Workers finished installing the restroom partitions
in the Women’s restroom on the 1st Floor of the
Allied Health/Nursing Building and the 1st Floor
restroom fixtures were installed. The contractor poured concrete for the raised
seating area in the 2nd Floor auditorium and began
installing the concrete forms for the auditorium
ramp and stairs. Drywall is being installed in the 2nd Floor
auditorium and the ceiling grid is being installed
on the 2nd Floor along the MEB loading dock side of
the building. The contractor started installing conduit for
the light fixtures in the Tiger Room and installed
the projector screen in Room 147. Wiring was installed for the lights in Room
138 and repairs are being made to door frames on the
2nd Floor. The contractor continued installing the metal
track for the wood panel system and the medical gas
system on the 2nd Floor.
The contractor
touched up paint for doors on the 2nd level of the
elevated mechanical/electrical enclosure at the
Student Residence Hall and insulated the domestic
water pipe on the C-tower side of the 1st Floor of
the main building. Crews finished insulating the generator and
fire pump exhaust pipes on the 2nd level of the new
building and patched the CMU wall around pipe
penetrations on the ground floor. The contractor continued insulating the 4
inch domestic water pipe on the ground floor.
The Resource Center
contractor finished installing the generator fuel
line on the 8th Floor and pressure tested the fuel
line.
Crews are welding the containment pipe for the
diesel fuel line on the 8th Floor. The installation of the generator fuel line
on the 1st Floor is in progress. Workers began installing the piping manifold
for the domestic hot and cold water pumps in the 2nd
Floor pump room. They are installing the controls on the 1st
Floor air handling units (AHUs). The contractor continued installing the
electrical conduit for the fire pump controller. They created floor penetrations on the 2nd
Floor for the fire water piping and began installing
the fire pump piping. Chilled water was connected to the two fan
coil units in the 1st and 2nd Floor pump rooms.
The contractor drove
an additional 86 wooden piles in the Lakeside lot at
the Clinical Education Building. All of the 110 piles that will support the
new elevated mechanical/electrical enclosure are now
in place. Crews continued welding and installing 6
inch chilled water pipe in the basement. They continued installing electrical conduits
on the 1st Floor and electrical conduits and
junction boxes on the 3rd Floor while other workers
continued removing the elevator shaft in the library
area.
The project to upgrade the CSRB exhaust system
continues. The contractor installed the exhaust duct
riser for Exhaust System #4 on the 3rd, 4th, 5th,
6th and 7th Floors and began installing temporary
ductwork on the 2nd Floor. Crews cut the roof penetration for Exhaust
System #1. They installed the plenum support for Exhaust
System #2 and the pipe support for exhaust fans 1D
and 2D.
Acid vent lines were relocated on the 2nd and 6th
Floors.
The contractor responsible for replacing the air
handling units at the Dental School continued
insulating the supply duct and heating hot water
lines for units 8A & 8D in the Clinic Building. Crews ran control wires for units 8A and 8D
and the fire alarm devices for unit 8D were
installed. Air
handling units 8A, 8B, 8C and 8D were put into
operation. The ceiling grid was installed in
Central Sterilization and on the 8th Floor and
ceiling tiles were installed on the 8th Floor.
Crews continued removing the ceiling on the 3rd
Floor of the Clinic Building and removed unit 3B
from the mechanical room. The drain pan was installed in the mechanical
room for unit 3B. Supply ductwork and VAV boxes are now being
installed on the 3rd Floor of the Clinic Building.
The AHU contractor continued installing the VAV
boxes and running reheat lines on the 3rd Floor of
the Administration Building and continued insulating
the heating hot water pipe in Room 2302. Conduits were installed for the controls in
Room 2302 and crews installed control wires for VAV
boxes on the 2nd Floor. The heating hot water lines for unit L3A on
the 3rd Floor were installed.
The building exterior
waterproofing contractor working at the Dental
School continued to remove the existing caulk,
prepare the surfaces between the exterior building
panels and install new backer rod and caulk on the
west and east sides of the Clinic Building and the
west and north sides of the Administration Building. They also secured three loose panels on the
east side of the Clinic Building.
Here are highlights of work
that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS &
MITIGATION:
- Workers finished installing the restroom partitions
in the Women’s restroom on the 1st Floor and
restroom fixtures were installed on the 1st Floor.
- The contractor poured concrete for the raised
seating area in the 2nd Floor auditorium.
- The concrete forms for the ramp and stairs in the
2nd Floor auditorium are being installed.
- Drywall is being installed in the 2nd Floor
auditorium.
- Ceiling grid is being installed on the 2nd Floor
along the MEB loading dock side of the building.
- The contractor started installing conduit for the
light fixtures in the Tiger Room.
- The projector screen was installed in Room 147.
- Wiring for the lights in Room 138 was installed.
- Repairs are being made to door frames on the 2nd
Floor.
- The contractor continued installing the metal track
for the wood panel system and the medical gas system
on the 2nd Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor touched up paint for doors on the 2nd
level of the new building.
- They insulated the domestic water pipe on the
C-tower side of the 1st Floor.
- The contractor finished insulating the generator and
fire pump exhaust pipes on the 2nd level of the new
building.
- They patched the CMU wall around pipe penetrations
on the ground floor.
- The contractor continued insulating the 4 inch
domestic water pipe on the ground floor.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor finished installing the generator
fuel line on the 8th Floor.
- They pressure tested the internal fuel lines on the
8th Floor.
- Crews continue to weld the containment pipe for the
diesel fuel line on the 8th Floor.
- The installation of the generator fuel line on the
1st Floor is in progress.
- Workers began installing the piping manifold for the
domestic hot and cold water pumps in the 2nd Floor
pump room.
- They are installing the controls on the 1st Floor
air handling units (AHUs).
- Workers began priming the walls in the fire pump
room.
- The contractor continued installing the electrical
conduit for the fire pump controller.
- They created floor penetrations on the 2nd Floor for
the fire water piping and began installing the fire
pump piping.
- The contractor connected chilled water to the two
fan coil units in the 1st and 2nd Floor pump rooms.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor drove an additional 86 wooden piles
in the Lakeside lot. All of the 110 piles are now in place.
- Crews continued welding and installing 6 inch
chilled water pipe in the basement.
- They continued installing electrical conduits on the
1st Floor and electrical conduits and junction boxes
on the 3rd Floor.
- Workers continued removing the elevator shaft in the
library area.
CSRB EXHAUST UPGRADE:
- The contractor installed the exhaust duct riser for
Exhaust System #4 on the 3rd, 4th, 5th, 6th and 7th
Floors.
- The contractor began installing temporary ductwork
on the 2nd Floor.
- Crews cut the roof penetration for Exhaust system
#1.
- The contractor installed the plenum support for
Exhaust system #2 and the pipe support for exhaust
fans 1D and 2D.
- The contractor relocated acid vent lines on the 2nd
and 6th Floors.
DENTAL SCHOOL AHU REPLACEMENT:
- The contractor continued insulating the supply duct
and heating hot water lines for units 8A & 8D in the
Clinic Building.
- Crews ran control wires for 8A and 8D.
- The fire alarm devices for unit 8D were installed.
- The contractor put units 8A, 8B, 8C and 8D into
operation.
- The ceiling grid was installed in Central
Sterilization and on the 8th Floor.
- The contractor installed the ceiling on the 8th
Floor.
- Crews continued removing the ceiling on the 3rd
Floor.
- The contractor removed unit 3B from the mechanical
room.
- Supply ductwork and VAV boxes are being installed on
the 3rd Floor of the Clinic Building.
- The drain pan was installed in the mechanical room
for unit 3B.
- The contractor continued installing the VAV boxes
and running reheat lines on the 3rd Floor of the
Administration Building.
- Crews continued insulating the heating hot water
pipe in Room 2302.
- Conduits were installed for the controls in Room
2302.
- Crews installed control wires for VAV boxes on the
2nd Floor of the Administration Building.
- The heating hot water lines for unit L3A on the 3rd
Floor were installed.
DENTAL SCHOOL BLDG EXTERIOR
WATERPROOFING:
- The contractor continued to remove the existing
caulk, prepare the surfaces between the exterior
building panels, and install new backer rod and
caulk on the west and east sides of the Clinic
Building and the west and north sides of the
Administration Building.
- They secured three loose panels on the east side of
the Clinic Building.
CEB COVERED WALKWAY:
- The contractor finished installing the flashing on
canopy B at the end of the walkway closest to the
Clinical Education Building.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.