Subject: Hurricane Katrina Recovery – Update #146
Posted: July 1, 2011
The Allied Health/Nursing Building contractor
relocated the heating hot water lines going into the
building and framed the temporary walls for the
monumental stairwell project. Workers
continued installing the metal framing for the
auditorium wall panel system and conduit for the
audio/visual equipment in the auditorium is being
run.
Crews started installing metal panels underneath the
walkway.
The walkway floor drains were re-routed.
The contractor
finished welding the diesel fuel line on the 1st
Floor of the Resource Center. They welded the casing for the fuel line on
the 1st Floor and in the electrical rooms and
continued welding the casing in the electrical rooms
on the 2nd and 3rd Floors. The electrical disconnects for the domestic
water pump were mounted and connected and light
fixtures were installed in the 2nd Floor pump room. The contractor insulated piping in the 2nd
Floor pump room and began installing wiring for the
four heating water pumps on the mezzanine deck of
the pump room.
Concrete forms for
the freight elevator shaft wall in the basement of
the Clinical Education Building were erected. The contractor continued excavating for the
12 pile caps in the Lakeside lot. Concrete forms for 5 of the 12 pile caps were
erected and two additional pile caps are being
formed up. Rebar was installed in the concrete forms for
the first 3 pile caps. The contractor continued installing
electrical conduit on the 2nd and 3rd Floors while
other workers continued to weld and install 8 inch
chilled water lines in the basement.
The CSRB exhaust upgrade contractor pulled the
emergency power wires for the exhaust fans.
Light
fixtures were removed on the 2nd Floor and the
construction wall was relocated to encompass
additional ductwork. The plaster ceiling was removed and
insulation was removed from the old exhaust ductwork
on the 2nd Floor.
The old air handling units 3A and 6A were removed
from the Dental campus Clinic Building. Workers
continued installing new heating hot water lines for
units 3A and 3B. The supply ductwork for unit
3-B was installed and crews are insulating the
ductwork. The contractor continues to install supply
ductwork and the VAVs for unit 3-A. The
ductwork for units 3A and 3B was pressure tested.
Crews demolished the existing doorway in the
mechanical room for unit 6A.
The contractor placed the concrete pads for units 3A
and 6A and set the new AHUs in place. They set VAV boxes for unit 6A. The asbestos
contractor removed ductwork near Rooms 6313, 6405
and 6302 and completed the abatement related to AHU
6A. The contractor installed isolation valves
on all units on the B-riser in the Clinic Building.
The AHU replacement project contractor replaced the
breakers for unit L2A in the Dental campus
Administration Building and started up the unit.
The ceiling was replaced in the main hallway on the
2nd Floor. Workers framed and hung sheetrock on the
ceiling of the 2nd Floor Men’s restroom. Crews
floated and painted the sheetrock ceiling in the
restroom and near Faculty Practice on the 2nd Floor.
The asbestos contractor removed ductwork from the
4th Floor mechanical room. The contractor
started pre-fabricating the chilled water lines for
the 4th Floor units.
The waterproofing contractor working on the Dental
School campus buildings pressure washed the concrete
fins on the north side of Clinic Building. Workers continue to remove the old caulk and
backer rod, prepare the surfaces of the building
panels and install new caulk on the ground floor
columns and the west side the Clinic Building and
the north side and penthouse of the Administration
Building.
Here are highlights of work
that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor relocated the heating hot water lines
going into the building.
- Crews framed the temporary walls for the monumental
stairwell project.
- Workers continued installing the metal framing for
the auditorium wall panel system.
- Conduit for the audio/visual equipment in the
auditorium is being run.
- Crews started installing metal panels underneath the
walkway.
- The walkway floor drains were re-routed.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor finished welding the diesel fuel line
on the 1st Floor.
- They welded the casing for the diesel fuel line on
the 1st Floor and in the electrical rooms.
- The contractor continued welding the diesel fuel
line casing in the electrical rooms on the 2nd and
3rd Floors.
- The electrical disconnects for the domestic water
pump in the 2nd Floor pump room were mounted and
connected.
- Light fixtures were installed in the 2nd Floor pump
room.
- The contractor insulated piping in the 2nd Floor
pump room.
- The contractor began installing wiring for the four
heating water pumps on the mezzanine deck of the 2nd
Floor pump room.
CEB PERMANENT REPAIRS & MITIGATION:
- Concrete forms for the freight elevator shaft wall
in the basement were erected.
- The contractor continued excavating for the 12 pile
caps in the Lakeside lot.
- The contractor erected the concrete forms for 5 of
the 12 pile caps. Two additional pile caps are being formed.
- Rebar was installed in the concrete forms for the
first 3 pile caps.
- The contractor continued installing electrical
conduit on the 2nd and 3rd Floors.
- Workers continued to weld and install 8 inch chilled
water lines in the basement.
CSRB EXHAUST UPGRADE:
- The contractor pulled the emergency power wires for
the exhaust fans.
- Light fixtures were removed on the 2nd Floor.
- The construction wall was relocated to encompass
additional ductwork on the 2nd Floor.
- The contractor removed plaster ceiling on the 2nd
Floor.
- The insulation was removed from the old exhaust
ductwork on the 2nd Floor.
DENTAL SCHOOL AHU REPLACEMENT:
- The contractor removed units 3A and 6A.
- Workers continued installing heating hot water lines
for units 3A and 3B in the Clinic Building.
- The supply ductwork for unit 3-B was installed and
crews are insulating the ductwork.
- The contractor continues to install supply ductwork
and the VAVs for unit 3-A.
- The ductwork for units 3A and 3B was pressure
tested.
- Crews demolished the existing doorway in the
mechanical room for unit 6A.
- The contractor placed the concrete pads for units 3A
and 6A and set the new units in place.
- They set VAV boxes for unit 6A.
- The asbestos contractor removed ductwork near Rooms
6313, 6405 and 6302 and completed the abatement
related to AHU 6A.
- The contractor installed isolation valves on all
units on the B-riser in the Clinic Building.
- The contractor replaced the breakers for unit L2A in
the Administration Building and started up the unit.
- The ceiling was replaced in the main hallway on the
2nd Floor.
- Workers framed and hung sheetrock for the 2nd Floor
Men’s restroom.
- Crews floated and painted the sheetrock ceiling in
the restroom and near Faculty Practice on the 2nd
Floor of the Administration Building.
- The asbestos contractor removed ductwork from the
4th Floor mechanical room.
- The contractor started pre-fabricating the chilled
water lines for the 4th Floor units.
DENTAL SCHOOL BLDG EXTERIOR
WATERPROOFING:
- The contractor pressure washed the concrete fins on
the north side of Clinic Building.
- Workers continue to remove the old caulk and backer
rod, prepare the surfaces of the building panels and
install new caulk on the ground floor columns and
the west side the Clinic Building and the north side
and penthouse of the Administration Building.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|