Monday, February 13, 2006 - The environmental remediation contractor completed their work on Floors 3-7 in the CSRB, excluding the mechanical rooms on those floors.
- The remediation work was also completed on the 5th and 7th floors of the Lion's Eye Center.
- Remediation work began on the 7th floor of the MEB and will continue tomorrow. When the 7th floor is complete, the teams will move to the 6th Floor of MEB.
|