Louisiana State University Health Sciences Center Administration & Finance
 

Monday, October 09, 2006

  • The elevator contractor at the Dental School has installed the control panels for the #3 elevator and is wiring the switches & controls to the contacts in the panels.  The contractor has also removed the basement elevator (exterior) doors of elevator #3 so they can be replaced. 
  • Student Parking Lot Lighting Project: The electrical conduits and wires have been run on the S. Prieur St. side of the lot and the trench has been backfilled.   
    • The contractor is now making the trench on the Bertrand St. side of the lot. 
    • The new aluminum light poles have been ordered and should be delivered within the next 2-3 weeks.  
    • Timber piles will be used to support the concrete footings for the new light poles.  Piles will begin to be driven tomorrow.
  • The elevator doors on the elevator that leads to the walkway by Stanislaus Hall have been replaced.