  • The contractor has started to install the boiler feeder water pumps in the MEB. They have completed the installation of the chemical pumps. The chemical pumps add chemical to the boilers to treat the water and de-scale the boiler.
  • The environmental remediation contractor is continuing to clean on the first floor of the Resource Center and the Nursing/Allied Health Buildings and in the basement of Stanislaus Hall.