Louisiana State University Health Sciences Center Administration & Finance
 

Friday, May 25, 2007

Dental School :

  • GVA coordinated a walk thru for the contractor involved in various change orders and the Central Sterilization project so that mechanical and electrical questions could be clarified. 
  • Boe-Tel continues to work on pulling network cable and making the connections on the 4th, 5th, 6th and 7th floors of the Clinic Building.
  • Zimmer continues work on the remediation project in both the Administration and Clinic Buildings .   
  • Schindler connected the emergency telephone lines to Clinic Building Elevators #1 and #2 this morning.  This will need to be verified by the State Elevator Inspector and LSUHSC.  Once this is verified, the elevators should be certified for normal use.
  • The electrical contractor examined at the lighting locations for the parking lots and the location of the power source that will service the parking lot lights. 

1542 Tulane Ave. :

  • Stratos Elevators continued their work to install the travel cable for Elevator #3. 
  • Ordes Electrical continues to connect the wiring to the 480V breaker panel in the basement.