  • NOTICE: In order to connect the replacement air conditioning unit that serves the 2nd floor of the MEB, a chilled water outage will be needed. This outage will take place on Saturday, July 22nd from 5:00 AM until 5:00 PM. This air conditioning outage will affect the entire MEB for the 12 hour duration of the planned work.
  • The contractor making repairs in the MEB Lecture Rooms is beginning to run the electrical and network wiring to the installed pedestals and table tops in Lecture Room B. As part of this task, they are coordinating the routing of the network cabling to the cabinets and securing them.
  • Another contractor responsible for the presentation equipment is wiring the new projectors that were installed in Lecture Room B yesterday.
  • In Lecture Room A, the acoustic wallpaper is being installed.
  • At 1542 Tulane Ave., the environmental remediation contractor is working to complete the cleaning on the first floor and in the basement.