  • The 2nd environmental remediation contract has been awarded and the contractor has begun to mobilize their work crews. This contract will address the Residence Hall, Stanislaus Hall, the Nursing/Allied Health Building and the Resource Center in this order of priority. As with the 1st remediation contract, we anticipate that multiple crews will allow work to be accomplished in more than one building at a time.
  • The damaged radiator has been removed from the emergency (roof mounted) generator at the MEB.
  • The elevator maintenance contractor started the installation of the DC generator for the #7 freight elevator at the MEB today.