Wednesday, March 21, 2007
- The Section 406 Hazard Mitigation proposal for protection of the campus elevators has been forwarded to FEMA by the Hazard Mitigation specialist from the State Public Assistance Office.
- Schindler continues to make progress on the repairs to the Dental School elevators. They were fine tuning Elevator #3 on the 8th floor of the Clinic Building today.
- The 1542 Tulane Ave. contractor continues their work on electrical panels and the drives in the basement, while the elevator contractor was progressing with making repairs to the building elevators.
- The pipe insulation project in the basement of 1542 Tulane Ave. is also still in progress.
|