Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, February 27, 2007

  • The 110 volt power supply was connected to the chemical treatment station in the Dental School Power Plant today. 
  • The contractor completed the replacement of the 1st of four electrical panels in the Dental Administration building. 
    • Upon completion, the resumed work in the 5th floor telecommunications room. 
  • The elevator contractor continues to work on the elevators in the Clinic Building on the 1st floor. 
  • The architects came on site to assess how the new 2 x 2 ceiling grid will be installed in the Clinic and Administration buildings, and how the new grid will impact on the existing sprinkler system and the placement of the HVAC vents. 
  • The contractor working at 1542 Tulane Ave. received some electrical cables for the switch gear located on the fourth floor. 
    • They now have most of the lights in the basement installed and in service. 
  • The project to insulate the new pipes in the 1542 Tulane Ave. basement continues.
    • The work is progressing well on the chilled water pipes.
    • The insulation of the steam lines began today. 
  • Installation of the new flooring in and around the MEB atrium continued today. 
    • Work on installing the hand rails is now underway.