Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, March 06, 2007

  • The Dental School contractor installed a replacement electrical panel on the 4th floor, Auditorium C in the Administration Building.
    • There is one more electrical panel to be installed in the Clinic Building.  The cellular telephone site on the roof will be affected when the existing panel is disconnected.
  • The architect was on site to survey the ceiling area of the 1st floor of the Clinic Building to finalize the new design for the ceiling. 
  • BellSouth examined Room 2315-A as they plan for the provision of a phone line for the building fire alarm system and of 4 separate telephone lines for the elevators in the Clinic Building. 
  • The 1542 Tulane Ave. contractor is installing the variable frequency drives for the chilled pumps.
  • The mechanical sub-contractor continued to work on the installation of the final sump pump in the basement and running the pipe to the city drain.
  • The project to insulate the new pipes in the 1542 Tulane Ave. basement is also proceeding.