Dental School : 

  • Zimmer completed the carpet removal on the 5th floor of the Clinic Building and started working on the 6th floor.
  • Boe-Tel began installing the new cable trays above the ceilings on 2nd and 3rd floors of the Clinic Building .  This work is part of the project to upgrade the network infrastructure prior to the return of the School to the campus.
  • Adco serviced the temporary boiler behind the Power House. 
  • AT&T and ADC worked together installing new equipment and software in Room 5312 as part of restoring telephone service to the buildings.
    • ADC installed a power shelf for the phone equipment that will work with the AT&T equipment.

1542 Tulane Ave. :

  • Arc Mechanical continued removing the damaged air compressors and pumps from the basement.
  • Stratos Elevator is still working on the safeties for Elevator #3. 
  • Ordes Electrical continued working on the air handling unit power and related control panels in basement. 
    • They are replacing flood damaged, cloth insulated wiring that was in the basement.