Monday, June 05, 2006

  • The replacement of the air conditioning feeder at the CSRB on Saturday went faster than anticipated, allowing us to cancel the outage planned for Sunday, June 4th. This completes the required work on the A/C feeder. Additional outages will follow in the next several weekends to replace the riser feeders which service CSRB lighting and receptacles. A mass email will be released later this week announcing this specific schedules and outages.
  • The vacuum pumps and medical air compressors have been installed and connected to the building systems at the Lions/LSU Clinic and the CSRB. The testing of these systems will begin tomorrow.
  • The damaged case work has been removed from the Gross Anatomy Lab and the Morgue.
  • The temporary fire pump for the Dental School arrived today. Installation will begin shortly.