From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #122
Posted: July 16, 2010
Progress is being
made at the Allied Health/Nursing Building. The granite panels that surrounded the
elevator lobby on the 1st Floor have been
re-installed. The new CMU walls for the Elevators 1, 2 and
3 were cleaned and three coats of the waterproofing
material were applied. The elevator sub-contractor has begun work on
installing the pit parts for the three elevators and
the new sump pump waste line serving the elevators
has been run. All of the required fire proofing material
has been applied to the new structural steel. The electrical contractor finished installing
electrical panel D1A and their crews continue
running new conduit. Outdated telephone and data wires were
removed from the telecom room on the 2nd Floor.
Crews finished
building the concrete forms for the roof of the new
electrical/mechanical enclosure at the rear of the
Student Residence Hall. The reinforcing steel was installed and the
concrete has been poured. Fifty feet of electrical conduit was laid in
the main driveway and the area has been back filled. The contractor installed a 6-inch roof drain
piping in the main driveway and back-filled the
area.
Workers partially removed an existing grade beam to
allow for the new electrical duct bank installation
in the main drive way and they continue installing
the new electrical duct bank.
At the Resource
Center, the breakers in two electrical panels in the
2nd Floor switchgear room were installed and the
contractor continues installing electrical conduit
in the 1st Floor ceiling for the electrical panels
on the 2nd Floor and in the 8th Floor electrical
room.
Crews have begun pulling wires in the new switchgear
room on the 2nd Floor and for the roof top
generator. Workers are insulating the chilled water
piping in the 2nd Floor pump room. The contractor removed one of four air
handling units from the 1st Floor mechanical room in
preparation for raising the unit. The first of the elevated platforms for the
AHUs has been installed, the concrete pad poured and
the AHU has been placed on the new platform. The elevator contractor continued removing
the pit parts from Elevators 1 and 2 while crews
laid CMU block for the elevators on the 1st Floor. A temporary shaft wall for Elevators 1 & 2
was constructed on the 1st Floor. The roofing contractor began erecting roof
curbs for the roof mounted emergency generator.
The ceiling tile
installation in the large conference room and the
Director’s Office on the 8th Floor of the Lions/LSU
Clinic Building has been completed. The new light shades were installed in the
elevator lobby and the Director’s office. LSUHSC Computer Services installed the
wireless access points in the renovated space. The lighting dimmer panel and the projection
screen in the large conference room have been
installed. The contractor installed cove base and doors
and painted the elevator soffit. Crews continue installing wall paper, wood
baseboard, wood ceiling tiles and the new millwork
throughout the renovated space.
The contractor built
the formwork and poured concrete for the concrete
curbs, islands, catch basins and sidewalks at the
new patient parking lot being constructed at the
Dental School. Protective bollards have been installed and
the parking area was given the final grading in
preparation for asphalt paving and the paving of the
parking lot has been completed. The contractor prepared for the electrical
installation, demobilized the paving equipment and
performed site clean-up.
Here are highlights of work
that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS &
MITIGATION:
- The electrical contractor finished installing
electrical panel D1A.
- They continue to install new electrical conduit.
- Workers cleaned the CMU wall for Elevators 1, 2, and
3 on the 1st Floor.
- Workers applied three coats of the elevator shaft
wall waterproofing.
- All five coats of fire proofing were applied to the
new structural steel beams.
- The sump pump waste line serving the elevator put
was run.
- The electrical contractor removed outdated telephone
and data wires from the telecom room on the 2nd
Floor.
- The contractor re-installed the granite panels
surrounding the elevator lobby.
- The elevator sub-contractor started installing pit
parts for Elevators 1-3.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed fifty feet of electrical
conduit in the main driveway and back filled the
area.
- They installed a 6-inch roof drain piping in the
main driveway and back-filled the area.
- Crews finished building the concrete forms for the
roof of the new electrical/mechanical enclosure.
- The reinforcing steel was installed in the forms and
the concrete has been poured.
- The contractor removed concrete near the A Tower
electrical room on the 1st Floor.
- They cleaned the parking area underneath the
basketball court.
- The contractor partially removed an existing grade
beam to allow for the new electrical duct bank
installation in the main drive way.
- The electrical contractor continues installing the
new electrical duct bank in the main driveway.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The breakers in two electrical panels in the 2nd
Floor switchgear room were installed.
- The contractor continues installing electrical
conduit in the 1st Floor ceiling for the electrical
panels on the 2nd Floor and in the 8th Floor
electrical room.
- They began pulling wires in the new switchgear room
on the 2nd Floor.
- The electrical contractor is pulling wire for the
roof generator.
- Workers are insulating the chilled water piping in
the 2nd Floor pump room.
- The contractor removed one of four air handling
units from the 1st Floor mechanical room in
preparation for raising the unit.
- The mechanical contractor installed one of four air
handling unit (AHU) raised platforms in the 1st
Floor mechanical room.
- They poured the concrete pad for the AHU in the 1st
Floor mechanical room.
- The AHU has been placed on the platform.
- The elevator contractor continued removing the pit
parts from Elevators 1 and 2.
- Crews laid CMU block for Elevators 1 & 2 on the 1st
Floor.
- The general contractor constructed the temporary
shaft wall for Elevators 1 & 2 on the 1st Floor.
- The roofing contractor began erecting roof curbs for
the emergency generator.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The ceiling tile installation in the large
conference room and the Director’s Office has been
completed.
- The contractor completed installing light shades in
the elevator lobby and the Director’s office.
- The contractor continues installing wall paper, wood
baseboard, wood ceiling tiles and the new millwork
throughout the renovated space.
- LSUHSC Computer Services installed the wireless
access points.
- Workers painted the elevator soffit.
- The contractor installed the lighting dimmer panel.
- The AV contractor installed the projection screen in
the large conference room.
- The contractor installed cove base and doors.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor built the formwork and poured
concrete for the concrete curbs, islands, catch
basins and sidewalks.
- Protective bollards have been installed and the
parking area was given the final grading in
preparation for paving.
- The asphalt paving of the parking lot has been
completed.
- They prepared for the electrical installation,
demobilized the paving equipment and performed site
clean-up.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|