Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, January 30, 2007

  • The emergency, truck mounted chiller that had served the Dental School Clinic and Admin buildings until the temporary chiller repairs were made was removed from the site today. 
  • The Dental School elevator contractor continued to make progress in completing their repairs to the freight elevator. 
  • The electrical contractor is continuing work on both the replacement of the motor control center and the initial repairs to support the restoration of telecommunications services at the Dental School .
  • The 1542 Tulane Ave. contractor is continuing to install new electrical panels in the basement. They also started pulling wire for the new transfer switch and transformer.
  • The mechanical subcontractor is still removing the old piping for the basement sump pumps at 1542 Tulane.
    • The chilled water pipe insulation project continued today.   
    • Elevator repairs are ongoing.