Dental School :

  • Zimmer has 90% of the ceiling tile grid removed from the 4th floor of the Administration Building and all of the grid removed from the 4th floor of the Clinic Building. 
  • The elevator contractor received a large shipment of motors and equipment for the elevators in the Administration Building . 
  • LSUHSC Animal Care staff with the help from Facility Services personnel started removing the old equipment and cages that were stored next to the fence in the parking lot.

 1542 Tulane:

  • Ordes Electrical continues to work on running a 4 inch conduit to the electrical vault to accommodate the additional switch gear that is on order. 
  • Stratos Elevators continued working on additional repairs to the cab of Elevator #3.
  • Arc Mechanical is making repairs to the steam station under an existing contract with LSUHSC.

 Elevator Interiors:

  • LSUHSC is undertaking some repairs and enhancements to the interiors of selected building elevators.  This work is not generally storm related.
  • Schindler will begin working on the interior repairs of the C tower elevator in the Residence Hall.  This work will take approximately 8 weeks.
  • They are also doing interior repairs to Elevator #3 in the Nursing/Allied Health Building while this particular elevator is down for mechanical repairs.