From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #103
Posted: October 9, 2009
The bids for the permanent
repairs and hazard mitigation project at the Allied
Health/Nursing Building were opened on October 7th.
The bid also included an alternate to construct a
new large lecture hall on the 2nd Floor; relocating
displaced offices to the 1st Floor. The architects
evaluated the bids and have recommended that the
contract be awarded to the low responsive bidder.
The contact award process now moved into the hands
of Facility Planning and Control. Pre-bid
conferences for the permanent repair and mitigation
projects at the Residence Hall and Resource Center
have been held. The bids are scheduled to be opened
for the Residence Hall on 10/14/09 and for the
Resource Center on 10/21/09.
FEMA recently prepared a
new hazard mitigation proposal for the CSRB addition
and presented the draft to GOHSEP and LSUHSC. Early
indications are that the proposal includes the major
elements that were proposed by LSUHSC and that FEMA
will support the project as eligible for funding.
GOHSEP and LSUHSC are completing their review of the
new proposal and hope to be able to sign off on it
early next week.
Renovations to the
Physiology labs located on the 7th Floor of the MEB
are nearing completion. The contractor installed
shelves in Rooms 7221, 7241, 7244 and 7250. Network
data cables have been terminated in the network
closet and in all of the rooms. The electrical
raceways were trimmed out in Rooms 7221, 7241, 7244,
and 7250. The receptacles and cover plates were
installed. Ceiling tile was installed in Rooms 7221,
7241, 7244, and 7250. Workers connected hot, cold,
DI water, and drain lines in the labs. The
contractor cleaned Rooms 7221, 7241, 7244, and 7250;
buffing and waxing the floors in all 4 rooms.
The contractor removed the
old roof from the Resource Center along Perdido
Street and S. Prieur St. and applied the two-ply
roof. They completed all the X-rays and successfully
cored the roof at all four corners. Crews placed
lightweight concrete on the main penthouse and
applied the two-ply roof. They placed lightweight
concrete on the Gravier Street Penthouse and on the
corner of Gravier and Bolivar Street. Tapered
insulation was laid and workers applied a two-ply
roofing system at all roof drains on the main
penthouse. Work on the replacement of the glazing
(glass) that forms the roof of the atrium is
expected to begin shortly.
The contractor roughed in
the electrical for the 2nd Floor entrance from the
1542 Tulane Ave. parking garage. Workers installed
sheetrock and the sprinkler heads for the entrance.
They pulled wiring for the power receptacles for the
2nd Flood corridor. The contractor taped and floated
the walls for the entrance corridor and in Rooms 242
and 202A. The walls in Room 242B were painted. The
contractor constructed the wood forms and installed
rebar for the 1st Floor ADA entrance. They poured
the concrete curbs and filled the slab penetrations
and poured concrete for the new ADA entrance ramp.
The air handling
replacement project at the MEB continues on
schedule. The contractor completed the control work
for AHU 4-C and 5-C. Facility Services set up the
temporary A/C units in the 4th and 5th Floor
Quadrant B (corner of South Roman and Perdido
streets). The contractor demolished AHU 4-B and 5-B
and removed the louvers on both mechanical rooms.
The new AHU 4-B and 5-B and the associated ductwork
and piping were installed. The contractor completed
installing the hot water and chilled water piping
for the new units.
They insulated the chilled
water piping for AHU 4-B and began the installation
of electrical and control wiring. Crews balanced RTU
1, RTU 2, and all AHUs on the 6th and 7th Floors.
Renovations to MDL #4 in
the MEB are underway. The contractor removed
plumbing, electrical, existing lab furniture, and
the existing partition panel from the lab. They
removed the old speakers and projector screens. The
contractor prepared the area for asbestos abatement
work and the abatement work was completed. The old
floor tile has been removed.
Renovations to a portion
of the 8th Floor of the Lions/LSU Clinic Building
have begun. Facilities Services started demolition
by removing fire alarm devices and plumbing fixtures
from the 8th Floor lobby and offices. They continue
with the demolition of the conference and lobby
areas. Creative presentations removed the existing
multimedia equipment from the small and large
conference rooms. The general contractor installed
studs in Room 804 (the lab area that is being
converted into the conference room).
A project to replace
portions of the perimeter fencing at the City Park
campus is underway. The contractor removed the old
fence posts along Florida Ave. and Moss St. Workers
staked out the monumental fence posts. On the Uptown
campus, a project to replace the chiller (begun by
the New Orleans Adolescent Hospital prior to being
closed) is continuing. The contractor installed the
condenser water pumps and completed the exterior
condenser piping. The existing chilled water pumps
have been removed.
The contractor corrected
the smoke detectors and the pull station zone
coverage issue in the newly expanded and renovated
Residence Hall lobby. Facility Services conducted a
successful audio test for the fire alarm system. The
flooring contractor removed one row of tile to allow
for the precast concrete installation. The
contractor placed the top precast panel along the
storefront and began installing the precast stone on
the concrete wall starting from the Bolivar Street
side.
Facility Services framed
up concrete forms and poured the new sidewalk in the
corner of the T-lot. Crews installed irrigation
piping adjacent to the Roman St. Garage along
Bolivar Street. They completed the final grading
around the T-lot, planted shrubs and mulched the new
planting beds. Crews also poured concrete for the
new driveway in the rear of Residence Hall on
Bolivar Street.
Here are highlights of
work that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING
PERMANENT REPAIRS AND MITIGATION:
- Bids were advertised on 9/11/2009
- The Pre-Bid Conference was held on 9/28/2009
in the Chancellor’s Conference Room.
- Bids were opened on 10/7/2009. The
architects have recommended the contract be
awarded to the low responsive bidder.
STUDENT RESIDENCE HALL
PERMANENT REPAIRS AND MITIGATION:
- Bids were advertised on 9/16/2009
- The Pre-Bid Conference was held on 10/1/2009
in the Chancellor’s Conference Room.
- Bids will be opened on 10/14/2009.
RESOURCE CENTER PERMANENT
REPAIRS AND MITIGATION:
- Bids were advertised on 9/23/2009
- The Pre-Bid Conference was held on 10/8/2009
in the Chancellor’s Conference Room.
- Bids will be opened on 10/21/2009.
MEB 7th FLOOR PHYSIOLOGY
LAB RENOVATIONS:
- The contractor installed shelves in Rooms
7221, 7241, 7244 and 7250.
- Crews terminated the network data jacks in
Room 7221, 7241, 7244, and 7250.
- They terminated the network cables in
the network closet.
- The contractor trimmed out the electrical
raceways in Rooms 7241, 7244, and 7250.
- Ceiling tile was installed in Rooms 7221,
7241, 7244, and 7250.
- The contractor cleaned Rooms 7221, 7241,
7244, and 7250.
- They buffed and waxed the floors in all
4 rooms.
- Workers connected hot, cold, DI water, and
drain lines in Room 7221, 7241, 7244, and 7250.
- The contractor installed receptacles and
cover plates in Rooms 7221, 7241, and 7250.
- This project is nearing completion.
RESOURCE CENTER ROOF
REPLACEMENT:
- The contractor removed the old roof along
Perdido Street and S. Prieur St. and applied the
two-ply roof.
- The contractor completed all the X-rays of
the roof in preparation for coring.
- All four roof cores were completed.
- Crews placed lightweight concrete on the
main penthouse for insulation.
- They completed applying the two-ply
roofing system over the lightweight concrete
at the main mechanical penthouse.
- The contractor placed lightweight concrete
on the Gravier Street Penthouse and on the
corner of Gravier and Bolivar Street.
- They installed tapered insulation and
applied a two ply roofing system at all roof
drains on the main penthouse.
1542 TULANE GARAGE
ENTRANCES:
- The contractor roughed in the electrical for
the 2nd Floor entrance.
- Workers installed sheetrock for the 2nd
Floor entrance.
- The sprinkler heads for the 2nd Floor
entrance were installed.
- The contractor pulled wiring for the power
receptacles at the 2nd level garage corridor.
- Crews installed sheetrock in Room 242B.
- The contractor taped and floated the walls
for the 2nd level garage entrance corridor.
- They taped and floated the walls in Room
242 and Room 202A for the 2nd level garage
corridor.
- The walls in Room 242B were painted.
- The contractor constructed the wood forms
and installed rebar for the 1st Floor ADA
entrance.
- They poured the concrete curbs and
filled the slab penetrations at the 1st
Floor entrance.
- The contractor poured concrete for the
new ADA entrance ramp.
1542 TULANE AVE. REPAIRS:
- The contractor installed the power
receptacle for the podium in the auditorium.
- Crews floated the sheetrock walls at the S.
Claiborne wall of the auditorium.
MEB AIR HANDLING UNIT
REPLACEMENT:
- The contractor completed the control work
for AHU 4-C and 5-C.
- Facility Services set up the temporary A/C
units in the 4th and 5th Floor Quadrant B
(corner of South Roman and Perdido streets).
- The contractor completed the demolition of
AHU 4-B and 5-B and removed the louvers on both
mechanical rooms.
- Workers installed the new AHU 4-B and 5-B,
new ductwork and new piping.
- The contractor completed installing chilled
water piping for AHU 4-B and 5-B.
- Crews balanced RTU 1, RTU 2, and all AHUs on
the 6th and 7th Floors..
- The contractor completed installing ductwork
and hot water piping for AHU 4-B and 5-B.
- They insulated the chilled water piping for
AHU 4-B and began the installation of electrical
and control wiring.
MDL 4 RENOVATIONS:
- The contractor removed plumbing, electrical,
existing lab furniture, and the existing
partition panel from the lab.
- They removed the old speakers and
projector screens.
- The contractor prepared for asbestos
abatement work.
- The abatement work was completed. The
contractor removed the plastic containment
and completed the final cleaning.
- The contractor removed the old floor tile.
LIONS EYE 8TH FLOOR
RENOVATIONS:
- Facilities Services started removing fire
alarm devices and plumbing fixtures from the 8th
Floor lobby and offices.
- Facilities Services continued demolition of
the conference and lobby areas.
- Creative presentations continued removing
multimedia equipment from the small and large
conference rooms.
- The general contractor installed studs in
Room 804 (lab area that is being converted into
the conference room).
DENTAL SCHOOL FENCE
REPLACEMENT:
- The contractor removed the old fence posts
along Florida Ave. and Moss St.
- The contractor staked the monumental fence
posts.
UPTOWN CAMPUS CHILLER
REPLACEMENT:
- The Uptown Campus is the former site of the
New Orleans Adolescent Hospital.
- The contractor installed the condenser water
pumps and completed the exterior condenser
piping.
- The contractor removed the existing chilled
water pumps.
RESIDENCE HALL LOBBY
EXPANSION:
- The contractor corrected the smoke detectors
and the pull station zone coverage issue.
- Facility Services conducted a successful
audio test for the fire alarm system.
- The flooring contractor removed one row of
tile to allow for the precast concrete
installation.
- The contractor placed the top precast panel
along the storefront.
- Workers installed four exit signs and
replaced light bulbs.
- The contractor began installing the precast
stone on the concrete wall starting from the
Bolivar Street side.
EXTERIOR/LANDSCAPING:
- Facility Services framed up concrete forms
and poured the new sidewalk in the corner of the
T-lot.
- They poured concrete for the new driveway in
the rear of Residence Hall on Bolivar Street.
- Facility Services installed irrigation
piping adjacent to the Roman St. Garage along
Bolivar Street.
- Crews completed the final grading around the
T-lot.
- Facility Services completed planting shrubs
and mulching around the perimeter of T-lot.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|