Friday, May 11, 2007

Dental School :

  • Zimmer started their work on the remediation at the first floor and will continue working their way to the top floors.
  • C&R Network continues to make the standard network drops to the offices on the fifth floor Clinic Building .
  • Boe-Tel continued the installation of the cable trays on the 6th floor and began on the 7th.
  • Bell South has pulled in wire to the basement in the Clinic and will feed that same wire to the basement of the Admin Building .
  • AT&T installed software cards that will bring in 95 phone lines to the equipment that ADS installed.
  • Computer services moved some data equipment up to room 5312.
  • G&M Cable installed 25 lines in room 5312 and 2 lines to the fire alarm in room but they found a problem in the closet in room 5322 that is canceling the dial tone.

1542 Tulane Ave.:

  • Ordes Electrical is installing disconnect panels for main power to the 4th floor.
  • Stratos Elevators is still installing and testing safeties to the #3 elevator.

MEB Cafeteria:

  • The cafeteria project started late this afternoon with the demolition of the ceiling and building of the construction wall.