Tuesday, March 21, 2006

  • Floor tile is now being removed from the 5th, 4th and 3rd floors in the Residence Hall. The environmental remediation contractor has also completed the cleaning of the 3rd and 4th floors of the Resource Center.
  • One of the two boilers in the MEB is now online and holding a load.