Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, December 06, 2006

  • The Dental School contractor finished the installation of the support braces and brackets for the new pipes connected to the temporary chillers in the Power Plant. 
  • LSUHSC Facility Services personnel removed more of the damaged chairs from the Dental Clinic Building. 
  • A leak was discovered on the 7th floor of the Dental Clinic Building ; Room 7401, at the east wall over the counter top. 
  • At Student Parking Lot #2, the new light fixtures continue to be installed.  The light pole bases are complete and have been painted.  Gravel is being spread in the areas where the trenches had been dug.