Tuesday, January 23, 2007· The subcontractor started changing the control valves for the re-heat coils in the Dental Clinic Building . · All of the dehumidifiers have been removed from the Dental Clinic and Admin buildings. Some damage occurred to the walkway and the ramp during this process. o Black granite tiles on the walkway were broken and the ramp was bent because of the weight of the fork lift and units. We'll pursue compensation from the contractor. · The final parts have been installed on the three air compressors in the Power Plant. They are now on line. · The insulation subcontractor measured the steam line and condensate return lines in preparation for the re-insulation process. ·
Work continues on the installation of the sump
pumps in the basement at o Mechanical Insulation is here preparing to insulate the chilled water pipes in the basement. o The contractor is installing starters for pumps, and pulling wire for lighting in the basement. o They also are running conduit for the transfer switches and for the transformer that will supply power to the elevators in the building. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |