From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #101
Posted: September 11, 2009
The next three permanent repair and
hazard mitigation projects for major campus
buildings are being let out for bid by the Office of
Facility Planning and Control. The Allied
Health/Nursing Bldg. project is being advertised
today and the bids are scheduled to be received on
October 7th. The advertisements for the Student
Residence Hall will be published on September 16th
and bids will be opened on October 14th. The
Resource Center project will be advertised on
September 23rd and the bids will be opened on
October 21st. The process of evaluating the bids
received for each project, awarding the work, and
getting the contract documents prepared and executed
takes time, but we are hopeful that all the
contracts will be in place before the end of the
calendar year.
Work on the expansion and renovation of the
Residence Hall lobby is substantially complete. The
A/V contractor programmed the digital signage
display in the expanded lobby area. The contractor
installed the wall covering behind the security desk
area and on the wall adjacent to the mailboxes. The
swing door for the security desk was installed and
the electrical outlet was trimmed out. The
contractor installed the stainless steel border
around the mailboxes. The pool table and the ping
pong table were delivered and set up in the
recreation room. Furniture was delivered and set up
throughout the 2nd Floor.
The contractor replacing the roof on the Resource
Center has made good progress on the initial phase
of the project. Thirty of the thirty-four roof
drains have been lowered and the temporary roofing
has been installed. They have been starting work
during the middle of the nights to reduce weather
delays and to minimize disruptions to the occupants
of the offices beneath the roof drains. However the
increased frequency of rain showers has caused some
delays.
The remaining work on the 1st Floor coffee kiosk at
the Clinical Education Building has been completed.
The contractor powered up the equipment
(refrigerators and ice machine) and made the final
connections for the coffee maker. LSUHSC Computer
Services installed and connected the cash register.
Painters touched-up the walls and door frames in the
coffee kiosk area.
The project to modify the entrances into 1542 Tulane
Ave. from the parking garage is progressing. The
contractor re-routed electrical conduit in the
garage at the 1st Floor ADA Ramp. Workers re-routed
conduit and wiring for the status switch on the exit
door in the garage. They erected a temporary wall at
the 1st floor garage/building entrance and removed
the metal door and frame. The sprinkler contractor
installed additional sprinkler heads at the 1st
Floor garage/building entrance.
Other miscellaneous tasks were also completed.
Workers contractor installed conduit for the fire
alarm panel enunciator in the basement and they
re-routed the fire alarm annunciator wiring and the
Cox cable wiring on the 1st level of the parking
garage. The floor tile was laid in Room 122F
(Women’s Restroom). The contractor installed door
locks for the pipe chase in the parking garage and
connected the gas line piping on the 1st level of
the parking garage. The plumbing contractor
re-routed and insulated the chilled water return
piping on the 1st level of the parking garage.
The remaining work in the Dental Clinic Auditoriums
is being completed. The A/V contractor adjusted the
projectors and screen image in Auditorium B. They
tested the fiber, programmed the podium monitors
made programming adjustments to the A/V and podium
equipment in Auditorium B. The microphones for the
podium were installed and the volume settings were
adjusted. The A/V contractor labeled and tested the
A/V communication cables in Room 4202B that
communicate with components in Auditorium B.
The network wiring crew pulled, connected,
configured and tested the network wires for the
wireless access connections in Auditoriums A and B.
The contractor adjusted the acoustical wall panels
in both Auditoriums A and B.
The MEB Air Handling Unit project continues on
schedule. Crews completed insulating the hot water
piping for AHU 4-D. The contractor installed the
electrical and controls for both AHUs. Workers are
testing and balancing air handling units 4-D and
5-D. Facility Services relocated the temporary A/C
units from the 4th and 5th Floor Quadrant D to the
4th and 5th Floor Quadrant C (corner of Bolivar
Street and MEB loading dock). They started the
temporary A/C units and began monitoring their
performance. The contractor closed Bolivar Street,
set-up their crane and started preparations for the
start of the demolition of AHU 4-C and 5-C.
Renovations to the Physiology labs on the 7th Floor
of the MEB are proceeding. The contractor completed
installing the ceiling grid and the new light
fixtures in Rooms 7221 and 7244. Sprinkler heads
were relocated in Rooms 7221, 7241, 7244, and 7250.
The contractor installed new lab furniture
(casework) in Rooms 7221, 7241, 7244 and 7250. The
HVAC supply grilles were installed in Rooms 7221 and
7241 and the receptacle outlets in Rooms 7241 & 7250
were trimmed out.
Here are highlights of work that has been
accomplished during the past two weeks.
ALLIED HEALTH/NURSING PERMANENT REPAIRS AND
MITIGATION:
- Bids will be advertised on 9/11/2009
- The Pre-Bid Conference will be held on 9/28/2009
in the Chancellor’s Conference Room.
- Bids will be opened on 10/7/2009.
STUDENT RESIDENCE HALL PERMANENT REPAIRS AND
MITIGATION:
- Bids will be advertised on 9/16/2009
- The Pre-Bid Conference will be held on 10/1/2009
in the Chancellor’s Conference Room.
- Bids will be opened on 10/14/2009.
RESOURCE CENTER PERMANENT REPAIRS AND MITIGATION:
- Bids will be advertised on 9/23/2009
- The Pre-Bid Conference will be held on 10/8/2009
in the Chancellor’s Conference Room.
- Bids will be opened on 10/21/2009.
RESOURCE CENTER ROOF REPLACEMENT:
- The contractor lowered five roof drains and
applied the two ply temporary roof system on the
South Prieur Street and Tulane Avenue corner of the
roof.
- The contractor lowered five additional roof drains
and applied the two-ply temporary roof system on the
Tulane Avenue Side of the building.
- They have completed work on 17 of 34 roof drains.
- The contractor lowered seven roof drains and
applied the two-ply temporary roof system on the Gravier Street side of the building.
- They have now completed 24 of 34 roof drains.
- The contractor lowered six roof drains and applied
the two-ply temporary roof system on the corner of
S. Prieur Street and Gravier Street of the building.
- They have now completed 30 of the 34 roof drains.
- The contractor removed the existing roof and
applied the two-ply temporary roof system along
Bolivar Street.
REPAIR WORK AT 1542 TULANE AVE.:
- The contractor powered up the equipment
(refrigerators and ice machine) for the coffee
kiosk.
- Painters touched-up the walls and door frames in
the coffee kiosk area.
- The plumbing contractor installed the final
connections of the coffee maker for the 1st Floor
kiosk.
- IT installed the cash register for the kiosk.
- The contractor re-routed electrical conduit in the
garage at the 1st Floor ADA Ramp.
- Workers re-routed conduit and wiring for the
status switch on the exit door in the garage.
- They erected a temporary wall at the 1st floor
garage/building entrance.
- The metal door and frame at the 1st Floor
garage/building entrance was removed.
- The contractor removed the remediation containment
barriers for the 2nd Floor Garage corridor
build-out.
- The sprinkler contractor installed additional
sprinkler heads at the 1st Floor garage/building
entrance.
- Workers contractor installed conduit for the fire
alarm panel enunciator in the basement.
- They re-routed the fire alarm annunciator wiring
and the Cox cable wiring on the 1st level of the
parking garage.
- Workers laid floor tile in Room 122F (Women’s
Restroom).
- The contractor installed door locks for the pipe
chase in the parking garage.
- The contractor connected the gas line piping on
the 1st level of the parking garage.
- The plumbing contractor re-routed the chilled
water return piping on the 1st level of the parking
garage.
- The contractor insulated the chilled water return
piping in the parking garage.
DENTAL AUDITORIUMS A & B RENOVATIONS:
- The A/V contractor adjusted the projectors and
screen image in Auditorium B.
- They tested the fiber and programmed the podium
monitors in Auditorium B.
- The A/V contractor is made programming adjustments
to the A/V and podium equipment in Auditorium B.
- The A/V contractor installed the microphones for
the podium in Auditorium B and adjusted the volume
settings.
- The A/V contractor labeled and tested the A/V
communication cables in Room 4202B that communicate
with components in Auditorium B.
- The network wiring crew pulled network wires for
the wireless access connections in Auditoriums A and
B.
- They tested network wires for the wireless access
connections in Auditoriums A and B.
- The contractor adjusted acoustical wall panels in
Auditoriums A and B.
- IT configured and tested wireless access in
Auditoriums A and B.
MEB AIR HANDLING UNIT REPLACEMENT:
- Crews completed insulating the hot water piping
for AHU 4-D.
- The contractor installed the electrical and
controls for both AHUs.
- They worked on punch list items in mechanical
rooms 6-A, 6-B, 6-C, 6-D, 7-A, 7-B, 7-C, and 7-D.
- The contractor is testing and balancing air
handling units 4-D and 5-D.
- Facility Services relocated the temporary A/C
units from the 4th and 5th Floor Quadrant D to the
4th and 5th Floor Quadrant C (corner of Bolivar
Street and MEB loading dock).
- They started the temporary A/C and began
monitoring.
- The contractor closed Bolivar Street, set-up their
crane and started preparations for the 6:00 PM
demolition start on AHU 4-C and 5-C.
MEB 7th FLOOR PHYSIOLOGY LAB RENOVATIONS:
- The contractor completed installing the ceiling
grid in Rooms 7221 and 7244.
- They installed the new ceiling light fixtures in
Rooms 7221 and 7244.
- Sprinkler heads were relocated in Rooms 7221,
7241, 7244, and 7250.
- The contractor installed new lab furniture
(casework) in Rooms 7221, 7241, 7244 and 7250.
- The contractor installed HVAC supply grilles in
Rooms 7221 and 7241.
- Crews trimmed out receptacle outlets in Rooms 7241
& 7250.
RESIDENCE HALL LOBBY EXPANSION:
- The A/V contractor programmed the digital signage
display in the expanded lobby area.
- The contractor installed the wall covering behind
the security desk area and on the wall adjacent to
the mailboxes.
- The swing door for the security desk was
installed.
- They trimmed out the electrical outlet for the
security desk.
- The contractor installed the stainless steel
border around the mailboxes.
- The pool table and the ping pong table were
delivered and set up in the recreation room.
- Furniture was delivered and set up throughout the
2nd Floor.
CITY PARK CAMPUS:
- The contractor replaced the window in the
breezeway between the Dental Clinic and
Administration Buildings that was damaged by
Hurricane Gustav.
LIONS/LSU CLINIC BLDG.:
- The contractor replaced half of the carpet on the
3rd Floor in Rooms 329A, 336 and 336B.
LANDSCAPING:
- Facility Services finished the final grading of
the planting beds on the Gravier Street side of the
Roman Street Garage.
- They demolished and removed the asphalt around the
perimeter of the T-lot in preparation for the new
landscaping.
- Workers laid sod and planted trees beside the
Roman Garage along Gravier Street.
- Shrubs were planted beside the Central Utility
Plant along Gravier Street.
- Crews spread mulch in the planting beds in front
of the Roman Street Garage on the Tulane Avenue
side.
ALLIED HEALTH/NURSING ROOF REPLACEMENT:
- The contractor continued to repair the metal
panels of the atrium roof.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|