Tuesday, January 24, 2006

  • The contractor cleaning the public areas and restrooms at the School of Dentistry has completed their work in the Clinic Building down to the 2nd floor.
  • The CSRB fire pump has been installed. The contractor must still pour the concrete pad to secure it and make the electrical connections to the motor. The fire pump at the Lion's Eye Center has been removed.
  • The contractor removing flood damaged carpet and building materials from the downtown campus buildings and the 1st floor of the Dental School Clinic and Administration buildings has largely completed their work. Minor tasks remain to be completed at Stanislaus Hall, 1542 Tulane Ave., and the Dental School.
  • In order to make repairs to the permanent power in the Medical Education Building, a temporary power outage estimated to last 4 hours is scheduled for Thursday, January 26, at noon.