Dental School :

  • Pflueger installed small switchgear on the 2nd level of the Power Plant to service the cooling tower.
    • They installed additional indicator lights on the motor control center and serviced several fuses that were blown. 
  • Zimmer continues working 24 hours a day on the remediation and duct cleaning project.  They are currently focusing on the Clinic Building. 
    • We are waiting for the sampling results in the three stairwells. 
    • The stairwell that passed has been coated with the antimicrobial paint as required by the contract.
    • Clinic 1st floor - The duct cleaning and sealing, as well as the area cleaning, is complete. 
    • Clinic 2nd floor - The duct cleaning is complete and they are doing the wipe down of all of the surfaces throughout the floor.
    • Clinic 3rd & 4th floors - The ducts are in the process of being cleaned. 
    • Clinic 5th floor - Individual items are being cleaned and boxed. 
  • The demolition work in the 4th floor Administration Building auditoriums (A & B) continues.  
  • Boe-Tel is working on the 7th floor of the Clinic Building installing new cable trays. 
    • They are installing wire mold and jacks on the 2nd and 3rd floors of the Administration Building. 
    • They are completing similar work on 5th floor of the Clinic Building.
  • C&R Network is working on the 3rd floor of the Clinic Building.  They are pulling cable to the marked locations in the clinic teaching bays.
  • BellSouth/AT&T installed a telephone line for the fire alarm service; running the line from the Room 5312 to Room 2315 where the fire alarm panel is located in the Clinic Building.

1542 Tulane Ave.:

  • Stratos Elevator continues installing communications cable for Elevator #3.
  • Arc Mechanical continues to remove the damaged air compressors and pumps from the basement.
  • Ordes Electrical continues pulling wire to the new breaker panels in the basement.

Cafeteria Project:

  • Demolition of the hallway wall is nearing completion.

Downtown Landscaping Project:

  • The contractor has started installing empty conduit under the sidewalks and driveways to allow completion of the irrigation systems.