From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #97
Posted: July 17, 2009
We have recently learned
that the permanent repair and hazard mitigation
proposals for the Allied Health/Nursing Building,
the Student Residence Hall and the Resource Center
have cleared the $ Million Queue in Washington, DC.
Funds for all three proposals should be obligated at
any time. The Office of Facility Planning and
Control is working closely with the architects to
insure that they complete the bid packages for these
three buildings in the next few weeks. With the
Federal funding in place, the contracts can be
advertised and put out for bid as soon as the
documents are ready.
The contract for the
permanent repairs and mitigation at the Lions/LSU
Clinic Building is substantially complete. The State
Fire Marshall recently completed his review and
granted us permission to occupy the renovated areas
of the building contingent upon addressing some
minor deficiencies. Conduit and electrical cable
have been run for the MRI trailer. The flood gates
for the 1st Floor entrances to the elevators are
being installed.
The Library Commons
officially opened on July 15th. The cash register
and coffee maker have been installed at the coffee
station and the coffee station is in operation. The
restoration work has been completed on the frieze.
The cove base has been installed throughout. The
contractor completed the installation of the
stairwell handrail and installed carpet at the main
entry.
A new project has gotten
underway that will renovate existing laboratory
spaces used by Physiology on the 7th Floor of the
MEB; Rooms 7221, 7241, 7244, and 7250. The
contractor will replace the ceilings, light
fixtures, flooring, casework, countertops and fume
hoods.
The walk in cooler (Room
7207) will also be re-floored. The contractor has
begun the demolition of the old casework,
countertops, etc.
On Saturday, July 11th, we
began a new project to replace the old exhaust fans
on the roofs of the Dental School Clinic Building
and the Power Plant. A crane was set up in the
horseshoe to lift the fans onto the roof of the
Clinic Building. The project plan calls for pairs of
the old fans to be removed and immediately replaced
with new fans to minimize the impact to building
occupants. When all of the new fans are in place,
the crane will remove all of the old fans from the
building roofs. The schedule calls for the work to
be completed by July 25th.
The contractor responsible
for re-roofing the Resource Center is expected to be
on site early in the month of August. The first step
in the contract will be to erect and attach a
temporary elevator/materials lift to the exterior of
the building.
We continue to complete
the final preparations for re-occupying the 1st and
2nd Floors of the Clinical Education Building. The
2nd Floor door locks and closers were adjusted. The
2nd Floor offices, restrooms and stairwells have
been cleaned. Stained carpet tiles have been
replaced on both floors. Furniture is being
installed in 1st Floor offices. LSUHSC Facility
Services is applying touch-up paint in the 1st and
2nd Floor offices and they installed cover-plates
over the electrical floor boxes in the Auditorium.
The network installers installed wiring for wireless
services in the conference room on the 1st Floor.
The new coffee kiosk in the 1st Floor lounge along
the front of the building is due in the next week or
two.
The contractor removed the
existing fire alarm devices from the renovated MEB
2nd Floor lobby. The storefront doors have been
installed for the Campus Office and Medical Center
Stores locations. The meeting minder is being
installed and the final connections have been made
for the digital signage. We anticipate that the
inspection by the State Fire Marshall will be
scheduled shortly.
The renovations to MDL #3
are moving towards completion. The contractor
connected the drain lines for the cabinet sinks. The
remaining cantilever frame and countertops have been
installed and the network contractor ran network
wiring to the new casework. The A/V contractor
installed the 65 inch LCD screens and the control
boxes for the new audio/visual equipment.
Much of the work that
remains to be completed in the Dental School
Auditoriums A & B relate to the state of the art
audio/visual upgrades. Wiring for the video cameras
in Auditorium A has been pulled and the projector
screen is in place. The auto-stack camera for the
projectors in Auditorium A has been installed. The
cameras and projection screen has been installed in
Auditorium B. The contractor installed the document
camera inside the podium of both Auditoriums and
pulled wire for the touch screen panels in both
rooms. Workers pulled network cables for the tables
in Auditorium B and the network terminals have been
installed in both auditoriums.
The contractor finished
installing the wavy ceiling grid and tiles in the
expanded lobby area at the Residence Hall. The
sprinkler heads were adjusted to accommodate the new
ceiling design. Electricians began installing the
light fixtures below the wavy ceiling and roughed in
the light fixtures for the suspended ceiling in the
recreation room. Gypsum board was installed on the
ceiling in the recreation room and the walls in the
recreation room were taped and floated. The flooring
contractor installed porcelain bases between the A,
B & C Towers. The millwork contractor completed
installation of the wood cladding around the
mailboxes.
The roofing contractor
working on the Allied Health/Nursing Building is
completing the remaining work. Workers finished
installing the parapet wall cap around the perimeter
of the roof. They installed PVC piping to drain the
HVAC units on the penthouse. The flashing around the
exhaust fans for the elevator penthouse was
installed. Lightening protection rods were installed
on the Stairwell C penthouse. The contractor
installed aluminum flashing around the parapet wall
on the Atrium.
The contractor completed
the installation of piping, insulation, electrical
and controls for MEB air handling unit 6C. Facility
Services shifted the temporary AC units from the C
quadrant on the 6th and 7th Floors to the B quadrant
(corner of Perdido Street and South Roman Street).
The contractor demolished and removed the old air
handling units 6B and 7B and installed the new AHUs.
Crews continue installing the new ductwork for AHU
6B and 7B. New air handling units 5-D and 4-D were
delivered to the T-lot lay down area.
Here are highlights of
work that has been accomplished during the past two
weeks.
DENTAL SCHOOL EXHAUST FAN
REPLACEMENT: A new project to replace the old
exhaust fans on the Clinic Building and the Power
Plant began on Saturday, July 11th. A crane was set
up in the horseshoe to lift the fans onto the roof
of the Clinic Building.
- As each fan is replaced, the fume hoods
affected will be out of service. It is important
that lab occupants take the necessary
precautions with any chemicals since there will
be no exhaust in the affected rooms during this
work. The entire schedule is as follows:
- July 13th: 8:00 AM thru 4:30 PM. Fans
F13 and F14 will be replaced; affecting fume
hoods in 7315 and 6313.
- July 14th: 8:00 AM thru 4:30 PM. Fans
F17 and F18 will be replaced; affecting fume
hoods in 6329 and 6335.
- July 15th: 8:00 AM thru 4:30 PM. Fans
F20 and F22 will be replaced; affecting fume
hoods in 7339 and 7333.
- July 16th: 8:00 AM thru 4:30 PM. Fans
F62 and F39 will be replaced; affecting fume
hoods in 7325 and 7323.
- July 17th: 8:00 AM thru 4:30 PM. Power
House ventilator will be replaced; affecting
the Power House.
- July 20th: 8:00 AM thru 4:30 PM.
Restrooms exhaust fans on 3rd Floor of the
Clinic Building will be replaced.
- July 25th: 8:00 AM thru 2:00 PM. The
crane will be in the horseshoe to remove old
fans from roof.
MEB 7th FLOOR PHYSIOLOGY
LAB RENOVATIONS: This is a new project that will
renovate existing laboratory spaces; Rooms 7221,
7241, 7244, and 7250. The walk in cooler (Room 7207)
will also be re-floored. The contractor will replace
the ceilings, light fixtures, flooring, casework,
countertops and fume hoods.
- The contractor began the demolition work in
Rooms 7221, 7241, 7244 and 7250.
Repair Work at 1542 Tulane
Ave.:
- Facility Services custodial staff vacuumed
the rooms along the main corridor on the 2nd
Floor.
- Facility Services is applying touch-up paint
in the 1st and 2nd Floor offices.
- The contractor completed cleaning all 2nd
Floor offices, restrooms and stairwells.
- The furniture contractor installed furniture
in the 1st Floor offices.
- The flooring contractor installed carpet
squares near Room 235L.
- Facility Services installed cover-plates
over the electrical floor boxes in the
Auditorium.
- The network installers installed wiring for
wireless services in the conference room on the
1st Floor.
- Facility Services adjusted locks and closers
for the offices on the 2nd Floor.
- The flooring contractor installed cove base
in the stairwells and replaced stained carpet
tiles on the 1st and 2nd Floors.
LIONS/LSU CLINIC PERMANENT
REPAIRS AND MITIGATION:
- The contractor pulled network wires for the
conference room along Bolivar Street and in the
large lecture hall.
- The contractor pulled data wire for the
classrooms on the S. Prieur St. side of the 6th
Floor.
- Crews pulled electrical cables for the MRI
trailer feed on the 1st Floor.
- Conduit was run to the MRI trailer
location.
- They drilled the holes for the flood gates
in the 1st Floor elevator lobby.
- The contractor finished installing the
flood gates for Elevators 2 and 3.
- Workers installed breakers for the
conference room tables on the 6th Floor.
- The Fire Marshal inspected the project and
granted occupancy contingent on the correction
of some minor deficiencies.
LIBRARY COMMONS PROJECT:
- The contractor installed wallpaper on the
center wall of the stairwell.
- The installation of the cove base is
finished.
- The contractor completed the installation of
the stairwell handrail and installed carpet at
the main entry.
- LSUHSC installed the cash register and
coffee maker.
- Facility Services cleaned the Commons in
preparation for opening.
- The Commons area opened on Wednesday, July
15th.
MEB 2nd FLOOR LOBBY
RENOVATIONS:
- The contractor removed existing fire alarm
devices.
- The contractor installed the storefront
doors at the Campus Office and Medical Center
Stores locations.
- The AV Contractor began installing the
meeting minder.
- IT made the final connections for the
digital signage.
MDL #3 RENOVATIONS:
- The contractor connected drain lines for the
cabinet sinks.
- The casework contractor completed installing
the remaining cantilever frame and countertops.
- The network contractor ran network wiring to
the new casework.
- The A/V contractor installed the 65 inch LCD
screens.
- They installed control boxes for the
audio/visual equipment.
- The network contractor terminated end
connectors for network cables in the new
casework.
DENTAL AUDITORIUMS A & B
RENOVATIONS:
- The A/V contractor pulled wiring for the
video cameras in Auditorium A and installed the
projector screen.
- They set the podium in Auditorium B and
pulled fiber from the rack room to both
auditoriums.
- Workers installed the auto-stack camera
for the projectors in Auditorium A.
- The contractor installed speaker grilles
in Auditoriums A and B and wired the
components in Auditorium B.
- The cameras and projection screen has
been installed in Auditorium B.
- The A/V contractor installed the
document camera inside the podium of
Auditoriums A and B.
- The general contractor continued pulling
wires and touched up paint in Auditorium A.
- The electrical installed electrical outlets
for the podiums.
- Workers pulled network cables for the
tables in Auditorium B.
- The contractor installed network
terminals in both auditoriums.
- The contractor also connected wiring for the
touch-screen panels at the podium in both
auditoriums.
- The contractor installed the painted
return-air grilles above the mechanical and
electrical rooms.
RESIDENCE HALL LOBBY
EXPANSION:
- The contractor finished installing the wavy
ceiling grid in the expanded lobby area.
- Crews installed the wavy ceiling tile in
the grid.
- The contractor adjusted the sprinkler
heads in the special ceiling system.
- Electricians began installing the light
fixtures below the wavy ceiling.
- Crews roughed in the light fixtures for
the suspended ceiling in the recreation
room.
- Gypsum board was installed on the ceiling in
the recreation room.
- Workers taped and floated the new walls in
the recreation room.
- The contractor taped and floated walls in
the corner lobby area of the C Tower.
- The flooring contractor installed porcelain
bases between the A, B & C Towers.
- The contractor trimmed out the electrical
floor boxes at both ends of the lobby.
- The contractor sanded the new walls and
ceiling in the recreation room.
- The millwork contractor completed
installation of the wood cladding around the
mailboxes.
ALLIED HEALTH/NURSING ROOF
REPLACEMENT:
- The contractor finished installing the
parapet wall cap around the perimeter of the
roof.
- The roofers installed PVC piping to drain
the HVAC units on the penthouse.
- The contractor installed flashing around the
exhaust fans for the elevator penthouse.
- Lighting protection rods were installed on
the Stairwell C penthouse.
- The contractor installed aluminum flashing
around the parapet wall on the Atrium.
MEB AIR HANDLING UNIT
REPLACEMENT:
- The contractor completed the installation of
piping, insulation, electrical and controls for
AHU 6C.
- Facility Services shifted the temporary AC
units from the C quadrant on the 6th and 7th
Floors to the B quadrant (corner of Perdido
Street and South Roman Street).
- The contractor demolished and removed the
old air handling units 6B and 7B.
- They installed the new air handling units;
6B and 7B.
- Crews continue installing new ductwork for
air handling units 6B and 7B.
- New air handling units 5-D and 4-D were
delivered to the T-lot lay down area.
EXTERIOR/LANDSCAPING:
- Facility Services installed sprinkler
station #1 on the Tulane Ave. side of the Roman
St. Garage.
- Facility Services replanted the beds in
front of the Allied Health/Nursing Building
following the repair of a leaking water line on
Saturday, July 11.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|