Subject: Hurricane Katrina Recovery – Update #120
Posted: June 18, 2010
The permanent repairs and mitigation project is
continuing at the Allied Health/Nursing Building.
The contractor installed new electrical lighting
circuits on the 1st Floor and conduits for the fire
alarm panels on the 2nd Floor. Fire alarm cables are
being pulled to the new 2nd Floor fire alarm panel.
The stairwell walls in the two stairwells near South
Roman Street were removed and six CMU walls five
feet tall were installed in the office area on the
1st Floor. The call lights and call stations were
removed from Elevators 1, 2, and 3. The contractor
laid CMU block in the stairwell near the corner of
the MEB loading dock and S. Roman Street.
Approximately half of the granite panels were
removed from the elevator lobby and the CMU block
was removed from around the elevator shafts.
The new elevated structure being constructed at the
rear of the Residence Hall is progressing. The
concrete for the 2nd Floor slab was poured and the
forms removed. Crews erected the concrete forms for
the columns that will support the walls and roof and
installed conduit and reinforcing steel in the
forms. The concrete was poured and the forms removed
from the columns. Workers started building concrete
forms for the roof of the new enclosure. The
trenched hole on the Bolivar Street Side was filled
and compacted. Two trenches that cross the main
driveway of the Residence Hall parking lot were
completed. The contractor trenched an area under the
basketball court near the oak tree for the plumbing
piping and an area behind the basketball court for
electrical conduit.
The contractor laid CMU walls and ran electrical
conduit in the 1st Floor office areas of the
Resource Center. The contractor completed blocking
the shaft for Elevators 3 and 4 and removed the
temporary shaft wall. Crews are installing the
elevator pit equipment for Elevators 3 and 4. Crews
began running the electrical control wires to the
ATS Room. A temporary construction wall was erected
in the Bookstore and the office walls are being
removed. The contractor continued construction of
the CMU walls in the 1st Floor office areas and in
the Women’s restroom and completed laying block in
the Men’s restroom. The contractor completed the 7
floor penetrations in the switchgear room and 16 of
25 conduits have been installed. Conduit was also
installed in 1st Floor ceiling under the new
switchgear room. Workers began fabricating chilled
water bypass piping in the 2nd Floor pump room.
The renovations underway on the 8th Floor of the
Lions/LSU Clinic Building continue. The new wall
panels have been installed in the large conference
room. Crews painted the office areas and the soffit
and door in the lobby. The ductwork in the large
conference room was relocated. The contractor
roughed in for the light fixtures in the large
conference room and installed the new light
fixtures. The glass was installed in the large
conference room doors. The wood floors in the
Director’s Office and the small conference room were
installed. Workers began installing the ceiling
tiles in the large conference room.
The wood piles that will support the CEB covered
walkway were delivered to the 1542 parking lot. The
contractor surveyed the site to determine the
locations for the wood piles. Crews have been
driving the piles that will support the walkway and
its cover. 10 piles remain to be driven.
The contractor completed backfilling the trenches
for the new drain piping for the new patient parking
lot being constructed at the Dental School. They
graded the site in preparation for the installation
of the underground electrical wiring. Piles for the
3 new light poles were driven and the formwork for
the concrete light pole bases was constructed. They
trenched for the light pole electrical service,
installed the electrical service conduit and
backfilled the trenches. The contractor has begun
the overall site grading and continued hauling
excavated material. Crews started installing the
geo-textile fabric and laying limestone base
material for the parking lot.
Here are highlights of work that has been
accomplished during the past two weeks.
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS &
MITIGATION:
- The contractor installed new
electrical lighting circuits on the 1st Floor
and conduits for the fire alarm panels on the
2nd Floor.
- They are pulling fire alarm cables to the
2nd Floor fire alarm panel.
- The stairwell walls in the two
stairwells near South Roman Street were removed.
- Crews installed six CMU walls five
feet tall in the office area on the 1st Floor.
- The call lights and call stations were
removed from Elevators 1, 2, and 3.
- The contractor installed CMU in the
stairwell near the corner of the MEB loading
dock and S. Roman Street.
- Approximately half of the granite
panels were removed from the elevator lobby.
- The CMU block was removed from the
elevator shaft.
- Crews laid six new CMU block walls for
office area on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed electrical
conduits in the forms for the 2nd Floor slab in
the new elevated mechanical/electrical/plumbing
enclosure.
- The concrete for the 2nd Floor slab in
the new elevated mechanical/electrical/plumbing
enclosure was poured and the forms removed.
- Crews began erecting concrete forms
for the columns on the 2nd Floor of the
enclosure and installed reinforcing steel in the
forms.
- The concrete was poured and the forms
removed from the columns.
- Workers started building concrete
forms for the roof of the new enclosure.
- The trenched hole on the Bolivar
Street Side was filled and compacted.
- Two trenches that cross the main
driveway of the Residence Hall parking lot were
completed.
- The contractor trenched an area under
the basketball court near the oak tree for the
plumbing piping and an area behind the
basketball court for electrical conduit.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor laid CMU walls and ran
electrical conduit in the 1st Floor office
areas.
- Crews installed conduit on the 2nd
Floor.
- The contractor completed blocking the
shaft for Elevators 3 and 4 and removed the
temporary shaft wall for Elevators 3 and 4.
- Crews began running the electrical
control wires to the ATS Room.
- A temporary construction wall was
erected in the Bookstore and the office walls
are being removed.
- The contractor continued construction
of the CMU walls in the 1st Floor office areas
and in the Women’s restroom.
- They completed the CMU walls in the
Men’s restroom.
- Crews are installing the elevator pit
equipment for Elevators 3 and 4.
- The contractor completed the 7 floor
penetrations in the switchgear room.
- 16 of 25 conduits have been installed
in the new switchgear room.
- Conduit was installed in 1st Floor
ceiling under the new switchgear room.
- The contractor began fabricating
chilled water bypass piping in the 2nd Floor
pump room.
- The contractor removed the exterior
wall of the new switchgear room.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor installed new wall
panels in the large conference room.
- They painted the office areas and the
soffit and door in the lobby.
- The ductwork in the large conference
room was relocated.
- The contractor roughed in for the
light fixtures in the large conference room and
installed the new light fixtures.
- The glass was installed in the large
conference room doors.
- They installed the wood floor in the
Director’s Office and the small conference room.
- Workers began installing the ceiling
tiles in the large conference room.
CEB COVERED WALKWAY:
- The wood piles were delivered to the
1542 parking lot.
- The contractor surveyed the site to
determine the locations for the wood piles.
- Crews have been driving the piles that
will support the walkway and its cover. 10 piles
remain to be driven.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor completed backfilling
the trenches for the new drain piping.
- They graded the site in preparation
for the installation of the underground
electrical wiring.
- The contractor drove piles for the 3
new light poles and constructed the formwork for
the concrete light pole bases.
- They trenched for the light pole
electrical service, installed the electrical
service conduit and backfilled the trenches.
- The contractor began overall site
grading and continued hauling excavated
material.
- The contractor continued the
preparation of the base course and hauling away
the excavated material.
- Crews started installing the
geo-textile fabric and laying limestone base
material.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|