Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, May 24, 2007

Dental School :

  • Zimmer started the pre-cleaning and wipe down in the rooms of the 6th floor of the Clinic Building.
    • The duct cleaning continues on the 5th floor.
    • The follow up cleaning of the 4th and 5th floors continues.
  • Boe Tel pulled network cable on the 6th and 7th floors.  They continued making the connections on the 4th and 5th floors.
  • Schindler worked on the two elevators in the Clinic Building that experienced outages.
    • They continued to work on the three elevators in the penthouse of the Administration Building .

1542 Tulane Ave. :

  • Ordes Electrical is running wire for the pump breaker panel in the basement.
  • Arc Mechanical is installing the new steam condensate pumps.  
  • Stratos Elevator is installing the travel cable for Elevator #3.

Cafeteria Renovation:

  • The demolition of the old terrazzo floor continues.