed a section of the new brick sidewalk by the
District Energy Garage elevator entrance on Gravier St. New fence panels have been installed. Trees and shrubs have been planted and the
planting area has been mulched. Sod has been laid and new benched have also
been installed.
Here are highlights of work
that has been accomplished during the past two
weeks.
Repair Work at
1542 Tulane Ave.:
- Painting:
- LSUHSC Facility
Services completed painting offices and
hallways on the 4th Floor.
- They began painting
hallways on the 3rd Floor.
- Lounge Areas:
- The general contractor
removed the old sprinkler piping from the
1st and 2nd Floor lounge areas.
- They completed
installing new sprinkler piping in the 2nd
Floor lounge.
- Crews have begun to
install new sprinkler pipe in the 1st Floor
lounge.
- Furniture:
- The furniture vendor
installed furniture in offices on the 4th
Floor.
- Misc.:
- The mechanical
contractor continues piping new fan coil
units on the 2nd and 3rd Floors.
- The network wiring
contractor completed installation of new
network drops on the 4th Floor.
- They continue to
install new network wiring on the 1st
Floor.
- LSUHSC Facilities
Services installed new doors on the freight
elevator lobby and installed two exterior
lights adjacent to the Shipping and
Receiving entrance.
Dental School
6th and 8th Floor Lab
Renovations:
- The contractor installed
the remaining corner guards in Rooms 8405A -
8405K.
- Cove base and plumbing
utility access panels have been installed
along the walls in Suites 8405A -
8405K.
- They installed doors
in Rooms 8405A, 8405B, 8405C, 8405E, 8405F,
and 8405K.
- The new ceiling tiles
were installed on the 6th and 8th Floors.
- The electrical contractor
installed light switches and duplex receptacles
in Suite 8405A - 8405K, and installed
light fixtures in Room 6335.
- They installed bulbs
for the new light fixtures and cover plates
for light switches and duplex receptacles.
- The electricians
installed bulbs for the new light fixtures
and cover plates for light switches and
duplex receptacles in Rooms 6333 and 6335.
- The contractor
installed the power feed for the exhaust fan
motor that will be installed on the roof.
- The painting contractor
primed and applied the first and second of coats
of paint on the door frames in
Suite
8405A - 8405K.
- They painted the
interior rooms on the 8th Floor.
- The insulation contractor
insulated the duct taps in Room 8405A.
- The mechanical contractor
installed flex duct and supply diffusers in
8405A and 8405B.
- The flooring contractor
installed the terrazzo floor patches in Rooms
8405A, 8405B, 8405C, 8405F, 8405G, 8405H, and
8405I.
- They honed and
polished the terrazzo floor patches in
Suite
8405.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- The mechanical
subcontractor insulated heating hot and chill
water lines in the mechanical room on the 6th
Floor, Bolivar Street side.
- They are installing
the new fire dampers on the 2nd Floor.
- They continue
installing control wire for AHU 1-4 on the
1st Floor.
- The mechanical
subcontractor is installing the diesel fuel
lines that will supply the roof mounted
emergency generator in the east chase on
Floors 2 through 9.
- The electrical
subcontractor switched the power service for
panel HDRB to the new switchgear.
- Electricians pulled
wire for the electrical outlets and switches
on the 6th Floor, Gravier/Bolivar Street
side and installed conduit to the generator
in Room 908.
- The contractor
installed conduit in Rooms 908 and 910.
- All the receptacles on
the 6th Floor have been tested.
- They and roughed in
lights in the old lab area on the 6th Floor.
- The sprinkler
subcontractor ran distribution lines to the new
stairwell and at the new fire pump.
- Crews installed sensor
lines to the fire pump controller on the 2nd
Floor, CSRB side.
- They installed valves
on the sprinkler pipe riser lines in the
east and west stairwells.
- The contractor installed
storefront glass located near the new stairwell
on the 6th Floor.
- They installed the mud
bed for tile in the elevator lobby on the
6th Floor.
- Sheetrock was hung in
the 6th Floor elevator lobby.
- The contractor
installed doors and transoms on the 1st
Floor, CSRB side.
- They installed window
frames in the 6th Floor simulation room on
the Bolivar St./Gravier St. side of the
floor.
- The restroom
partitions and mirrors were installed in the
Women’s restroom on the 6th Floor, S. Prieur Street
side.
- Crews installed metal
framing in the 6th Floor elevator lobby and
reception area and angle supports on top of
CMU walls on the 1st Floor, S. Prieur Street side.
- They plastered the
walls in the restrooms on the 1st Floor,
Bolivar/CSRB side.
- The contractor grouted
the floor tile on the 1st Floor, S. Prieur Street side.
- Crews are taping and
floating the walls in the elevator lobby and
cleaning the granite wall on the 1st Floor.
- The vertical steel has
been installed on the 1st and 2nd Floors of the
exterior stairwell.
- The horizontal steel
was installed on the 1st through 4th Floors
of the new stairwell.
- The contractor
installed curtain wall mullions on the 2nd
through the 4th Floors of the new stairwell.
- Crews continue
installing curtain wall mullions on the 5th
and 6th Floors of the exterior stairwell.
Library Commons Project:
- The contractor installed
storefront at the stairs.
- LSUHSC personnel installed
security cameras.
- The contractor sanded and
primed walls and installed the new main
automatic entrance doors to the Library.
- LSUHSC electricians
installed light fixture supports and light
fixtures above the coffee kiosk.
- The contractor painted the
walls the main study area and primed and painted
the walls in the multi-media rooms.
- The contractor painted the
fire exit door near the stairs.
- LSUHSC plumbers installed
the water fountain.
- The painting contractor is
touching up conduit in the black ceiling area.
- LSUHSC plumbers connected
the large kitchen sink for the coffee kiosk.
- The flooring contractor
completed the subfloor prep for the installation
of carpet.
- They completed
carpeting the large multi media room.
- The carpet in the
large study area has been laid.
- The contractor continues
installing and floating the composite wall
panels in the multi-media rooms.
MEB 2nd Floor Lobby Renovation:
- The contractor installed
ceiling grid on the
Bolivar Street side.
- Crews finished the
storefront wall under the window frames.
- The contractor installed
the interior storefront walkway door.
- The contractor floated the
storefront wall under window frames.
- They installed the steel
frame for the exterior sliding glass door on the Bolivar Street side.
- Crews painted the exposed
sprinkler pipe and painted underneath the store
front windows.
- The contractor removed
electrical conduit from the exposed ceiling.
MEB MDL 6 RENOVATIONS:
- The contractor completed
patching and leveling the concrete subfloor
floor in the lab.
- They installed new VCT
tiles in the main MDL room and in the corner
rooms.
- The contractor is
installing the casework frame in the main MDL
lab.
- They installed marker
boards and replaced existing receptacle outlets
with new ones.
- The contractor roughed in
the gas line for the new casework.
MEB PHARMACOLOGY LAB
RENOVATIONS:
- The mechanical contractor
installed waste water pipes below the laboratory
area.
- The general contractor
completed the sheetrock installation and
insulation in the laboratory area.
- Crews hung sheetrock
in the administrative area.
- The electrical contractor
completed the installation of conduit in the
administration area.
- They began running
lighting circuits in the administration
area.
Residence Hall 2nd Floor
Expansion:
- The enclosure contractor
completed removing the temporary wall.
- They installed the
door frame, the door and the sidelight glass
on the walkway leading to the Residence Hall
Lobby.
- The contractor
installed break metal on the underside of
the new, expanded storefront along the Perdido Street
side.
- The interior contractor
completed painting the fur down for the lobby
and mezzanine level.
- The mechanical contractor
installed hard duct for the diffusers in the
extended lobby area.
- They installed hard
duct near Elevator B.
- A crew ran roof drain
pipes near the walkway.
- The
interior contractor installed ceiling grid for
the lobby between the
A & B Towers
and in the lobby.
- The flooring contractor is
removing exterior brick pavers on the corner of Bolivar St. and Perdido St.
DENTAL SCHOOL
BOILER INSTALLATION:
- A second temporary boiler
has been purchased to provide the redundancy
needed to support the clinical operations. The installation of the new boiler is
beginning.
- The contractor set up
a construction fence for this project.
ALLIED HEALTH/NURSING ROOF
REPLACEMENT:
- Preparations are underway
by the contractor who will replace the
storm-damaged roof on the Allied Health/Nursing
Building.
- The contractor set forms
for the concrete base that will support the
temporary exterior elevator lift.
- The concrete for the
base has been poured.
CSRB AUTOMATIC WALKWAY
INSTALLTION:
- The contractor installed
the door framing.
EXTERIOR/LANDSCAPING:
- Facility Services planted
shrubs in the planting beds on the Gravier St. side of the Resource Center.
- Crews finished
installing landscape edging around the
Resource Center planting bed
at the corner of
Bolivar St. and
Gravier St.
- They installed
irrigation piping and sprinklers and filled
in the open trenches.
- LSUHSC Facility
Services installed irrigation piping and
sprinklers behind the Resource Center
at the corner of
S. Prieur St.
and
Gravier St.
- Contractor placed concrete
footers for the new fence at the corner of Gravier St. and S. Claiborne Ave. and placed a
section of the new sidewalk by the District
Energy Garage elevator entrance on
Gravier St.
- The contractor
installed new fence panels and planted
shrubs and trees at the corner of Gravier St.
and S. Claiborne Ave.
- The contractor
continued planting trees and spreading mulch
in the lot at the corner of Gravier St.
and S. Claiborne Ave.
- Contractor laid sod
and installed new benches in the lot at the
corner of Gravier St. and S. Claiborne Ave.
- Facility Services prepared
the blue, brown and purple lots for use by University Hospital
during Mardi Gras.
RESIDENCE HALL WALKWAY RESURFACING
- The contractor painted the
final coat on the underside of the walkway.
- The project is now
complete.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|