  • The contractor removing flood damaged building materials has completed their work at Stanislaus Hall and they have requested the final walk through.
  • The building power at the Residence Hall was shut down today as planned. The cleaning of the switchgear went well and the contractor will be on site to continue their work tomorrow.
  • The contractor completed the installation of the fire control panel at the CSRB and the replacement fire pump for the building was delivered today.