From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #92
Posted: May 8, 2009
We have recently learned that our
proposal for making permanent repairs to the
Clinical Education Building and elevating the
critical building systems into a raised addition has
been approved by all levels of FEMA. The additional
$10.7 million should be obligated within the next
few days. LSUHSC and the Office of Facility Planning
and Control have forwarded their comments regarding
the Construction Documents for this project to the
architects. When the comments have been incorporated
into the plans and specifications, bid documents
will be prepared and the bids can be advertised.
FEMA representatives recently met
with the downtown campus architects to discuss a few
minor issues that remained to be addressed in the
permanent repair and mitigation proposals for the
Allied Health/Nursing Bldg., the Student Residence
Hall and the Resource Center. FEMA has already
completed new drafts of these proposals. They will
incorporate the information gathered from the
architects into the proposals and they will be
submitted for formal review and approval. Based on
the new guidance received from the FEMA Decision
Team led by Charlie Axton, we anticipate that the
proposals will be received favorably and approved
promptly. The bid documents for these three
buildings are nearing completion.
The next significant move of
clinical faculty and staff into 1542 Tulane Ave. is
expected to occur late this month. The 3rd and 4th
Floors of the building will be re-occupied at that
time. Work continues on the 1st and 2nd Floors to
prepare them to be placed back into use later in
June. The Department of Auxiliary Enterprises,
Duplicating and Printing operations have already
been moved back into the spaces they occupied on the
1st Floor prior to the storm.
We expect to receive "constructive
occupancy" of the Cohn Learning Center on the 6th
Floor of the Lions/LSU Clinic Building late in May
or early June. This will allow the Health Sciences
Center to prepare the space for use in advance of
the start of the next academic year. The architects
are working closely with the contractor to develop
punch lists and monitor their progress on the work
that remains to be substantially completed on the
floor. The finishing work on the exterior stairwell
is progressing rapidly as the interior walls are
being dry-walled, taped and floated. The windows
have been installed and the mullions/trim pieces are
being applied to the window. The electrical
contractor remains busy completing the work related
to the elevation of the mechanical and electrical
equipment.
Punch list items are being worked in
the Library Commons and the project approaches
completion. The opening in the ceiling of the
elevator lobby was patched. Workers installed two
return air grilles and one access panel in the
elevator lobby. They relocated lights in the wooden
ceiling and installed the ceiling frame in the back
office area. The contractor painted the elevator
lobby ceiling, installed wall covering in the
elevator lobby, and installed fire sprinkler caps.
The fire alarm devices have been tested.
Renovation work is nearing
completion in the MEB Pharmacology lab area in the
MEB. Receptacle raceways, light fixtures and doors
have been installed in the laboratory area. Sheet
vinyl flooring was installed in the animal care
room. Floor tile has been installed throughout.
Ceiling tiles have been installed in the
administrative and lab areas and the network wiring
contractor is pulling network cable.
The contractor installed surface
mount light fixtures throughout the MEB 2nd Floor
lobby. The wall panel contractor installed wall
panels on the Campus Office Stores side of the
lobby. The glazing for the new windows in Campus
Office Stores and Medical Center Stores has been
installed. Crews continue to finish the interiors of
the two Stores.
The new double-doors for the Dental
School Auditoriums A and B have been installed. The
contractor completed ceiling tile installation in
Auditorium A, and started in Auditorium B. Carpet
was installed on the top two tiers of Auditorium A.
Sheetrock and floor tile were installed in Room
4202B and the sheetrock was taped and floated.
Electricians ran conduit for electrical services in
Room 4202B and they pulled wires for the electrical
transformers and panels in Auditorium B. The
contractor roughed-in chilled water piping for the
2nd Liebert unit.
At the Student Residence Hall, the
contractor completed installing ceiling grid for the
sheetrock ceiling underneath the mezzanine level of
the A & B & C Towers and in the expanded lobby area.
The slab was cored for new floor boxes to be
installed between the A & B Towers. The mechanical
contractor ran wires for pull stations and fire
alarm devices in the extended lobby area. Plenum
boxes were installed along the expanded storefront
windows. Crews installed sprinkler heads beneath the
mezzanine level between the A & B lobbies and the
sprinkler line underneath the mezzanine level was
raised. The sprinkler heads have been adjusted to
the center of the tiles in the drop ceiling. New
network closets in the expanded lobby area have been
framed up and dry walled.
The re-roofing of the Allied
Health/Nursing Building is well underway. The
contractor removed the remaining portions of the old
roof on the main building and installed the
temporary cap over those areas of the roof. This
phase of the work on the roof is complete. Workers
removed the old roof from the walkway roof and
installed insulation and the cap sheet. The roof
drains were cut on the walkway and the roofing
membrane has been attached to the metal roof. The
old roof materials were removed from the 4th Floor
lower level roofs and the new insulation and a cap
sheet were installed.
The project to replace the air
handlers in the MEB is well underway. The contractor
removed the old rooftop unit number one, installed
the new unit and patched the roof. Workers completed
connections to the existing ductwork, insulated the
piping, installed the control cabinet, made the
electrical connections and started the unit. The
balancing and testing was completed. The contractor
disconnected ductwork and piping leading to the
existing rooftop unit number two and removed it.
They installed the new rooftop unit number two and
began making connections to the existing ductwork,
making piping and electrical connections.
Here are highlights of work that has
been accomplished during the past two weeks.
Repair Work at 1542 Tulane Ave.:
- Painting:
- Crews finished painting the auditorium.
- The rear elevator lobby on the 2nd Floor
was painted.
- The walls in Room 312B were patched and
painted.
- Lounge Areas:
- The mechanical contractor installed
flexible duct and diffusers in the 1st and
2nd Floor lounges.
- Workers completed installing the ceiling
grid in the 1st Floor lounge.
- The electrical contractor installed
ceiling lights in the 1st Floor lounge.
- The sprinkler contractor installed
sprinkler heads in the 1st Floor lounge.
- The walls in the 1st Floor lounge are
being primed.
- The furniture vendor installed furniture
in the 3rd Floor lounge.
- Misc.:
- Duplicating and Printing was relocated
from their temporary location in the
Residence Hall to Rooms 110, 111 and 111A.
- The light fixtures have been installed
in Rooms 341, 342 and 343.
- Carpeting and cove base was installed in
Rooms 341, 342 and 343.
- The furniture vendor installed furniture
in the 3rd Floor conference room, and in all
offices on the 3rd Floor.
- The general contractor started cleaning
the auditorium floor.
LIONS/LSU CLINIC PERMANENT REPAIRS
AND MITIGATION:
- The contractor installed new sprinkler lines
in the landscaping at the front of the building;
replacing lines that were removed during the
excavation for the new exterior stairwell.
- The contractor installed plants in the
new landscaping area.
- They completed the extension of the
metal platform on the roof for the
electrical panel.
- Workers installed carpet on the Gravier
St. side of the 6th Floor.
- The contractor installed floor tile in
the 1st Floor restroom.
- Workers installed ceiling grid on the
CSRB/S. Prieur St. side of the 1st Floor.
- Ceiling tile is being installed on the
1st Floor, CSRB/S. Prieur Street side.
- They repaired the wall by the switchgear
room following the installation of new fire
pump breaker.
- Crews installed restroom partitions and
ceiling grid in the restrooms on the Bolivar
St. side of the 1st Floor.
- Crews applied the 2nd coat of epoxy in
the mechanical and electrical rooms on the
1st Floor, Bolivar Street side.
- The final coat of epoxy was applied to
the floors in the old PBX room, the
mechanical room, the electrical room, the
control room and the stairwell on the 1st
Floor.
- They plastered the new wall in the old
PBX room on the 1st Floor.
- Workers installed wall tile on the
Bolivar St. side of the 1st Floor.
- Crews grouted the 1st floor
marble wall tile and the 1st
Floor restrooms wall tile.
- The contractor installed floor tile on
the 6th Floor in the computer lounge for the
new floor boxes.
- Workers completed waxing the 1st Floor
lobby floor.
- External Stairwell:
- Workers continued to waterproof the
granite wall panels on the new stairwell.
- Workers installed trim for the windows
of the stair tower at the 2nd, 3rd, 4th and
5th levels.
- Crews framed up the shaft walls of the
stairwell at the 1st, 2nd and 3rd levels.
- The new shaft walls on the 3rd through
the 6th levels have been taped and floated.
- Crews applied a second coat of mud on
stairwell shaft walls on the 3rd through the
6th levels.
- The stairwell handrails on the 1st
through the 6th levels of the exterior
stairwell were painted.
- A French drain was installed around the
new stairwell slab.
- A crew continues to install metal for
the mullions in the stairwell.
- The electrical contractor began terminating
the new fiber cables in the 6th Floor network
closet.
- Electricians installed breakers for the
elevator sump pumps.
- They ran wire for the sump pumps in the
elevator pits.
- Door closures were installed on the
Bolivar St. side of the 6th Floor.
- The contractor installed light fixtures
on the 1st Floor, CSRB and Bolivar Street
side of the building.
- They roughed in an exit light on the
Bolivar St./Gravier St. side of the 1st
Floor.
- They secured the fire pump controller to
the wall and wired flow switches and valves
in the fire pump room on the 2nd Floor.
- The new breakers for the fire pump motor
on the roof and on the 2nd Floor were
installed.
- The electricians installed a 600 amp
breaker for EMDP panel and the 1600 amp
breaker for the fire pump motor on the roof.
- The electrical contractor installed wire
for the 1600 amp breaker for the fire pump
motor on the roof and began piping in the
1600 amp breaker on the 2nd
Floor.
- They installed smoke detectors and
strobes on the Bolivar St. side of the 1st
Floor.
LIBRARY COMMONS PROJECT:
- The contractor patched the opening in the
ceiling of the elevator lobby.
- They installed an access panel in the
elevator lobby and installed a temporary panic
bar at the fire door.
- Workers installed two return air grilles and
one access panel in the elevator lobby.
- They relocated lights in the wooden ceiling
and installed the ceiling frame in the back
office area.
- The contractor painted the elevator lobby
ceiling, installed wall covering in the elevator
lobby, and installed fire sprinkler caps.
- The fire alarm devices have been tested.
- Crews patched the sheetrock underneath the
stairwell.
MEB PHARMACOLOGY LAB RENOVATIONS:
- The contractor installed receptacle raceways
and light fixtures in the laboratory area.
- The doors in the laboratory area have been
installed.
- Sheet vinyl flooring was installed in the
animal care room.
- Ceiling tiles have been installed in the
administrative and lab areas.
- The network wiring contractor started
pulling network wires.
- Return air grilles have been installed in
the new doors.
- They completed the installation of the floor
tile.
MEB 2nd FLOOR LOBBY RENOVATIONS:
- The contractor installed surface mount light
fixtures throughout the lobby.
- They taped and floated the walls around the
new doors across from the elevators.
- The wall panel contractor installed wall
panels on the Campus Office Stores side of the
lobby.
- The contractor installed glazing for the new
windows in Campus Office Stores and Medical
Center Stores.
- Crews continue to finish the interiors of
the two Stores.
- The wall panel contractor installed metal
trim pieces for the wood wall panels adjacent to
the elevators.
MDL-3 RENOVATIONS:
- The contractor abated the floor in the MDL.
- Workers raised the support beam for the
partition.
- The electrical contractor installed MC whips
for light fixtures.
DENTAL AUDITORIUMS A & B
RENOVATIONS:
- The contractor installed sheetrock and floor
tile in Room 4202B.
- They taped and floated the new sheetrock in
Room 4202B.
- The new double-doors for Auditoriums A and B
were installed.
- Electricians ran conduit for electrical
services in Room 4202B.
- The contractor installed the transformers
and sub-panels for the electrical services in
the auditoriums.
- They pulled wires for the electrical
transformers and panels in Auditorium B.
- The contractor completed ceiling tile
installation in Auditorium A, and started in
Auditorium B.
- The contractor painted the 1st coat of paint
in Room 4202B.
- Carpet was installed on the top two tiers of
Auditorium A.
- The contractor roughed-in chilled water
piping for the 2nd Liebert unit in Room 4202B.
RESIDENCE HALL LOBBY EXPANSION:
- The contractor completed installing ceiling
grid for the sheetrock ceiling underneath the
mezzanine level of the A & B Towers and in the
expanded lobby area.
- Workers completed installing ceiling grid
for the acoustical ceiling between the B & C
Towers.
- The contractor cored holes for floor boxes
between the A & B Towers.
- Workers installed break metal along the fur
down of the extended storefront.
- The mechanical contractor ran wires for pull
stations and fire alarm devices in the extended
lobby area.
- Plenum boxes were installed along the
expanded storefront windows.
- The interior contractor patched the wall
where the fire alarm devices were installed in
the lobby.
- Crews installed sprinkler heads beneath the
mezzanine level between the A & B lobbies.
- They framed the network closets in the
expanded lobby area and gypsum board was hung.
- Gypsum board was installed to fur out the
concrete wall in the back corner lobby area
along S. Roman St. and Poydras Ave.
- The mechanical contractor raised one
sprinkler line underneath the mezzanine level
between the B & C Towers.
- They adjusted sprinkler heads to the center
tile of the drop ceiling.
- The interior contractor began taping and
floating the wall in the back corner lobby area
on S. Roman St. and Poydras Ave.
ALLIED HEALTH/NURSING ROOF
REPLACEMENT:
- The contractor removed the remaining
portions of the old roof and installed the
temporary cap over those areas of the roof.
- This phase of the work is complete on
the roof of the building.
- The contractor removed the old roof from the
walkway roof and installed insulation and the
cap sheet.
- They tarred around the edge of the walkway
between the MEB and the Allied Health/Nursing
Building.
- The contractor cut the roof drains on the
walkway.
- They attached the roofing membrane to the
metal roof.
- Workers removed the old roof materials,
installed new insulation and a cap sheet for the
4th Floor lower level roofs.
- They installed a cap sheet on the roof of
the walkway between the Allied Health/Nursing
Bldg. and the MEB and on the 4th Floor lower
level roofs.
MEB AIR HANDLING UNIT REPLACEMENT:
- The contractor removed the old rooftop unit
number one, installed the new unit and patched
the roof.
- The new air handling unit was piped in.
- Workers completed connections to the
existing ductwork, insulated the piping,
installed the control cabinet, made the
electrical connections and started the unit.
- The balancing and testing has begun.
- The contractor disconnected ductwork and
piping leading to the existing rooftop unit
number two and made preparations to install the
new unit.
- Workers disconnected and removed the old
rooftop unit number two.
- They installed the new rooftop unit
number two and began making connections to
the existing ductwork, making piping and
electrical connections.
- The roof around the new unit was
repaired.
EXTERIOR/LANDSCAPING:
- Facility Services planted Algerian Ivy under
the rear corner of the Resource Center.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|