From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #91
Posted: April 24, 2009
We were pleased to have an
opportunity to meet with Rep. Joseph Cao and his
staff for several hours on April 24th and discuss
the continuing challenges that we face in our
recovery from Hurricane Katrina. Tony Russell, the
acting head of the FEMA Temporary Recovery Office
participated in the meeting as did Charlie Axton,
appointed as head of the “Decision Team” by
Secretary Napolitano to resolve long-standing
disputes or issues delaying the recovery issues.
Also attending were Paul Rainwater, head of the
Louisiana Recovery Office and senior officials from
GOHSEP and the Office of Facility Planning and
Control. Rep. Cao asked a number of probing
questions that helped bring important issues to the
surface. The group was given a tour of key
facilities that helped to illustrate our challenges
and better inform the leaders of these key
organizations of the importance of the work that
remains to be done.
Rep. Cao and his staff
have promised that their interest and support of our
recovery will continue in the weeks and months
ahead. We have been encouraged to keep them informed
of issues that arise and our progress in resolving
them. A meeting with FEMA and GOHSEP has already
been scheduled for next week to review our
outstanding hazard mitigation proposals and identify
specific impediments to their submittal and approval
and establish the path forward to address each.
The contractors at the
Clinical Education Building are working toward
completion of the remaining tasks that must be
finished to allow reoccupation of the lower floors.
The three new offices that were created on the 3rd
Floor have had doors installed, the walls painted
and the ceiling grid is being installed. Carpet has
been installed in the 3rd Floor lounge and the
remaining data drops have been installed. The final
cleaning has begun in the offices along the center
hallway on the 3rd Floor.
The 2nd Floor lounge walls
have been painted and the ceiling tiles are in
place. Carpet has been laid in 2nd Floor offices.
Ceiling grid is being hung in the 1st Floor lounge.
Data drops and furniture have been installed in
Rooms 111 and 111A. The State Elevator Inspector
certified Elevators #1, #2 and #3 for normal use.
The remaining punch list items for the new roll up
door at the entrance of the parking garage have been
completed and final adjustments are done.
The flurry of work in the
Lions/LSU Clinic Building continues as the project
nears completion. A variety of trim work has been
finished on the 6th Floor. Sprinkler heads have been
installed in the computer lounge and elsewhere on
the floor. Window blinds have been hung in a number
of the exterior rooms. Additional light fixtures
were installed and the 6th Floor fire alarm devices
were trimmed out and tested. Stryker continues
installing and testing their equipment in the
simulation labs.
The granite pavers
surrounding the base of the new exterior stairwell
were installed and grouted. The exterior granite has
been waterproofed. Workers framed, insulated and
sheet rocked the interior walls of the new stairwell
on the 3rd through the 6th levels and the window
trim is being installed. The 1st Floor mechanical
rooms floors have been coated with an epoxy floor
coating and the walls have been painted. Lights and
electrical receptacles have been installed on the
1st Floor and conduit has been run to hold the 200
pair telephone cable being routed to the 2nd Floor
location.
The efforts at the Dental
School Auditoriums A & B are now focused on
installing the state-of-the-art audio/visual
equipment. The electrical contractor installed
conduit in the elevator lobby outside Auditoriums A
& B for the A/V wiring and connections. Creative
Presentations installed speaker wiring and
structural supports for the projector mounts in
Auditorium B. They installed speakers and wiring in
Auditorium A.
The contractor finished
installing the fire dampers and smoke detectors in
the Library Commons area. The restroom partitions
have been installed and the ceiling trim was
installed above the coffee kiosk. LSUHSC
electricians installed light fixtures near the
decorative screens and installed the faceplates for
the network drops. Wallpaper was hung beneath the
windows and in the back office area. The roll-up
doors have been tested in manual mode. LSUHSC
Facility Services personnel pulled wiring for the
fire phone and trimmed out the electrical
receptacles. The contractor installed sprinkler caps
throughout the space and started the general
cleaning of the construction areas.
The renovations to the
Pharmacology labs in the MEB are continuing. The
casework contractor installed the second side of the
peninsula casework and the countertops in Rooms
5219, 5219A and 5262. Fume hoods have been connected
and the sinks have been plumbed in. The new door
frame was installed in Room 5219 and VCT was
installed in the administrative area. The final coat
of paint was applied to Rooms 5262B, 5264, 5262A,
5206C and in the department head’s office. The
contractor installed receptacle raceways above the
laboratory furniture.
A new contract has been
issued to renovate Multi-Disciplinary Lab 3 in the
MEB. The renovations will replicate the renovations
that were completed in MDL 6 including a completely
new layout, new casework, new countertops, new
flooring, etc. The audio/visual equipment will be
replaced with state of the art equipment. The
contractor began work by demolishing the existing
casework, removing acid waste lines, and
disconnecting the old plumbing. They removed ceiling
grids and tiles, removed light fixtures, and
disconnected receptacle outlets. The A/V contractor
de-installed the old LCD and speakers in the main
MDL lab area. The existing partitions have been
removed from the main MDL room and the casework and
ceiling from Room 4108A.
Work on the MEB 2nd Floor
lobby renovations continue. The contractor installed
the new storefront frames at the Medical Center
Stores location and installed the fur down across
from the elevators. The fur down was taped and
floated and the loose wire was removed from the open
ceiling areas. The wall panel contractor installed
wall panels along the Medical Center Stores wall and
the contractor began installing new metal around the
elevators.
The interior contractor
taped and floated the fur down in the expanded lobby
area of the Student Residence Hall. They completed
installing ceiling tiles in the A and C Towers and
in the area between the A & B Towers and began
framing the sheet rock ceiling in the expanded lobby
space. The electrical contractor ran fire alarm
wires in the expanded lobby area. The contractor
installed ceiling grid for the sheetrock ceiling
underneath the mezzanine level of the A & B Towers
and in the expanded lobby area. They installed
ceiling grid for the acoustical ceiling between the
B & C Towers.
The contractor responsible
for installing the new roof on the Allied
Health/Nursing Building has made good progress. The
contractor removed a 30 ft. by 30 ft. section of the
roof at the corner of Roman St. and Gravier St. and
another 30 ft. by 30 ft. section of the roof at the
corner of the MEB loading dock and Roman Street.
They applied the temporary two-ply roofing system to
those sections of the roof. Workers installed
tapered insulation and a cap on a 40 foot section of
the roof parallel to Perdido St. and on a section
forty feet beyond the elevator penthouse toward S.
Roman St. The contractor removed the old flashing
from around the roof.
Here are highlights of
work that has been accomplished during the past two
weeks.
REPAIR WORK AT 1542 TULANE
AVE.:
-
The general contractor
completed installing doors in Room 111B.
-
Painting:
-
The contractor
painted the walls in Rooms 341, 342, and
343.
-
They applied the
first coat of paint in the auditorium.
-
Lounge Areas:
-
The walls in the
2nd Floor lounge have been painted and the
ceiling tiles have been installed.
-
The flooring
contractor installed carpet in the 3rd Floor
lounge.
-
Workers started
installing ceiling grid in the 1st Floor
lounge.
-
The mechanical
contractor installed new fan coil units in Rooms
345 and 345A.
-
The electrical
sub-contractor continued wiring fan coil units
on the 3rd Floor.
-
Misc.:
-
The State Elevator
Inspector cleared the final items on
Elevators 1, 2 and 3 and certified them for
normal use.
-
The flooring
contractor installed carpet in offices on
the 2nd Floor.
-
The furniture
vendor installed desks and file cabinets in
Room 111.
-
The network wiring
contractor installed new drops in Rooms 111
and 111A.
-
LSUHSC-Facility
Services personnel installed door locks on
Rooms 111 and 111A.
-
The ceiling grid
contractor completed repairs to the 3rd
Floor hallway ceiling.
-
The cleaning
contractor has been cleaning offices along
the center hallway on the 3rd Floor and has
begun in the offices along the front
hallway.
-
The roll-up door
contractor completed the punch list items
and made final adjustments to the parking
garage roll-up door.
-
The access control
contractor installed door contacts and panic
bars on the emergency exit doors on the
Charity side of 1st Floor hallway.
-
New locks and
hardware have been installed by LSUHSC
Facility Services personnel on the doors to
Rooms 110, 111 and 111A.
LIONS/LSU CLINIC PERMANENT
REPAIRS AND MITIGATION:
-
The contractor
finished installing wall covering in the
computer lounge.
-
Workers installed
cove base in the new mechanical rooms on the
2nd Floor.
-
Workers installed
sprinkler heads in the 6th Floor computer
lounge.
-
Window blinds have
been hung in windows on the 6th Floor.
-
Crews installed
tile floor on the Bolivar St. side of the
1st Floor.
-
Painters primed
the CMU walls of the mechanical rooms,
electrical rooms, and stairwells on the 1st
Floor.
-
Workers installed
the remaining exterior glass in the
stairwell.
-
Granite pavers
have been laid around the new stairwell.
The pavers have been grouted.
-
Workers
framed, insulated and sheet rocked the
interior walls of the new stairwell on
the 3rd through the 6th levels.
-
Workers
waterproofed the granite wall panels on
the new stairwell.
-
The contractor
began installing trim for the windows of
the stair tower at the 6th level.
-
Workers applied
joint compound on the new wall on the 5th
Floor by the new stairwell.
-
They painted the
1st Floor walls on the S. Prieur Street side
of the building and painted the mechanical
room on the 1st Floor, Bolivar Street side.
-
Workers patched
the 1st Floor in preparation for the epoxy
installation.
-
Crews installed
wall and floor tile on the Bolivar St. side
of the 1st Floor.
-
Workers sealed the
original penetrations in the 6th Floor
computer lounge.
-
The electrical
contractor installed lights on the Gravier St.
side of the 6th Floor.
-
Electricians
installed lights and receptacles on the
Bolivar St. side of the 1st Floor and
cleaned light fixtures on the 1st floor.
-
They installed
lights in the 1st Floor restrooms and
receptacles on the Prieur St. side of the
1st Floor.
-
The fire alarm
devices on the 6th Floor were trimmed out
and tested.
-
Conduit was run
from the 6th Floor to the 2nd Floor demark
(telephone) room for the 200 pair cable.
-
Conduit was run
for the sump pump in the freight elevator.
-
The contractor ran
conduit from the controller to the motor for
the fire pump.
-
They ran wire from
the controller to the motor for the fire
pump.
-
They rewired the
tamper proof switches for the fire pump
controller.
-
Crews removed the
tombstones in the simulation room on the 6th
Floor.
-
The electrical
contractor installed a junction box for the
new fiber cables on the 6th Floor, Bolivar
Street side.
-
Electricians wired
the firemans switch for the exhaust fans in
the new stairwell and installed door closure
on the 6thFloor, Gravier Street side.
-
The mechanical
contractor installed a sink in the 6th Floor
break room.
-
Stryker continued to
install wires and equipment on the 6th Floor.
-
AT&T continues to
install the new telephone feeder.
LIBRARY COMMONS PROJECT:
-
The contractor
finished installing the fire dampers and smoke
detectors in the Commons area.
-
The contractor
finished installing the restroom partitions.
-
Ceiling trim was
installed above the coffee kiosk.
-
LSUHSC electricians
installed light fixtures near the decorative
screens and installed the faceplates for the
network drops.
-
The contractor hung
wallpaper beneath the windows.
-
They tested the
roll-up doors in manual mode.
-
LSUHSC Facility
Services personnel pulled wiring for the fire
phone.
-
The contractor
installed sprinkler caps throughout the space.
-
The contractor started
the general cleaning of the construction areas.
-
The ceiling in the
elevator lobby was repaired.
-
LSUHSC electricians
trimmed out the electrical receptacles.
-
LSUHSC electricians
relocated light fixtures above the magazine
racks.
MEB PHARMACOLOGY LAB
RENOVATIONS:
-
The casework
contractor installed countertops in Rooms 5219,
5219A and 5262.
-
The new door frame was
installed in Room 5219. .
-
The contractor hooked
up plumbing underneath the casework in Room
5219.
-
VCT was installed in
the administrative area.
-
The casework
contractor installed the second side of the
peninsula casework in Room 5219.
-
Workers installed
casework and countertops in Rooms 512A and 5124.
-
They hung shelves in
Room 5124 and installed sinks in Rooms 5219A,
5262.
-
The final coat of
paint was applied to Rooms 5262B, 5264, 5262A,
and 5206C.
-
The remaining sinks
were installed in both the lab area and
administrative areas.
-
The plumbing
contractor completed plumbing in the fume hoods
in both sections and started hooking up the
sinks in the administrative area.
-
The casework
contractor installed countertops on the second
side of the peninsula casework in Room 5219.
-
The contractor applied
the final coat of paint in the department head’s
office.
-
The casework
contractor completed touch up work to the
casework in the administrative and lab areas.
-
The contractor
installed receptacle raceways above the
laboratory furniture.
-
Workers connected
drains to the sinks in the laboratory furniture.
MEB 2nd FLOOR LOBBY
RENOVATIONS:
-
The contractor
installed the new storefront frames at the
Medical Center Stores location.
-
The contractor
installed the fur down across from the elevators
and removed the loose wire in the open ceiling
areas.
-
The contractor taped
and floated the fur down across from the
elevators.
-
The wall panel
contractor installed wall panels along the
Medical Center Stores wall.
-
The contractor began
installing new metal around the elevators.
MDL-3 RENOVATIONS:
-
A new contract has
been issued to renovate Multi-Disciplinary Lab 3
in the MEB.
-
The renovations
will replicate the renovations that have
recently been completed in MDL 6 including a
completely new layout, new casework, new
countertops, new flooring, etc. The
audio/visual equipment will be replaced with
state of the art equipment.
-
The contractor began
work by demolishing the existing casework,
removing acid waste lines, and disconnecting the
old plumbing.
-
The contractor
demolished ceiling grids and tiles, removed
light fixtures, and disconnected receptacle
outlets.
-
The A/V contractor
de-installed the old LCD and speakers in the
main MDL lab area.
-
The contractor removed
the existing partitions from the main MDL room
and removed the casework and ceiling from Room
4108A.
-
The contractor
completed demolition in the MDL.
-
The abatement
contractor began preparation for abatement over
the weekend.
DENTAL AUDITORIUMS A & B
RENOVATIONS:
-
The electrical
contractor installed conduit in the elevator
lobby outside Auditoriums A & B for the A/V
wiring and connections.
-
Creative Presentations
installed speaker wiring and structural supports
for the projector mounts in Auditorium B.
-
The electrical
contractor installed junction boxes for conduit
in the crosswalk (the conduit stretches between
the Auditoriums and the rack room; Room 4202B).
-
The A/V contractor
installed speakers and wiring in Auditorium A.
-
The electrical
contractor installed additional conduit and
junction boxes in the crosswalk outside Room
4202.
RESIDENCE HALL LOBBY
EXPANSION:
-
The interior
contractor taped and floated the fur down in the
expanded lobby area.
-
The interior
contractor completed installing ceiling tiles in
the A and C Towers and in the area between the A
& B Towers.
-
The electrical
contractor ran fire alarm wires in the expanded
lobby area.
-
The interior
contractor began framing the sheetrock ceiling
in the expanded lobby area.
-
The interior
contractor hung ceiling wires in the expanded
lobby area.
-
They prepared the
concrete wall to in-set the wall-mounted fire
alarm devices.
-
The contractor
installed ceiling grid for the sheetrock ceiling
underneath the mezzanine level of the A & B
Towers and in the expanded lobby area.
-
They installed ceiling
grid for the acoustical ceiling between the B &
C Towers.
ALLIED HEALTH/NURSING ROOF
REPLACEMENT:
-
The contractor removed
a 30 ft. by 30 ft. section of the roof at the
corner of Roman St. and Gravier St.
-
The contractor removed
another 30 ft. by 30 ft. section of the roof at
the corner of the MEB loading dock and Roman
Street.
-
The contractor
installed tapered insulation and a cap on a 40
foot section of the roof parallel to Perdido
Street.
-
The contractor removed
the old flashing from around the roof.
-
The contractor
installed insulation and a cap on a 40-foot
section of the roof parallel to Perdido Street.
-
The contractor
installed insulation and a cap forty feet beyond
the elevator penthouse toward South Roman
Street.
EXTERIOR/LANDSCAPING:
-
LSUHSC Facility
Services installed irrigation piping and
sprinklers at the corner of S. Roman St. and
Perdido St.
-
They began grading the
planting beds at the corner of S. Roman St. and
Perdido St.
-
Facility Services
finished installing new sod at the corner of S.
Roman St. and Perdido St.
-
We encourage you to
follow the details of our progress through the
daily updates which are posted on the web site.
|