Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, February 21, 2007

  • The installation of the motor control center at the Dental School Power Plant is approximately 75% complete.  Minor wiring remains to be done. 
    • Three sections of the old motor control center have been removed and the contractor has started disassembling the largest unit so that it can be removed. 
  • The contractor hired to assist in removing ceiling tiles from the Dental School buildings has finished with the removal of the tiles in the Clinic Building. 
    • They are cleaning and dusting the areas in which tiles have been removed.
    • Only the ceiling in one of the small auditoriums in the Administration Building is left to be removed.
  • The Dental School elevator contractor is working on the passenger elevators in the Administration Building . 
  • The 1542 Tulane Ave. contractor continues his work on installing electrical panels and lighting in basement.
    • The insulation contractor is progressing on the insulation of the chilled water pipes.
  • The installation of the new floor tile in the MEB atrium continues.