From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #147
Posted: July 15, 2011
The Allied Health/Nursing Building contractor
erected scaffolding above the monumental stairs.
The glass railing surrounding the staircase was
removed; the structural supports for the new
monumental staircase were welded in place and
grouted.
The contractor re-routed the walkway floor drains
and installed a check valve on the 1st Floor.
Additional AV conduit was run on the 2nd Floor and
floor epoxy was applied to the ramp in the
auditorium. Crews continued installing the
metal framing for the auditorium wall panel system
and sheetrock was hung on the rear wall. The Resource Center contractor continued
welding the diesel fuel line casing on the 1st Floor
and fire alarm system components are being
installed.
The first 3 pile caps that will support the elevated
mechanical/electrical enclosure at the Clinical
Education Building were poured. Forms for 6
additional pile caps have been set in the Lakeside
lot and the rebar has been installed. (There will be a total of 12 pile caps.) The contractor continued forming up the
freight elevator shaft wall in the basement. Metal support framing for the corridor wall
was installed on the 3rd Floor. Workers installed the 6 inch domestic water
supply line in the basement and continued installing
conduits on the 2nd and 3rd Floor.
The CSRB exhaust
system upgrade contractor connected the temporary
exhaust ductwork on the 2nd Floor. The existing 2nd Floor exhaust ductwork was
removed and new ductwork hangers were installed. Crews began installing new ductwork and
relocating fire alarms and electrical devices on the
2nd Floor. The ceiling in Room 729 was removed. The exhaust fan frames for exhaust fan
systems 1, 2, 3 and 4 on the roof were welded and
the pitch pockets (roof penetrations for utilities)
were installed. The roof flashing for exhaust systems 1 and 2
is being installed.
Work on the air handler replacement project at the
Dental School is progressing. The contractor installed heating hot water
lines for unit 3A in the Clinic Building and the
heating hot water lines for units 3A and 3B are
being insulated. Crews continued installing supply ductwork
for units 3A and 3B and insulating the new ductwork. The ceiling grid was installed on the 3rd
Floor of the Clinic Building and control wires for
unit 3A were installed. The contractor installed ceiling and light
fixtures for unit 3A above the Radiology clinic area
and began putting up the ceiling grid up for unit
3A. The ceiling tile was removed from Room
3312N. The VAV boxes for AHU 6A have been set
in place and the heating hot water lines are being
installed. The controls contractor wired the control
panel for L2A in the Administration Building and
crews are installing the controls for units L2A and
L3A. The supply ductwork and heating hot water
lines for unit L3A were installed.
The waterproofing contractor finished caulking the
west side of the Clinic Building and the columns on
the ground floors of the Clinic and Administration
Buildings. The loose panels on the south side of the
Clinic Building were repaired. Crews are washing the north, south and east
sides of the Power Plant.
Here are highlights of work that has been
accomplished during the past two weeks.
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- Scaffolding was erected above the monumental stairs.
- The glass railing surrounding the monumental
staircase was removed and structural supports for
the new monumental staircase were welded in place.
- Workers grouted the structural supports for the new monumental staircase.
- The contractor re-routed the walkway floor drains and installed a check valve on the 1st Floor.
- Additional AV conduit was run on the 2nd Floor.
- Floor epoxy was applied to the ramp in the auditorium.
- The contractor continued installing the metal framing for the auditorium wall panel system.
- Sheetrock was hung on the rear wall of the auditorium.
- The contractor continued prefabricating chilled water lines.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the diesel fuel line casing on the 1st Floor.
- The fire alarm system components are being installed.
CEB PERMANENT REPAIRS & MITIGATION:
- The first 3 pile caps in the Lakeside lot were poured.
- Forms for 6 additional pile caps have been set in the Lakeside lot and the rebar has been installed.
- The contractor continued forming up the freight elevator shaft wall in the basement.
- Metal support framing for the corridor wall was installed on the 3rd Floor.
- The contractor installed the 6 inch domestic water supply line in the basement.
- The contractor continued installing conduits on the 2nd and 3rd Floor.
CSRB EXHAUST UPGRADE:
- The contractor connected the temporary exhaust ductwork on the 2nd Floor.
- The existing 2nd Floor exhaust ductwork was removed.
- The new ductwork hangers were installed on the 2nd Floor.
- Crews began installing new ductwork on the 2nd Floor.
- The contractor began relocating fire alarms and electrical devices on the 2nd Floor.
- The ceiling in Room 729 was removed.
- The contractor welded the exhaust fan frames for exhaust fan systems 1, 2, 3 and 4 on the roof.
- They installed pitch pockets (roof penetrations for utilities) on the roof for exhaust systems 1 – 4.
- The roof flashing for exhaust systems 1 and 2 is being installed.
DENTAL SCHOOL AHU REPLACEMENT:
- The contractor installed heating hot water lines for unit 3A in the Clinic Building.
- The heating hot water lines for units 3A and 3B are being insulated.
- Crews continued installing supply ductwork for units 3A and 3B and insulating the new ductwork.
- The ceiling grid was installed on the 3rd Floor of the Clinic Building.
- Control wires for unit 3A were installed.
- The contractor installed ceiling and light fixtures for unit 3A above the Radiology clinic area.
- They began putting up the ceiling grid up for unit 3A.
- The ceiling tile was removed from Room 3312N.
- The VAV boxes for AHU 6A have been set in place.
- The contractor is installing heating hot water lines for unit 6A in the Clinic Building.
- The controls contractor wired the control panel for L2A in the Administration Building.
- Crews are installing the controls for units L2A and L3A.
- They installed supply ductwork and heating hot water lines for unit L3A.
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:
- The contractor finished caulking the west side of
the Clinic Building and the columns on the ground
floors of the Clinic and Administration Buildings.
- The loose panels on the south side of the Clinic Building were repaired.
- The contractor is washing the north, south and east sides of the Power Plant.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|